Invitation
The Buffalo Trace Covered Wooden Bridge Authority (BTCWBA) is requesting sealed bids for restoration of the historical Dover Covered Bridge in Mason County, near the City of Dover, Kentucky. Severe storms, flash flooding and age has caused the wooden bridge to sustain structural damage requiring rehabilitation of the bridge. Interested parties should submit to BTCWBA at 201 Government Street, Suite 300, PO Box 460, Maysville, KY 41056.
Scope of Work
BTCWBA will enter into an agreement with a contractor, licensed in the state of Kentucky. The contractor must have specific experience in the knowledge and workings of wooden covered bridges and follow the standards of the Secretary of the Interior for Rehabilitation and Restoration of Covered Bridges. Contractors shall submit a proposal including but not limited to documentation regarding their experience/credentials, and a detailed plan outlining how all construction phases will be completed including a project schedule. Work will be awarded based on lump sum low bid. Submitted Bid to include cost breakdown for each Phase. Bridge shall still be considered historic at the completion of the rehab per the minimum standards and requirements set by the Burlington Charter for the Preservation of Historic Covered Bridges.
Available Documents
Location of Bridge
Phase 1
Dismantle bridge as necessary
Add additional support
Raise bridge off abutments and correct chamber
Construct a support platform under the bridge
Phase 2
Dismantle lower cords, inspect, repair or replace as necessary
Inspect and repair end bracing
Repair top cord and roof framing as needed
Install new metal roof
Install floor beams and floor plank as needed
Reinstall/replace siding trim and portals as needed
Phase 3
Approach wing walls to be reworked and repaired
Approaches to be graded and paved to divert water as needed
Guard rails repaired /replaced as needed
Contractor shall remove all waste and materials not reused in bridge rehab; including but not limited to unused steel beams onsite
All original timbers and components of Dover Covered Bridge are to be reused where possible.
Documents to be submitted by the selected Contractor at the conclusion of the Project
Reserve Clause
BTCWBA reserves the right to reject any and all bids that do not meet the required specifications. Businesses performing work for BTCWBA shall comply with all applicable federal, state, and local laws and ordinances
For additional information, please contact Missy Hardy at 606/564-6894
Deadline for Submission of Bids
Please submit the sealed bid by 4:00 PM on July 25, 2025.