Project Description: The Contractor shall remove and dispose of approximately 1,917 linear feet of 8-inch concrete pipe and furnish and install approximately 1,917 linear feet of 10-inch C-900 DR-18 minimum pipe. The work will include, but not be limited to customer notification, bypass pumping, reinstatement of all laterals, testing, final CCTV inspection and all other task required perform
the work.
Additional work shall consist of re-channeling and epoxy or polyurethane lining of 16 manholes of various depths for corrosion prevention, removal and replacement of one 48-inch concrete manhole, replacement of existing manhole steps, and removal of two additional 48-inch manholes.
The Work shall be Physically Complete within 60 Working Days from the Notice to Proceed.
Engineer's Estimate - $ 2,343,410

With GovernmentContracts, you can:
...Bid Number: PW-0161 Bid Title: 95TH PLACE SEWER AND WATER IMPROVEMENTS PROJECT Category: ...
City of Bothell
Bid Due: 12/03/2026
...of the construction of approximately 10 linear feet of storm sewer, 2 drainage ...
City of Spokane
Bid Due: 12/08/2026
...of the construction of approximately 10 linear feet of storm sewer, 2 drainage ...
City of Spokane
Bid Due: 12/08/2026
.... Developer Project Review 12. Construction Support B. SANITARY SEWER: 1. Pump Stations, ...