AE Gale Meadows Pond Dam Rehabilitation Design Addendum 2

Location: Vermont
Posted: Apr 1, 2026
Due: Apr 10, 2026
Agency: State of Vermont
Type of Government: State & Local
Category:
  • C - Architect and Engineering Services - Construction
  • Y - Construction of Structures and Facilities
Publication URL: To access bid details, please log in.
TITLE QUESTIONS DUE ANSWERS POSTED DUE DATE NO POSTING AFTER
AE Gale Meadows Pond Dam Rehabilitation Design
Addendum 1
Addendum 2

03/23/2026 04:30PM


04/10/2026 04:30PM

Attachment Preview

ARCHITECTURAL AND ENGINEERING SERVICES
FOR THE
GALE MEADOWS POND DAM REHABILITATION DESIGN
ADDENDUM # 2
State of Vermont
Department of Buildings and General Services
Office of Purchasing & Contracting
133 State Street
Montpelier, Vermont 05633-8000
March 30, 2026
TO ALL BIDDERS OF RECORD:
This Addendum consists of 3 page(s).
Acknowledge receipt of this Addendum by entering its number and date on the Proposal Form. This Addendum forms
a part of the Contract Documents and modifies them as follows:
Items:
1. Date Changes:
RESPONSES DUE BY: April 10, 2026
2. Questions & Answers:
a) You are obtaining funding through FEMA. Is the scope of this project only for the dam?
Answer: Yes.
b) To be clear, this work is really only specific to the auxiliary spillway and not some of the other
recommendations for the dam that are in the comprehensive assessment?
Answer: Yes, its only for the auxiliary spillway.
c) Has FEMA provided you with a scope of work for funding?
Answer: No. We’ve not yet had a formal response from them on funding scope, but we were only
requesting funding for the repairs to the auxiliary spillway.
d) Since funding is not in place, will you pause or wait for FEMA funding to be in place?
Answer: No. Given the urgency of this work, we will have to move forward with the design and will
identify state funding if FEMA funds are not available.
e) The RFP has identified that an emergency action plan (EAP) and operation, maintenance, and inspection
plan (O&M plan) would have to be submitted. Do you have existing plans that can be reviewed or
utilized?
Answer: The contractor will be required to provide an up-to-date EAP and O&M manual. There has
been a dam breach analysis completed with inundation mapping, that could be used to inform the EAP.
There is an existing, old EAP on file, so that could be used, but will need to be updated. Unfortunately,
there is not an expired or active O&M plan, so that will need to be created.
f) You noted climate change. Do you have any preference on being conservative in the design with respect to
climate change?
Answer: The technical standards portion of the Vermont dam safety rules which are currently under
development are not proposing to include climate change specific standards. When incorporating
Rev 12.24.25
climate change considerations into our designs, we typically look at incremental increases in
flooding/rainfall and balance that against cost of the project to see what may be feasible to account for
by providing additional conservatism in the design. We can check with FEMA to see if they have any
climate change requirements. Our ability to incorporate additional conservatism in the design may be
dictated by the FEMA funding source.
g) Are there any additional special provisions attached to the FEMA funding?
Answer: The federal Davis-Bacon Act does not apply to FEMA funding. The design/construction
must follow current codes and standards and the state currently defaults to federal dam safety standards
such as those from FEMA.
h) Do you have a page limit? And are electronic signatures acceptable?
Answer: Electronic signatures are fine. The submission directions are lined out in the RFP 5.2 Bid
Delivery “Bids must consist of a single email with a single, digitally searchable PDF attachment
containing all components of the bid. Multiple emails and/or multiple attachments will not be accepted.
There is an attachment size limit of 40 MB. It is the Bidder’s responsibility to compress the PDF file
containing its bid if necessary, in order to meet this size limitation.” So there is not a page limit, but
there is a size limit.
i) Are there any concerns with a drawdown during construction?
Answer: The primary concerns would be with impacts to rare, threatened, and endangered species
(RTE). If there are any RTE surveys needed, the Department will complete those surveys. The
contractor will also need to ensure there are sufficient flows coming out of the pond during the
drawdown. The Dam Safety permit will require a control of water plan, which should address this
issue.
j) Is permitting part of this contract or is it being handled separately?
Answer: Permitting is part of this contract.
k) Do you have target for issuing the addendum for the questions?
Answer: March 30th.
l) When is this project expected to go to bid for contractors and what is the expected start date for
construction?
Answer: Ideally summer 2027 with a start date fall 2027 or spring 2028.
m) Could you provide the Alternatives Analysis Report and supplemental information? We will need this to
identify data gaps and strategize the design effort.
Answer: Pertinent files have been uploaded to the following google drive. Anyone with the link should
be able to download the files and review them.
https://drive.google.com/file/d/1lNORBJVxdQ4tqBXl1vsba9FR11xJBFZl/view?usp=sharing
n) In order to correctly acknowledge receipt of Addendum 1, where is the Proposal Form referenced in the
addendum? Is it possible to make an acknowledgement statement at the end of the cover letter instead?
Answer: The bid proposal form was inadvertently omitted previously. It has been added to the bid
documents and addendum acknowledgements must be noted on this form.
o) What is the FEMA grant or funding mechanism for this project? Is the funding for both the design and
construction covered by this funding?
Answer: FEMA has not yet approved the Department’s scope change request, but we have asked for
both design and construction to be covered. These are eligible costs and it has been FEMA’s intention
Rev 12.24.25
all along to revise the scope of the project to include both design and construction.
p) For Criterion 3, may hourly rates be provided by labor category rather than for individual team members?
Answer: Yes
q) If additional borings were proposed as part of Milestone #1, what are the requirements for work plan
submissions and permitting the field investigation?
Answer: A subsurface exploration plan will have to be prepared and submitted to the Vermont (DEC)
Dam Safety Program for review and approval. A plan was submitted for review and approval as part of
the soil borings performed as part of the previous phase of work.
r) Are the downstream toe of the dam and auxiliary spillway accessible by drill rig?
Answer: This probably depends on the driller. We recommend reviewing photos of the site included in
the file upload or visiting the site in person to make this determination. Access improvements may be
necessary. The driller that performed the borings as part of the previous phase of work did not want to
drive their rig down to the toe of the dam.
s) With the extension of the pre-bid meeting and question due dates, would the State consider an extension for
the proposal due date?
Answer: We have extended the proposal due date to Friday, April 10, 2026.
END OF ADDENDUM # 2
Rev 12.24.25
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL
* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.