Date Issued: 3/3/2025
Request for Proposal:
2025 ROOF REPLACEMENTS
Request for Proposal Number:
#CC603-25
PROPOSAL DUE DATE AND TIME:
March 20, 2025 – 2:00 P.M. Mountain Time
Request for Proposal Opening:
March 20, 2025 – 2:00 P.M. Mountain Time
Question Deadline:
March 14, 2025– 4:00 P.M. Mountain Time
Non-Mandatory Site Visit:
March 13, 2025– 2:00 P.M. Mountain Time
PROCUREMENT REPRESENTATIVE: Shane Pulliam
E-MAIL ADDRESS: shane.pulliam@caspercollege.edu
TELEPHONE NO.: (307) 268-2633
1
Date Issued: 3/3/2025
TABLE OF CONTENTS
SECTION ONE:
DEFINITIONS AND TERMINOLOGY
SECTION TWO:
INSTRUCTIONS TO BIDDERS AND BID REQUIREMENTS
1.
General Conditions
2.
Preparation of Proposals
3.
Pre-Proposal Meeting and Job Walk
4.
Submission / Modifications / Withdrawals / Late Bids
5.
Questions About RFP / Addendums
6.
Bid Opening
7.
Award and Contract Information
8.
Required Documentation for Awarded Proposal
9.
Qualification of Bidder
10. Laws and Regulations
11. Environment, Health, and Safety
SECTION THREE: SCHEDULE OF ACTIVITIES
SECTION FOUR: SPECIFICATIONS AND SCOPE OF WORK
SECTION FIVE:
EVALUATION METHODOLOGY
1.
Overview
2.
Evaluation Criteria
SECTION SIX:
BID FORM
2
Date Issued: 3/3/2025
SECTION 1: Definitions and Terminology
In this bid and related procurement documents, the following terms shall have the meanings specified
below. These definitions apply to both singular and plural forms, and the terms may be used
interchangeably.
• Addendum: Written or graphic documents issued before bid opening that clarify, correct, or
modify the bid or related procurement documents.
• Bid / Bid Form: The pricing and/or submission provided to the College in response to the
Request for Proposal (RFP).
• Bidder / Firm: The company or vendor submitting a bid.
• Contract: An agreement between Casper College and the awarded bidder, which includes a
written contract, RFP, addenda (if any), purchase orders, purchase order terms and conditions,
and the bidder’s response to the RFP.
• Contractor: The company awarded a contract or purchase order as a result of this bid.
• Evaluation Committee / Stakeholders: Casper College employees or contracted personnel
involved in the project who have a vested interest in the selection process.
• Purchase Order (PO): A contractual agreement between Casper College and a firm for goods or
services, outlining payment terms, delivery dates, item details, quantities, freight terms, and other
conditions.
• Request for Proposal (RFP) / Proposal: A formal, publicly released document outlining Casper
College’s needs and inviting businesses to submit bids to fulfill the request.
• Schedule of Values: A detailed list of project work items, from start to finish, including
associated costs, which bidders will use to request payment throughout the project.
• Specifications / Scope of Work: The portion of the proposal that provides written or graphic
technical descriptions of materials, equipment, construction systems, standards, workmanship,
goods, services, and administrative details relevant to the project.
SECTION 2: Instructions to Bidders and Bid Requirements
1. The Procurement Department will receive proposals for the 2025 ROOF REPLACEMENT.
Proposals are due no later than March 20, 2025, at 2:00 P.M. Mountain Time.
a. Casper College reserves the right to waive irregularities and informalities, even those
listed as mandatory requirements, as long as doing so does not provide an unfair
advantage to the bidder submitting the proposal or disadvantage competing bidders.
b. Casper College may accept or reject any or all proposals. The college is not obligated to
select the lowest bid but rather the proposal that is deemed to be in the institution's best
interest. While pricing is an important factor, it will not be the sole consideration when
evaluating proposals.
c. The bidder warrants that no kickbacks, gratuities, or contingency fees have been paid or
promised in connection with this request for proposal. The bidder also warrants that no
individual receiving payment under the proposal is engaged in activities that would create
a conflict of interest.
3
Date Issued: 3/3/2025
d. Casper College ensures that minority business enterprises are afforded full opportunity to
submit proposals. The college will not discriminate based on age, race, color, sex, creed,
religion, national origin, or disability status. Additionally, the successful bidder must
comply with the Americans with Disabilities Act and the Wyoming Fair Employment
Practices Act.
e. The bidder certifies that all persons employed by their firm, affiliates, subsidiaries, holding
companies, or subcontractors are treated equally, without regard to age, race, color, sex,
creed, religion, national origin, or disability, as required by federal and state anti-
discrimination laws. Violation of this certification may constitute a material breach of
contract, which could result in contract cancellation, termination, or suspension by the
owner.
f. All proposals submitted in response to this request become public records and are
subject to public inspection. Any proprietary or confidential information must be clearly
identified and will only be treated as such to the extent permitted under the Open
Records Act. Proprietary or confidential information is defined as information that is not
generally known to competitors and may provide a competitive advantage (pricing is not
considered proprietary or confidential). A proposal cannot be designated as proprietary or
confidential in its entirety.
2. Preparation of Proposals
a. Bidders are encouraged to examine all documents, specifications, scope of work,
drawings, and addenda associated with the request for proposal (RFP) and to attend
scheduled site visits. Failure to do so will be at the bidder’s risk. The RFP and all
referenced documents must be used in the preparation of each proposal. Casper College
assumes no responsibility for errors, misinterpretations, or verbal communications
resulting from the use of incomplete proposal documents.
b. The bidder shall furnish the information required by the RFP. The bid form and all
requested documents (see Section Five) must be completed, signed, and returned by
the authorized agent of the respective firm. All required bid documents must be submitted
with the bidder’s sealed bid.
c. Any deviation or substitution from the specifications, scope of work, or drawings must be
noted in detail and attached to the bid form. Complete specifications must accompany
any deviations or substitutions offered. If a specifications deviation statement and
accompanying specifications are not provided, the bidder shall be held accountable for
full compliance with the RFP specifications.
d. Failure to submit a specifications deviation statement and accompanying specifications, if
applicable, may be grounds for rejection of the item(s) offered or the entire proposal.
e. A proposal may be rejected if it modifies any provisions, specifications, or minimum
requirements of the RFP.
f. Proposal prices must include all materials, labor, installation, removal, and proper
disposal of existing materials, bonds, insurance, profit, and delivery (FOB Casper
College, Casper, WY). A copy of material and labor warranties must be included when
applicable. In case of an error in price extension in the proposal, unit prices will govern.
4
Date Issued: 3/3/2025
g. If applicable, please submit a schedule of values with each payment application in your
proposal package. The schedule of values must be agreed upon by both the bidder and
Casper College. Payments will be based on the bidder’s successful completion of
deliverables within the stated deadlines and upon the Agency’s written acceptance of
those deliverables or services. Casper College prefers the AIA G702 format.
h. Expenses incurred in proposal preparation, pre-bid meetings, site visits, submission,
presentations, and demonstrations are the responsibility of the bidder and will not be
reimbursed by Casper College.
3. Pre-Proposal Meeting and Job Walk
a. A non-mandatory pre-proposal meeting will be held on March 13, 2025, at 2:00 P.M.
Mountain Time in Gateway Building Room 310 of the Gateway Building on the Casper
College Campus. After the meeting concludes, a job walk will begin for potential bidders
to view the work site.
b. While attendance is not mandatory, it is strongly recommended that bidders visit the job
site(s) before submitting their bids.
c. Casper College stakeholders will be present at the pre-proposal meeting to answer
questions regarding interpretation or clarification of this proposal. If any interpretations or
clarifications are deemed essential/material, an addendum will be issued on all websites
where the RFP is posted.
d. All bid documents will be available free of charge at:
i. www.caspercollege.edu/offices-services/purchasing
ii. www.rockymountainbidsystem.com
4. Submission, Modifications, Withdrawals, and Late Bids
a. Sealed proposals must be accompanied by the attached Casper College Bid Form and
signed by the proper official of the firm. All sealed proposals must be in the possession of
the Casper College Procurement Department by the due date and time. Any proposal
that is not sealed or received after the due date and time will be rejected.
b. The Total Lump Sum Price on the Bid Form must include all costs necessary to complete
the outlined work, including, but not limited to, labor, materials, operations, inspections,
permits, bonds, insurance, profit, accessories, incidentals, rentals, hotels, per diem, tax,
shipping, and removal/disposal of existing materials.
c. Sealed proposals must be mailed or hand-delivered to:
Attention: Procurement Department GW #311
Casper College
125 College Drive
Casper, WY 82601
d. Clearly mark the outside of your sealed proposal with: “2025 ROOF REPLACEMENT
#CC603-25”
5