SE-310
INVITATION FOR DESIGN-BID-BUILD CONSTRUCTION SERVICES
AGENCY: TCL - Technical College of the Lowcountry
PROJECT NAME: TCL - New River Auditorium
PROJECT NUMBER: H59-N375-JR
CONSTRUCTION COST RANGE: $80,000 to $120,000
PROJECT LOCATION: Building 50
DESCRIPTION OF PROJECT/SERVICES: (450 character limit)
This project includes the installation of an interior perforated drainage system and exterior sump pump. The project also
includes a new floor system over the lowest two risers of the tiered auditorium. Painting and carpeting included.
BID/SUBMITTAL DUE DATE: 05/14/2026
TIME: 10:30 AM
NUMBER OF COPIES: 1
PROJECT DELIVERY METHOD: Design-Bid-Build
AGENCY PROJECT COORDINATOR: Samuel Dellorso
EMAIL: sdellorso@tcl.edu
TELEPHONE: (724) 554-9795
DOCUMENTS OBTAINED FROM: gbell@studio2lr.com
BID SECURITY IS REQUIRED IN AN AMOUNT NOT LESS THAN 5% OF THE BASE BID.
PERFORMANCE AND LABOR & MATERIAL PAYMENT BONDS: The successful Contractor will be required to
provide Performance and Labor and Material Payment Bonds, each in the amount of 100% of the Contract Price.
DOCUMENT DEPOSIT AMOUNT: $0.00 IS DEPOSIT REFUNDABLE:
Yes
No
N/A
Bidders must obtain Bidding Documents/Plans from the above listed sources(s) to be listed as an official plan holder. Bidders that
rely on copies obtained from any other source do so at their own risk. All written communications with official plan holders &
bidders will be via email or website posting.
Agency WILL NOT accept Bids sent via email.
All questions & correspondence concerning this Invitation shall be addressed to the A/E.
A/E NAME: Studio 2LR
A/E CONTACT: Gene Bell
EMAIL: gbell@studio2lr.com
TELEPHONE: (803) 233-6602
PRE-BID CONFERENCE:
Yes
No MANDATORY ATTENDANCE:
PRE-BID DATE: 04/28/2026
TIME: 10:30 AM
PRE-BID PLACE: 100 Community College Drive Oakitie SC 29909
BID OPENING PLACE: 921 Ribaut Rd Beaufort SC 29901 Building 3 Conference room
BID DELIVERY ADDRESSES:
HAND-DELIVERY:
MAIL SERVICE:
Attn: Christine Winchester
Attn: Christine Winchester
921 Ribaut Rd
Beaufort SC 29901 Building 3
921 Ribaut Rd
Beaufort SC 29901
Yes
No
IS PROJECT WITHIN AGENCY CONSTRUCTION CERTIFICATION?
Yes
No
APPROVED BY:
(OSE PROJECT MANAGER)
DATE: 04/20/2026
DO NOT INCLUDE THIS PAGE IN THE PROJECT DOCUMENTS
SE-310, Page 2
INVITATION FOR DESIGN-BID-BUILD CONSTRUCTION SERVICES -
PROJECT INFORMATION
ENTIRE FORM MUST BE COMPLETED PRIOR TO ADVERTISING PROJECT FOR BIDS
AGENCY: TCL - Technical College of the Lowcountry
PROJECT NAME: TCL - New River Auditorium
PROJECT NUMBER: H59-N375-JR
1. BUDGET
Total Approved Project Funding:
$150,000.00
Construction Budget for this Contract: $140,000.00
Estimate of Construction Cost: $139,713.50
(The Final Estimate of Construction Cost cannot be greater than the Agency's Construction Budget for this Project)
2. FLOOD HAZARD (Provide ALL of the following information for ALL projects, even if not in a flood hazard zone)
Flood Map Information: Flood Zone: AE
(A Floodplain Permit is required for A and V Zones)
Community Number: 450025 0055D
Panel Number: 55 of 163
Is the Project Site in a 100-Year Floodplain?
Yes
No
3. STATUS OF PERMITS AND APPROVALS REQUIRED PRIOR TO BID ADVERTISEMENT
(Copies of all Permits and Approvals MUST be attached prior to advertisement.)
FLOODPLAIN (OSE approval required, not subject to
certification):
SE-510 submitted to OSE
DHEC (List Individual Permits and/or Approvals): N/A
Status of Each Permit/Approval:
N/A
SCDOT: N/A
Status of Each Permit/Approval:
N/A
ZONING (Include Name of Local Authority): N/A
Status of Permit/Approval:
N/A
OTHER (List Separately): N/A
Status of Each Permit/Approval:
N/A
4. EROSION AND SEDIMENT CONTROL
All Land Disturbing Activity associated with this project shall be performed pursuant to the Contract Documents.
5. GREEN CONSTRUCTION
Is project required to be certified as LEED or Green Globes per the Energy Efficiency Act of 2007?
Yes
No
If Yes, what certification is being pursued?
LEED Silver
2 Green Globes
AGENCY CERTIFICATION
I hereby certify that all of the information on this SE-310 is true and accurate and that the Agency has authorized,
unencumbered funds available for obligation to a contract for the project to be advertised.
BY: Samuel Dellorso
TITLE: Dir. of Facility Management
DATE: 04/20/2026