    Proposal No. 54-TJK-01-PR36058 1 June 24, 2026
    STATE OF NORTH CAROLINA
    DEPARTMENT OF TRANSPORTATION
    REQUEST FOR PROPOSAL
    DATE AND TIME OF BID OPENING: JULY 15, 2026 AT 2:00 P.M.
    BID PROPOSAL NO.: 54-TJK-01-PR36058
    WBS ELEMENT NOS.: VARIOUS
    COUNTIES: BERTIE, CAMDEN, CHOWAN, CURRITUCK, DARE, GATES,
    HERTFORD, HYDE, MARTIN, NORTHAMPTON,
    PASQUOTANK, PERQUIMANS, TYRRELL, AND
    WASHINGTON - DIVISION 1
    LOCATION: VARIOUS PRIMARY AND SECONDARY ROADS
    TYPE OF WORK: ON CALL ANNUAL SEEDING AND MULCHING
    DATE OF AVAILABILITY: SEPTEMBER 1, 2026
    COMPLETION DATE: AUGUST 31, 2027
    PRE-QUALIFICATION MANDATORY

    Proposal No. 54-TJK-01-PR36058 2 June 24, 2026
    PROPOSAL
    FOR THE CONSTRUCTION OF
    BID NO. 54-TJK-01-PR36058 IN BERTIE, CAMDEN, CHOWAN, CURRITUCK, DARE, GATES,
    HERTFORD, HYDE, MARTIN, NORTHAMPTON, PASQUOTANK, PERQUIMANS, TYRRELL, AND
    WASHINGTON COUNTIES - DIVISION 1, NORTH CAROLINA
    JUNE 24, 2026
    DEPARTMENT OF TRANSPORTATION,
    RALEIGH, NORTH CAROLINA
    The Bidder has carefully examined the location of the proposed work to be known as Contract No. 54-TJK-01-
    PR36058; has carefully examined the plans and specifications, which are acknowledged to be part of the proposal,
    the special provisions, the proposal, the form of contract, and the forms of contract payment bond and contract
    performance bond; and thoroughly understands the stipulations, requirements and provisions. The undersigned
    bidder agrees to bound upon his execution of the bid and subsequent award to him by the Department of
    Transportation in accordance with this proposal to provide the necessary contract payment bond and contract
    performance bond within fourteen days after the written notice of award is received by him. The undersigned Bidder
    further agrees to provide all necessary machinery, tools, labor, and other means of construction; and to do all the
    work and to furnish all materials, except as otherwise noted, necessary to perform and complete the said contract in
    accordance with the 2024 Standard Specifications for Roads and Structures by the dates(s) specified in the Project
    Special Provisions and in accordance with the requirements of the Engineer, and at the unit or lump sum prices, as
    the case may be, for the various items given on the sheets contained herein.
    The Bidder shall provide and furnish all the materials, machinery, implements, appliances and tools, and perform the
    work and required labor to construct and complete State Highway Contract No. 54-TJK-01-PR36058 for the unit or
    lump sum prices, as the case may be, bid by the Bidder in his bid and according to the proposal, plans, and
    specifications prepared by said Department, which proposal, plans, and specifications show the details covering this
    project, and hereby become a part of this contract.
    The published volume entitled North Carolina Department of Transportation, Raleigh, Standard Specifications for
    Roads and Structures, January 2024 with all amendments and supplements thereto, is by reference incorporated into
    and made a part of this contract; that, except as herein modified, all the construction and work included in this contract
    is to be done in accordance with the specifications contained in said volume, and amendments and supplements
    thereto, under the direction of the Engineer.
    If the proposal is accepted and the award is made, the contract is valid only when signed either by the Contract Officer
    or such other person as may be designated by the Secretary to sign for the Department of Transportation. The
    conditions and provisions herein cannot be changed except over the signature of the said Contract Officer or Division
    Engineer.
    The quantities shown in the itemized proposal for the project are considered to be approximate only and are given as
    the basis for comparison of bids. The Department of Transportation may increase or decrease the quantity of any
    item or portion of the work as may be deemed necessary or expedient.
    An increase or decrease in the quantity of an item will not be regarded as sufficient ground for an increase or decrease
    in the unit prices, nor in the time allowed for the completion of the work, except as provided for the contract.

    Proposal No. 54-TJK-01-PR36058 3 June 24, 2026
    TABLE OF CONTENTS
    PROJECT SPECIAL PROVISIONS - GENERAL PAGE NO.
    General 5
    Pre-Qualification 5
    General Contractors Licensing Requirements 5
    Contract Time for ID/IQ 6
    Work Order Assignment (Multiple Awards) for ID/IQ 6
    Mobilization and Liquidated Damages for ID/IQ 7
    Emergency Mobilization ID/IQ 7
    Renewal of Contract (CPI Price Adjustment) for ID/IQ 7
    Dispute Resolution Process for ID/IQ 8
    Intermediate Contract Time Number 1 and Liquidated Damages 8
    Intermediate Contract Time Number 2 and Liquidated Damages 8
    Intermediate Contract Time Number 3 and Liquidated Damages 8
    Non-Exclusive Contract 9
    Award of Contract 9
    Basis of Award 10
    Quantities Estimated 10
    Multi-Year Maintenance Contracts 10
    Bond Requirements 10
    Performance Guarantee 10
    Insurance 11
    Progress and Prosecution 11
    Traffic Control and Work Zone Safety 11
    Flaggers 12
    Safety Vests 12
    Prompt Payment 12
    Payment and Retainage 12
    Minority Business Enterprise and Women Business Enterprise 13
    PROJECT SPECIAL PROVISIONS - ROADWAY PAGE NO.
    Description 23
    Erosion Control 23
    Notification of Work 23
    Inspection of Work 23
    Stabilization Requirements 24
    Mobilization 24
    Seeding and Mulching 24
    Repair Seeding 30
    Permanent Soil Reinforcement Mat 30
    Safety 31
    Supervision by Contractor 31
    Equipment 31
    Miscellaneous 32
    STANDARD SPECIAL PROVISIONS PAGE NO.
    Availability of Funds - Termination of Contracts 33
    Authority of the Engineer 33
    Minimum Wages 33
    On-The-Job Training 34

    Proposal No. 54-TJK-01-PR36058 4 June 24, 2026
    Work Zone Signing 36
    NCDOT General Seed Specification for Seed Quality 36
    Plant and Pest Quarantines 38
    Bankruptcy 38
    Subletting of Contract 38
    Responsibility for Damage Claims 39
    Debarment Statement 39
    Default of Contract 39
    No Major Contract Items 39
    No Specialty Items 39
    Subsurface Information 39
    Utility Conflicts 39
    Traffic Signs & Mailboxes 39
    Driveways and Private Property 40
    Posted Weight Limits 40
    Cooperation between Contractors 40
    Cooperation with State Forces 40
    Outsourcing Outside the USA 40
    Title VI and Nondiscrimination 40
    INSTRUCTIONS TO BIDDERS PAGE NO.
    Preparation and Submission of Traditional Paper Bids 47
    Opening of Bids 48
    BID SUBMITTAL PACKAGE PAGE NO.
    Cover Sheet 1
    Contract Bid Form 2
    Contractor Information 3
    Federal Employer Identification Number 4
    List of MBE/WBE Subcontractors 5
    List of Equipment 6
    Contractor's Work Experience and References 7
    Execution of Bid Non-Collusion, Debarment and Gift Ban Certification 8
    Bid Submittal Package Checklist 16

    Proposal No. 54-TJK-01-PR36058 5 June 24, 2026
    PROJECT SPECIAL PROVISIONS - GENERAL
    GENERAL
    This contract is for miscellaneous erosion control work on primary and secondary roads in Bertie, Camden,
    Chowan, Currituck, Dare, Gates, Hertford, Hyde, Martin, Northampton, Pasquotank, Perquimans, Tyrrell, and
    Washington Counties in Division 1. The Contractor will also be responsible for matting, repair seeding,
    fertilization, and traffic control as directed by the Engineer. The Contractor is to provide all equipment, labor and
    material.
    All materials and workmanship shall be in accordance with the following:
    The Project Special Provisions, Project Standard Provisions, most current Standard Special Provisions, Manual of
    Uniform Traffic Control Devices (MUTCD), Provisions contained in the applicable Sections of the North Carolina
    Department of Transportation's 2024 Standard Specifications for Roads and Structures and Drawings contained in
    the applicable sections of the North Carolina Department of Transportation's 2024 Roadway Standard Drawings
    shall apply.
    The published volume entitled North Carolina Department of Transportation, Standard Specifications for Roads
    and Structures, with all amendments and supplements thereto, is by reference incorporated into and made a part of
    this contract; that, except as herein modified, all the construction and work included in the contract is to be done in
    accordance with the specifications contained in said volume, and amendments and supplements thereto, under the
    direction of the Engineer.
    The Contractor shall keep himself fully informed of all Federal, State, and local laws, ordinances, and regulations,
    and shall comply with the provisions of Section 107 of the Standard Specifications.
    These manuals may be found at the following websites: http://mutcd.fhwa.dot.gov/ and
    https://connect.ncdot.gov/resources/Specifications/Pages/2024-Specifications-and-Special-Provisions.aspx
    PRE-QUALIFICATION
    Any prospective bidder that wishes to bid as a prime contractor on this project shall be prequalified as a "Bidder" or
    "PO Prime Contractor".
    Prospective bidders shall obtain prequalification approval at least two (2) business days prior to any letting in which
    they intend to submit a bid. It is recommended that the prospective bidder file all required statements and
    documents with the State Prequalifications Engineer no less than four (4) weeks before a given letting. A bid shall
    not be opened unless all prequalification requirements have been met by the bidder and have been found acceptable
    by the Engineer.
    Information regarding prequalification can be found at:
    https://connect.ncdot.gov/business/Prequal/Pages/default.aspx.
    Prior to performing the work, the prime contractor and/or subcontractor(s) shall be prequalified in the work code(s)
    which are identified as work items in the prime contractor's construction progress schedule that they will complete
    themselves. Any contractor identified as working outside their expertise may be considered in default of contract.
    GENERAL CONTRACTORS LICENSING REQUIREMENTS
    A General Contractors license is not required to bid or perform work on this project.

    Proposal No. 54-TJK-01-PR36058 6 June 24, 2026
    INTERESTED PARTIES LIST NOT REQUIRED:
    (6-21-22)(Rev. 2-20-24) 102 SP1 G02
    Revise the Standard Specifications as follows:
    The Interested Parties List sign up process is not applicable to this contract.
    Page 1-13, Article 102-3 PROPOSALS AND INTERESTED PARTIES LIST, lines 12-15, delete the first
    paragraph.
    Page 1-14, Article 102-8 PREPARATION AND SUBMISSION OF BIDS, lines 43-44, delete the first sentence
    of the first paragraph.
    CONTRACT TIME FOR ID/IQ:
    (2-15-22)(Rev. 4-15-25) 108 SP1 G11
    The date of availability for this contract is September 1, 2026.
    The completion date for this contract is August 31, 2027..
    Except where otherwise provided by the contract, observation periods required by the contract will not be a part of
    the work to be completed by the completion date and/or intermediate contract times stated in the contract. The
    acceptable completion of the observation periods that extend beyond the final completion date shall be a part of the
    work covered by the performance and payment bonds.
    Work shall be accomplished in a continuous manner once the contractor begins.
    The liquidated damages for this contract will be assessed per the Mobilization and Liquidated Damages for ID/IQ
    provision located elsewhere in this contract.
    WORK ORDER ASSIGNMENT (MULTIPLE AWARDS) FOR ID/IQ:
    (2-15-22)(Rev. 4-19-22) SPD 01-800B
    Work orders will be assigned based on the lowest work order cost for the line items and estimated quantities
    necessary to complete the work order. Unit prices from each awarded contractor's bid will be used to determine the
    lowest cost for each work order. The assigned Contractor shall respond to the work order assignment with the
    anticipated start date, within three working days of notification unless noted otherwise. Failure on the part of the
    Contractor to reply within the specified time frame may be received as a rejection of the work order. If the
    Contractor with the lowest work order cost cannot complete the work within the time specified in the assignment,
    the Engineer may contact the Contractor with the next lowest work order cost. If that Contractor can complete the
    work within the time specified in the assignment, then the work order will be assigned to that contractor. If not,
    assignment of work order will continue in order of work order cost until all awarded Contractors have had a chance
    to accept the terms of the assignment.
    For federal ID/IQ contracts, all work orders will be assigned via the Work Order Assignment form (Form IDIQ-
    1MA), and the Contractor is required to formally respond in writing for federal work orders within three working
    days, unless noted otherwise. The Work Order Assignment form will also be used for any state ID/IQ contract in
    which the estimated work order cost meets the threshold for Performance and Payment Bonds in accordance with
    the Bonding Requirements for ID/IQ provision found elsewhere in this contract. For state ID/IQ contracts in which
    the work order assignment doesn't meet the threshold for bonds, the Department has the option to use the Work
    Order Assignment Form or other methods for work order assignments as agreed upon by the Engineer and
    Contractor.
    The Contractor shall be required to prosecute the work in a continuous and uninterrupted manner from the time
    they begin the work until completion and final acceptance of the work order. Multiple failures of the Contractor to
    mobilize and begin work on the work order within the agreed upon time frame or failure to complete the work

    Work Order Value Liquidated Damages (per calendar day)
    $0 - $100K $100.00
    $100K - $200K $250.00
    $200K - $300K $500.00
    $300K - $500K $600.00
    $500K - $1M $700.00
    $1M - $2M $850.00

    Proposal No. 54-TJK-01-PR36058 7 June 24, 2026
    within the given time frame may result in the Contractor being excluded from future work on this contract in
    accordance with the Standard Specifications.
    MOBILIZATION AND LIQUIDATED DAMAGES FOR ID/IQ:
    (2-15-22) SPD 01-820
    The Contractor shall mobilize to each location he is required to perform work.
    The Contractor will be provided a Work Order Assignment for each project with location(s), estimated quantities,
    and liquidated damages unless waived by the Engineer. Notification will be verbal followed by a faxed or emailed
    signed Work Order Assignment. There will be no minimum quantities for any line item associated with a particular
    mobilization. The Contractor shall complete the work identified on each Work Order Assignment.
    The Contractor shall mobilize and complete the work within the time specified on the Work Order Assignment.
    Failure to complete the work by the completion date may result in the application of liquidated damages.
    Liquidated damage amounts will be based on the work order estimate and the liquidated damage table below.
    Liquidated Damages (per calendar
    Work Order Value
    day)
    $0 - $100K $100.00
    $100K - $200K $250.00
    $200K - $300K $500.00
    $300K - $500K $600.00
    $500K - $1M $700.00
    $1M - $2M $850.00
    EMERGENCY MOBILIZATION FOR ID/IQ:
    Emergency mobilization will not be utilized in this contract. No payment will be made for this item.
    RENEWAL OF CONTRACT (CPI PRICE ADJUSTMENT) FOR ID/IQ:
    (2-15-22)(Rev. 9-19-23) SPD 01-840
    The Contractor shall submit a bid for one year. At the option of the Department, this contract may be extended for
    two (2) additional periods of one year each (maximum (3) three years total). Each year shall have a limit of One
    Million Dollars ($1,000,000).
    The compensation payable to the contractor shall be fixed for the first twelve months of this contract. However,
    upon an application of renewal of the contract, or thirty days prior to the end of each contract period, the renewal
    contract may be adjusted to reflect the adjustment in the Consumer Price Index over the latest twelve month period
    as published by the US Bureau of Labor and Statistics at http://www.bls.gov/cpi to be applied to new work order
    assignments. The Consumer Price Index for All Urban Consumers (CPI-U), US City Average, All Items, 1982-
    84=100, not seasonally adjusted will be used. If the amount of the requested adjustment is more than ten percent,
    the Department of Transportation reserves the right to cancel this contract.
    CPI adjustment values can be determined using the calculator on the NCDOT Construction website.
    This price escalation method will not be applied to items of work that are separately covered under commodity
    price escalation clauses. No other changes in the terms, conditions, etc. of this contract will be made when an
    extension to the contract is implemented. The Engineer will notify the Contractor in writing 60 days before the
    end of the contract period if the contract may be extended. The Contractor must notify the Engineer in writing
    within 15 calendar days of his acceptance or rejection of this offer. Failure on the part of the Contractor to reply
    will be received as a rejection of contract extension.

    Proposal No. 54-TJK-01-PR36058 8 June 24, 2026
    DISPUTE RESOLUTION PROCESS FOR ID/IQ:
    (2-15-22)(Rev. 1-16-24) SPD 01-850
    If a question should arise on the contract or assignment of a work order, the contractor should notify the Engineer
    noted on the assignment documentation or the Division Engineer within 48 hours after the scheduled time of bid
    opening or work order assignment. The following should be included in the notification if applicable:
    (A) the contract for which bids were solicited;
    (B) the particular law, regulation, or contract specification violated;
    (C) a detailed description of the alleged violation; and
    (D) any other information deemed to be relevant.
    Once the initial evaluation has been completed, the contractor may be asked to attend a meeting for further
    discussion and clarification.
    Once a determination has been made, the contractor will be notified of the decision by the Division Engineer. If the
    decision does not meet the satisfaction of the contractor, they have 24 hours from the Division Engineer's
    notification to elevate the dispute to the Chief Engineer. The Chief Engineer will make the final decision and will
    not be subject to further review by NCDOT.
    INTERMEDIATE CONTRACT TIME NUMBER 1 AND LIQUIDATED DAMAGES
    The Contractor shall perform seeding and mulching operations on major slopes and areas determined to abut High
    Quality Water within the timeframes described below.
    The date of availability for this intermediate contract time will be the day the Contractor receives notification
    to perform the work. The Division Roadside Environmental Engineer or their representative will issue a work
    request to the Contractor, notifying them of work needed at the various locations by the by telephone, fax, or email.
    The completion date for this intermediate contract time will be five (5) calendar days after the date of
    availability.
    Liquidated damages for this contract time are Five Hundred Dollars ($500) per day for each calendar day the
    Contractor fails to complete the work beyond the completion date.
    INTERMEDIATE CONTRACT TIME NUMBER 2 AND LIQUIDATED DAMAGES
    The Contractor shall perform seeding and mulching operations on minor slopes within the timeframes described
    below.
    The date of availability for this intermediate contract time will be the day the Contractor receives notification
    to perform the work. The Division Roadside Environmental Engineer or their representative will issue a work
    request to the Contractor, notifying them of work needed at the various locations by the by telephone, fax, or email.
    The completion date for this intermediate contract time will be ten (10) calendar days after the date of
    availability.
    Liquidated damages for this contract time are Five Hundred Dollars ($500) per day for each calendar day the
    Contractor fails to complete the work beyond the completion date.
    The Contractor's operations are restricted to daylight hours. No work shall be performed on Saturdays, Sundays,
    and Legal State holidays unless by written consent of Engineer. Work shall only be performed when weather and
    visibility conditions allow safe operations.
    INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES
    MONDAY-THURSDAY FROM THIRTY (30) MINUTES BEFORE SUNSET TO THIRTY (30) MINUTES
    AFTER SUNRISE THE FOLLOWING DAY

    Proposal No. 54-TJK-01-PR36058 9 June 24, 2026
    FRIDAY FROM THIRTY (30) MINUTES BEFORE SUNSET TO THIRTY (30) MINUTES AFTER
    SUNRISE THE FOLLOWING MONDAY
    The Contractor shall not work within the roadway or associated right of way on ANY STATE MAINTAINED
    ROUTE, detain and /or alter the traffic flow on or during holiday weekends, special events, or any other time when
    traffic is unusually heavy, including the following schedules:
    HOLIDAY AND HOLIDAY WEEKEND WORK RESTRICTIONS:
    1. For unexpected occurrence that creates unusually high traffic volumes, as directed by the Engineer.
    2. For New Year's Day, between the hours of 4:00 p.m. December 31st and 8:30 a.m. January 2nd. If New Year's
    Day is on a Friday, Saturday, Sunday or Monday, then until 8:30 a.m. the following Tuesday.
    3. For Martin Luther King, Jr. Day, between the hours of 4:00 p.m. Friday and 8:30 a.m. Tuesday.
    4. For Easter, between the hours of 4:00 p.m. Thursday and 8:30 a.m. Monday.
    5. For Memorial Day, between the hours of 4:00 p.m. Friday and 8:30 a.m. Tuesday.
    6. For Independence Day, between the hours of 4:00 p.m. the day before Independence Day and 8:30 a.m. the day
    after Independence Day.
    If Independence Day is on a Friday, Saturday, Sunday or Monday, then between the hours of 4:00 p.m. the
    Thursday before Independence Day and 8:30 a.m. the Tuesday after Independence Day.
    7. For Labor Day, between the hours of 4:00 p.m. Friday and 8:30 a.m. Tuesday.
    8. For Veteran's Day, between the hours of 4:00 p.m. Friday and 8:30 a.m. Tuesday.
    9. For Thanksgiving Day, between the hours of 4:00 p.m. Tuesday and 8:30 a.m. Monday.
    10. For Christmas, between the hours of 4:00 p.m. the Friday before the week of Christmas Day and 8:30 a.m. the
    following Tuesday after the week of Christmas Day.
    Holidays and holiday weekends shall include New Years, Easter, Memorial Day, Independence Day, Labor Day,
    Thanksgiving, and Christmas. The Contractor shall schedule his work so that work is not required during these
    periods, unless otherwise directed by the Engineer.
    Liquidated damages for this contract are Five Hundred Dollars ($500.00) per hour or portion thereof that the
    Contractor operates outside of the work hours as stated above.
    NON-EXCLUSIVE CONTRACT
    The Department may, as it deems to be in the best interest of the State and the Department of Transportation,
    execute more than one contract based on this proposal. The Contractor(s) understands and agrees, by signature on
    the Purchase Order Contract Bid Form, that this agreement does not constitute an exclusive contract. If awarded,
    the contracts will be executed with the lowest responsible bidders. The Department of Transportation reserves the
    right to make multiple awards for the services provided by this contract. Furthermore, the Department reserves the
    right to reject all bids received.
    AWARD OF CONTRACT
    (6-28-77)(Rev 2/16/2018) Z-6
    "The North Carolina Department of Transportation, in accordance with the provisions of Title VI of the Civil
    Rights Act of 1964 (78 Stat. 252) and the Regulations of the Department of Transportation (49 C.F.R., Part 21),
    issued pursuant to such act, hereby notifies all bidders that it will affirmatively insure that the contract entered into
    pursuant to this advertisement will be awarded to the lowest responsible bidder without discrimination on the
    ground of race, color, or national origin".

    Proposal No. 54-TJK-01-PR36058 10 June 24, 2026
    All eligible proposals will be evaluated and acceptance made of the bid judged in the discretion of the contracting
    agency to determine the lowest responsible bidder for the purpose intended. The Contracting Agency using its
    discretion, will determine whether a bidder is a "responsible" bidder. In determining whether a bidder is
    "responsible, the Contracting Agency will evaluate, the bid price, completeness and content of the bid, Bidder's
    related work experience, ability of the Bidder and staff to perform the services required, Bidder's past performance,
    references, and Bidder's financial stability. After opening bids and prior to award, the Contracting Agency may
    also seek supporting documentation prior to determining whether a bidder is a "responsible" bidder. No changes in
    bid price or price negotiations will be allowed after bids are opened and prior to an award. After the Contracting
    Agencies evaluation, the award of the contract, if awarded, will be made to the lowest responsible bidder. The
    lowest responsible bidder will be notified that his bid has been accepted and that he has been awarded the contract.
    Withdrawal of proposal will be allowed only under limited conditions. If a Bidder is awarded a contract, he/she
    will be expected to perform the work. Failure to perform may result in the Bidder being held in default of contract.
    In the event of default, the Department may, in its discretion, contact the next lowest responsible bidder to
    determine whether that next lowest responsible bidder is willing and able to complete the contract at its bid price.
    All awards are final and are not subject to further review. Any formal complaints concerning awards should be
    made in writing to the Engineer.
    BASIS OF AWARD
    Quantities for this work are estimated and are not guaranteed. Determination of the apparent low bidder will be made
    by extending the unit prices quoted on the Bid Proposal Form.
    Unit prices shall reflect actual costs; unbalanced bids may be rejected per the North Carolina Department of
    Transportation's Standard Specifications for Roads and Structures.
    QUANTITIES ESTIMATED
    The quantities shown on the itemized bid form are considered to be approximate only and are given as the basis for
    comparison of bids. For accounting purposes only a purchase order may contain quantity amounts and they SHALL
    NOT be construed as minimum quantities. Quantities shall be determined solely by the Department on an "as needed"
    basis. In the event of a conflict between any purchase orders and this proposal, this proposal shall control. An
    increase or decrease in quantities shall not be cause for an adjustment in unit prices.
    MULTI-YEAR MAINTENANCE CONTRACTS (ID/IQ):
    (4-20-21) (Rev. 4-19-22) SP1 G75
    This contract is a multi-year maintenance contract let pursuant to the provisions of N.C. General Statute 136-28.1(b).
    No minimum quantity of services is guaranteed to be awarded bidders under this contract. In accordance with N.C.
    General Statute 136-28.1(b), an award in a maintenance contract may be for an amount less but shall not exceed
    $5,000,000 per year. No payments in excess of this amount will be disbursed, in accordance with the Statute.
    BOND REQUIREMENTS
    The provisions of Articles 102-10 and 103-7 of the Standard Specifications for Roads and Structures are waived for
    this project. No bonds required.
    PERFORMANCE GUARANTEE
    Due to the nature of the contract, no retainage will be withheld. However, the Department reserves the right to
    withhold payment for a specific location until after successful completion of the work as verified by the final
    inspection of that location.

    This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
    Daily notification on new contract opportunities

    With GovernmentContracts, you can:

    • Find more opportunities and win more business
    • Receive daily alerts for all new bid opportunities
    • Get contract opportunities matched to your business
    ONE WEEK FREE TRIAL

    See also

    Bid Title: EAST WILLIAMS LOWER Substation Structural & Electric Materials Category: Utility Construction

    Town of Apex

    Bid Due: 8/21/2026

    D6D1.SBE.008 SBE Light Duty Maintenance Crew - Various Routes - Robeson D6D1.SBE.008 -

    Division of Highways

    Bid Due: 8/05/2026

    July 24, 2026 | Advertisements Advertisement for Bids - Avent Ferry Technology Center

    North Carolina State University

    Bid Due: 8/18/2026

    Follow Appalachian Ranger District Office and Work Center Janitorial Services Active Contract Opportunity

    AGRICULTURE, DEPARTMENT OF

    Bid Due: 8/20/2026

    * Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.