SBN | Facilities Construction Department, MTFC Training Center Roof Replacement & Water Damage Repairs

Location: Washington
Posted: Jan 21, 2026
Due: Feb 3, 2026
Agency: The Confederated Tribes of the Colville Reservation
Type of Government: State & Local
Category:
  • U - Education and Training Services
  • Z - Maintenance, Repair or Alteration of Real Property
Publication URL: To access bid details, please log in.

SBN | Facilities Construction Department, MTFC Training Center Roof Replacement & Water Damage Repairs | Closing Date Feb 3, 2026 PDF

Attachment Preview

Confederated Tribes of the Colville Reservation
P.O. Box 150 Nespelem, WA 99155 (509) 634-2200
Sealed Bid Notice
MTFC Training Center Roof Replacement &
Water Damage Repairs
1.01 Description
The Confederated Tribes of the Colville Reservation (Colville Tribes) Facilities Construction
Department is seeking Construction firms (Contractor) registered in the state of Washington to
provide roof replacement and water damage repair services for the Mt Tolman Training Center
(MTFC) building located at 90 Mt. Tolman Rd., Keller, WA. The services provided must meet
objectives as described herein.
The Colville Tribes business hours are Monday thru Thursday 7:00 a.m. to 5:30 p.m. excluding
Saturdays, Sundays, Tribal and Federal holidays.
1.02 Introduction
The Confederated Tribes of the Colville Reservation is a Sovereign Nation. Presidential Executive
Order established the Colville Indian Reservation in 1872, with a land base of 1.4 million acres
located in North Central Washington State. The Administrative Headquarters are located at the
Lucy Covington Government Center, 21 Colville Street, Nespelem, WA 99155.
1.03 Purpose of Sealed Bid
The purpose of this Sealed Bid Notice is to solicit proposals from qualified Contractors and
establish a Contract for roof replacement and water damage repair for the MTFC Training Center
at 90 Mt. Tolman Road Keller, WA as identified in the scope of work. The instructions on Bid
preparation, required documents, eligibility requirements and evaluation criteria are provided
herein.
1.04 General Scope of Work
The Contractor shall provide all permits; meet all regulatory requirements and all construction
activities necessary to perform a complete job of limited renovation of the approximately 3,500sf
MTFC Training Center building located at 90 Mt. Tolman Road Keller, WA. The required
construction activities include but not limited to removing existing metal roof, install plywood
sheeting, underlayment and install new 26-gauge metal roofing and flashing. Install new cove base,
patch and repair drywall, install access panel for water shut off valve, replace damaged ceiling
tiles, paint interior, new casework and countertops in the kitchen. Tribal Employment Rights
Ordinance, TOSHA and Tribal Solid Waste Disposal requirements apply. Before proceeding with
the work, Contractor will have in place all required permits from each applicable regulating
authority.
1
Mt. Tolman Training Center – Construction RFP
1.05 Response Format
Contractor proposals must be submitted in the format specified below. Contractors that deviate
from this format may be deemed non-responsive.
1.06 Completeness of Proposal
The Contractor must submit a completed Bid form signed by a Contractor representative
authorized to bind the proposing firm contractually. The Contractor must identify on the form any
exceptions the Contractor takes to the Tribes Sealed Bid Proposal, or declare that there are no
exceptions taken.
1.07 Proposal Response Date and Location
Proposals must be submitted to the Confederated Tribes Community Facility Manager no later
than 03:00 pm February 17, 2026 at which time the bids will be opened. The FedEx delivery
address is Facilities Construction Manager, Colville Confederated Tribes, 21 Lakes St. Nespelem,
WA 99155; hand delivery at the Facilities Construction Manager Office, Yellow Cloud Building,
28 Lakes St., Agency Campus, 2 mi. south of Nespelem, WA 99155, and or USPS PO Box 150,
Nespelem, WA 99155. All Bids and accompanying documentation will become the property of
the Colville Tribes and will not be returned. Contractors accept all risk of late delivery of mailed
proposal regardless of fault.
A public bid opening will be held virtually on Google Meet on Tuesday, February 17, 2026, 3:30
pm. Google Meet joining info:
Video call link: https://meet.google.com/mhx-dork-cob
Or dial: (US) +1 574-213-8477 PIN: 339 264 999#
1.08 Proposal Submission
Submit 1 original signed Bid form and accompanying forms and or documentation in a sealed
envelope titled Facilities Construction Manager – “Sealed Bid MTFC Training Center” February
17, 2026, 2026 03:00 pm that has clear markings of the responding business name and address.
1.09 Site Visitations
A site visit is required and will be held on February 3, 2026 at 02:00 pm. A site visit can be
scheduled by contacting Theresa Desautel, CCT Facilities Construction Manager at (509) 634-
9967. By submitting his/her proposal, the Contractor acknowledges that he/she has satisfied
him/herself as to the nature and locations of the work.
1.10 Contractor’s Cost to Develop Proposals
Costs for developing proposals in response to the Bid Notice are entirely the obligation of the
Contractor and shall not be chargeable in any manner to the Colville Tribes.
1.11 Indian Preference
Notice is hereby given that the Confederated Tribes of the Colville Reservation has in force Title
10 Employment and Contracting; Chapter 10-1 Tribal Employment Rights Ordinance (TERO),
and Chapter 10-3 Indian Preference in Contracting, covering but not limited to Indian employment,
Training, contracting and subcontracting. Bidders are directed to contact the Colville Tribal TERO
department to obtain complete information regarding compliance requirements and
2
Mt. Tolman Training Center – Construction RFP
responsibilities under the law. It is also incumbent on the contractor and/or subcontractor to insure
all compliance requirements are met prior to commencing work. It is also advisable for covered
entities to be aware of the TERO requirements for certification as an Indian firm, sanctions for
non-compliance and the appeal process. The Colville Tribal TERO department can be reached by
calling (509) 634-2735
Section 2 TERMS AND CONDITIONS
2.01 Questions Regarding the Bid Notice
Requests for interpretation/clarification of the Bid Notice document must be made in writing and
submitted to Mrs. Theresa Desautel, the Facilities Construction Manager, by e-mail
theresa.desautel.adm@colvilletribes.com. Unauthorized contact with other tribal employees
regarding this Bid Notice may result in disqualification. All oral communications will be
considered unofficial and non-binding on the Colville Tribes. Allow seven (7) days for processing
written questions received. All questions must be submitted no later than February 10, 2026 at
05:30 pm.
2,02 Bid Notice Amendments
The Colville Tribes reserves the right to request any respondent clarify its proposal or to supply
any additional material deemed necessary to assist in the evaluation of the Bid.
The Colville Tribes reserves the right to change the Bid Notice schedule or issue amendments to
the Bid Notice at any time. The Colville Tribes also reserves the right to cancel or reissue the Bid
Notice. All such addenda must be acknowledged and will become part of the Bid Notice.
2.03 Withdrawal of Proposal
Provided notification is received in writing, proposals may be withdrawn at any time prior to the
proposal response due date and time specified. Proposals cannot be changed or withdrawn after
the time designated for receipt.
2.04 Rejection of Proposals
The Colville Tribes reserves the right to reject any or all proposals, to waive any minor
informalities or irregularities contained in any proposal, and to accept any proposal deemed to be
in the best interest of the Colville Tribes.
2.05 Proposal Validity Period
Submission of a proposal will signify the Contractor’s agreement that its proposal and the content
thereof are valid for 120 days following the proposal response deadline unless otherwise agreed to
in writing by both parties. The proposal will become part of the Contract negotiated between the
Colville Tribes and the successful Contractor.
2.06 Proposal Signatures
A representative authorized to obligate the firm must sign the proposal, with the Contractor’s
address and telephone information provided. Unsigned proposals will not be considered.
3
Mt. Tolman Training Center – Construction RFP
2.07 Insurance Requirements
The Colville Tribes will require the selected Contractor to comply with the insurance requirements
as listed in the Bid Notice; see Attachment “A”. Questions regarding insurance requirements can
be discussed with the Tribes Risk Management Office, (509) 634-2447.
2.08 Equal Opportunity Requirements
The Colville Tribes is an equal opportunity employer and requires all Contractors to comply with
policies and regulations concerning equal opportunity. The contractor, in the performance of the
Contract, agrees not to discriminate in its employment because of the employees or applicant’s
race, religion, national origin, ancestry, sex, age, or physical handicap.
2.09 Other Compliance Requirements
In addition to the nondiscrimination and affirmative action compliance requirements previously
listed, the Contractor awarded a Contract shall comply with Tribal, Federal, State and local laws,
statutes and ordinances relatively to the execution of the work. This requirement includes, but is
not limited to, protection of public and employee safety and health; environmental protection;
waste reduction and recycling; the protection of natural resources; permits; fees; taxes; and similar
subject.
2.10 Ownership of Documents
Any reports, studies, conclusions and summaries prepared by the Contractor shall become the
property of the Colville Tribes.
2.11 Confidentiality of Information
All information and data furnished to the Contractor by the Colville Tribes and all other documents
to which the Contractor’s employees have access during the term of the Contract, shall be treated
as confidential to the Colville Tribes. Any oral or written disclosure to unauthorized individuals
is prohibited.
2.12 Hold Harmless
The Contractor shall hold harmless, defend, and indemnify the Colville Tribes and the Tribes
officers, agents, and employees against any liability that may be imposed upon them by reason of
the Contractor’s failure to provide worker’s compensation coverage or liability coverage.
2.13 Safety
All applicable regulations pertaining to safety, the Contractor shall strictly adhere to; including
Tribal Occupational Safety and Health Act (TOSHA) standards and regulations and OSHA 29CFR
1910.1001 & 1926.1101. Particular care shall be exercised in connection with the operation of
vehicles and other equipment on the site.
2.14 TERO
The Colville Tribal Employment Rights Ordinance (TERO), including the 5% TERO fee shall
apply to the Contract to the extent any of the work to be performed under the Contract is on or
near the Colville Indian Reservation. No work will take place until a TERO Utilization Plan has
been signed, approved, and filed with the TERO office. The 5% TERO fee applies to all contracts
4
Mt. Tolman Training Center – Construction RFP
over $5,000.00 where the contractor is not a preference-certified entity.
2.15 Bonds
Bid proposals shall be accompanied by security in the amount of 5% of the total Bid amount on
forms provided by the Contractor surety. The successful Contractor will furnish Performance
Security and Labor and Material Security Bonds in the amount of 100% of the contract and will
be required before start of work.
The bonds will be from an AA rated surety acceptable to the Colville Tribes. If allowable and the
Colville Tribes chooses to select a Contractor that cannot provide bonding, then the Colville
Tribes will retain 20% of the contract price until verified that the Contractor has satisfied
all obligations in relation to the contract.
2.16 Liquidated Damages
For failure to complete the specified work in the identified contract time a penalty of $100.00 per
day will be assessed.
2.17 Davis Bacon Wages are Required for this Project
As this project is a federally funded project, the Davis Bacon Act does apply. Contractor will be
required to submit certified payrolls.
Section 3 REQUESTED SERVICES
3.01 Duration of Services
The Colville Tribes anticipates the service period for this work to be from approximately March
3, 2026 through July 1, 2026. The total duration of the Contract shall not exceed 120 days.
3.02 Information
The forms and required documentation referenced below must be submitted with the Contractor’s
proposal. Do not leave any space blank.
Financial and Credit Reference: Provide credit references that can verify the financial
standing of your company; or the most recently audited financial statement for your
company.
Contracting License: Provide a copy of your current Washington State Department of
L&I Contractor Registration.
TERO Certification: Provide a copy of the TERO certification of your firm (if
applicable).
Company Information: Complete Form # 1.
Client References: Complete Form # 2.
Certification Regarding Debarment: Complete Form #3.
5
Mt. Tolman Training Center – Construction RFP
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL
* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.