Board of County Commissioners
Request for Quotation
Date: 06/11/2026
THIS IS NOT AN ORDER
Page: 1 of 1
RFQ#20260469
Charlotte County Purchasing Division Contact Person: Ariel Johnson, Contract Specialist
18500 Murdock Circle, Room 344 Contact Phone: 941.743.1376
Port Charlotte, Florida 33948-1094 Contact Email: ariel.johnson@charlottecountyfl.gov
FAX: 941.743.1384 Reply No Later Than: June 25, 2026 @ 3:00 p.m. EST
ADDENDUM #3 - OYSTER CREEK BOARDWALK REPLACEMENT
To: All Interested Quoters
Quoters are hereby notified that this Addendum shall be made a part of the above named quote documents. The following items are issued
to add to, modify, and clarify the quote documents. These items shall have the same force and effect as the original quote documents. Quote
Forms, to be submitted on the specified date, shall conform with the additions, deletions and revisions listed herein.
ITEM #1 CLARIFICATION:
1. Site Access and Equipment Restrictions: Access to the project site is available through the designated access point. Contractors
shall limit equipment and vehicles to those smaller than ten-wheel vehicles due to site access constraints.
2. Existing Pile Removal: The Contractor shall remove and properly dispose of all existing piles associated with the boardwalk
structure. This requirement applies even though not explicitly depicted on the plans. The pilings are about 5 feet deep.
3. Updated Decking Fasteners Requirement:
* Revise the construction plans page 7 of 9 to require the use of stainless-steel screws for all decking attachments in lieu
of S.S ringshank nails.
* Nail-fastened decking will not be accepted.
4. Permitting Requirements: The County has secured applicable environmental exemptions associated with this project, including
exemptions from SWFWMD and U.S. Army Corps of Engineers permitting requirements. The Contractor shall be responsible for
obtaining required local permits, such as applicable County permits.
5. Staging Area: The approved staging area is identified on the attached site map below.
6. Mangrove Impacts: No mangrove trimming or removal is necessary for this project.
7. Pile Load Baring Test: Pile Load Baring Test will not be needed.
8. Decking Configuration: Boardwalk decking shall consist of square-edge decking.
9. Pedestrian Safety: Maintenance of Traffic (MOT) is not required for this project. However, the Contractor shall provide appropriate
cones, caution tape, and signage as necessary to secure the work area and prevent pedestrian access during construction activities.
10. Pressure-Treated Lumber Requirements: Contractors shall refer to the original construction plans and specifications:
* 6x6 Pilings 2.5 CCA, AWPA C3 & C18
* 4x6 Pile Caps 0.6 CCA, AWPA C2 & C18
* 4x6 Stringers 0.4 CCA, AWPA C2 & C18
Quoters are required to acknowledge receipt of this addendum on their quote forms. All other terms and conditions of the original quote and
contract documents remain the same.
for
Kimberly Corbett, C.P.M., CPPB
Senior Division Manager - Purchasing
KC/AJ
RFQ No. 20260469, ADDENDUM NO. #3
Staging Area
Boardwalk Location

With GovernmentContracts, you can:
Notice: 31366713 Notice of Bid/Request for Proposal Division: Florida Sheriffs Association View Notice
Florida Department of State
Bid Due: 3/01/2027
Follow Fiscal Year (FY) 2027 Florida Panhandle Optimized Remediation Contract (ORC) and Military
DEPT OF DEFENSE
Bid Due: 12/18/2026
Follow Request for Information - Potential Research and Technology Partnership Opportunities Active Contract
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
Bid Due: 11/20/2026
Follow Replace Elevators at FDC Miami Active Contract Opportunity Notice ID 15BBNF26Q31000001 Related
JUSTICE, DEPARTMENT OF
Bid Due: 12/03/2026