HL-0008G TYPE OF WORK: GRADING, DRAINAGE, PAVING, WIDENING AND SIGNALS

Location: North Carolina
Posted: Sep 23, 2026
Due: Oct 14, 2026
Agency: Division of Highways
Type of Government: State & Local
Category:
  • Y - Construction of Structures and Facilities
  • Z - Maintenance, Repair or Alteration of Real Property
Publication URL: To access bid details, please log in.
  • DE00380
    POC
    HL-0008G
  • Attachment Preview

    DE00380 HL-0008G Wake County
    STATE OF NORTH CAROLINA
    DEPARTMENT OF TRANSPORTATION
    HIGHWAY DIVISION 5
    PROPOSAL
    DATE AND TIME OF BID OPENING: October 14, 2026 AT 2:00 PM
    CONTRACT ID: DE00380
    WBS ELEMENT NO.: 49367.3.3
    FEDERAL AID NO.: 1375007
    COUNTY: Wake County
    TIP NO.: HL-0008G
    MILES: 0.254
    ROUTE NO.: SR 1375 (Lake Wheeler Road)
    LOCATION: SR 1375 (Lake Wheeler Road) at SR 1393 (Hilltop Needmore Road)
    TYPE OF WORK: GRADING, DRAINAGE, PAVING, WIDENING AND SIGNALS
    NOTICE:
    ALL BIDDERS SHALL COMPLY WITH ALL APPLICABLE LAWS REGULATING THE PRACTICE OF
    GENERAL CONTRACTING AS CONTAINED IN CHAPTER 87 OF THE GENERAL STATUTES OF
    NORTH CAROLINA WHICH REQUIRES THE BIDDER TO BE LICENSED BY THE N.C. LICENSING
    BOARD FOR CONTRACTORS WHEN BIDDING ON ANY NON-FEDERAL AID PROJECT WHERE THE
    BID IS $40,000 OR MORE, EXCEPT FOR CERTAIN SPECIALTY WORK AS DETERMINED BY THE
    LICENSING BOARD. BIDDERS SHALL ALSO COMPLY WITH ALL OTHER APPLICABLE LAWS
    REGULATING THE PRACTICES OF ELECTRICAL, PLUMBING, HEATING AND AIR
    CONDITIONING AND REFRIGERATION CONTRACTING AS CONTAINED IN CHAPTER 87 OF THE
    GENERAL STATUTES OF NORTH CAROLINA. NOTWITHSTANDING THESE LIMITATIONS ON
    BIDDING, THE BIDDER WHO IS AWARDED ANY FEDERAL - AID FUNDED PROJECT SHALL
    COMPLY WITH CHAPTER 87 OF THE GENERAL STATUTES OF NORTH CAROLINA FOR
    LICENSING REQUIREMENTS WITHIN 60 CALENDAR DAYS OF BID OPENING.
    THIS IS A ROADWAY PROJECT. BID BOND IS REQUIRED.
    NAME OF BIDDER
    ADDRESS OF BIDDER

    DE00380 HL-0008G Wake County
    PROPOSAL FOR THE CONSTRUCTION OF
    CONTRACT No. DE00380 IN WAKE COUNTY, NORTH CAROLINA
    DEPARTMENT OF TRANSPORTATION,
    RALEIGH, NORTH CAROLINA
    The Bidder has carefully examined the location of the proposed work to be known as Contract No. DE00380; has carefully
    examined the plans and specifications, which are acknowledged to be part of the proposal, the special provisions, the
    proposal, the form of contract, and the forms of contract payment bond and contract performance bond; and thoroughly
    understands the stipulations, requirements and provisions. The undersigned bidder agrees to bound upon his execution of
    the bid and subsequent award to him by the Department of Transportation in accordance with this proposal to provide the
    necessary contract payment bond and contract performance bond within fourteen days after the written notice of award is
    received by him. The undersigned Bidder further agrees to provide all necessary machinery, tools, labor, and other means
    of construction; and to do all the work and to furnish all materials, except as otherwise noted, necessary to perform and
    complete the said contract in accordance with the 2024 Standard Specifications for Roads and Structures by the dates(s)
    specified in the Project Special Provisions and in accordance with the requirements of the Engineer, and at the unit or lump
    sum prices, as the case may be, for the various items given on the sheets contained herein.
    The Bidder shall provide and furnish all the materials, machinery, implements, appliances and tools, and perform the work
    and required labor to construct and complete Contract No. DE00380 in Wake County, for the unit or lump sum prices, as
    the case may be, bid by the Bidder in his bid and according to the proposal, plans, and specifications prepared by said
    Department, which proposal, plans, and specifications show the details covering this project, and hereby become a part of
    this contract.
    The published volume entitled North Carolina Department of Transportation, Raleigh, Standard Specifications for Roads
    and Structures, January 2024 with all amendments and supplements thereto, is by reference incorporated into and made
    a part of this contract; that, except as herein modified, all the construction and work included in this contract is to be done
    in accordance with the specifications contained in said volume, and amendments and supplements thereto, under the
    direction of the Engineer.
    If the proposal is accepted and the award is made, the contract is valid only when signed either by the Contract Officer or
    such other person as may be designated by the Secretary to sign for the Department of Transportation. The conditions and
    provisions herein cannot be changed except over the signature of the said Contract Officer or Division Engineer.
    The quantities shown in the itemized proposal for the project are considered to be approximate only and are given as the
    basis for comparison of bids. The Department of Transportation may increase or decrease the quantity of any item or portion
    of the work as may be deemed necessary or expedient.
    An increase or decrease in the quantity of an item will not be regarded as sufficient ground for an increase or decrease in the
    unit prices, nor in the time allowed for the completion of the work, except as provided for the contract.
    Accompanying this bid is a bid bond secured by a corporate surety, or certified check payable to the order of the Department
    of Transportation, for five percent of the total bid price, which deposit is to be forfeited as liquidated damages in case this
    bid is accepted and the Bidder shall fail to provide the required payment and performance bonds with the Department of
    Transportation, under the condition of this proposal, within 14 calendar days after the written notice of award is received by
    him, as provided in the Standard Specifications; otherwise said deposit will be returned to the Bidder.

    DE00380 HL-0008G Wake County
    TABLE OF CONTENTS
    COVER SHEET
    PROPOSAL SHEET
    PROJECT SPECIAL PROVISIONS
    DIVISION LET PREQUALIFICATION: .................................................................................. G-1
    BOND REQUIREMENTS: ........................................................................................................ G-1
    HAUL ROADS: .......................................................................................................................... G-1
    BUILD AMERICA, BUY AMERICA (BABA): ....................................................................... G-1
    CONTRACT TIME AND LIQUIDATED DAMAGES: ........................................................... G-2
    INTERMEDIATE CONTRACT TIME NUMBER (1) AND LIQUIDATED DAMAGES: ..... G-2
    INTERMEDIATE CONTRACT TIME NUMBER (2) AND LIQUIDATED DAMAGES: ..... G-3
    INTERMEDIATE CONTRACT TIME NUMBER (3) AND LIQUIDATED DAMAGES: ..... G-4
    INTERMEDIATE CONTRACT TIME NUMBER (4) AND LIQUIDATED DAMAGES: ..... G-4
    PERMANENT VEGETATION ESTABLISHMENT:............................................................... G-5
    MAJOR CONTRACT ITEMS: .................................................................................................. G-5
    SPECIALTY ITEMS: ................................................................................................................. G-6
    FUEL PRICE ADJUSTMENT: .................................................................................................. G-6
    STEEL PRICE ADJUSTMENT: ................................................................................................ G-7
    SCHEDULE OF ESTIMATED COMPLETION PROGRESS: ............................................... G-19
    DISADVANTAGED BUSINESS ENTERPRISE (DIVISIONS): ........................................... G-19
    CERTIFICATION FOR FEDERAL-AID CONTRACTS: ...................................................... G-33
    RESTRICTIONS ON ITS EQUIPMENT AND SERVICES: .................................................. G-34
    USE OF UNMANNED AIRCRAFT SYSTEM (UAS): .......................................................... G-34
    EQUIPMENT IDLING GUIDELINES: ................................................................................... G-34
    U.S. DEPARTMENT OF TRANSPORTATION HOTLINE: ................................................. G-35
    SUBSURFACE INFORMATION: ........................................................................................... G-35
    ELECTRONIC BIDDING: ....................................................................................................... G-35
    TWELVE MONTH GUARANTEE: ........................................................................................ G-36
    OUTSOURCING OUTSIDE THE USA: ................................................................................. G-36
    EROSION AND SEDIMENT CONTROL/STORMWATER CERTIFICATION: ................. G-37
    PROCEDURE FOR MONITORING BORROW PIT DISCHARGE: ..................................... G-42
    NOTE TO CONTRACTOR: .................................................................................................... G-43
    ROADWAY .................................................................................................................................R-1
    STANDARD SPECIAL PROVISIONS
    AVAILABILITY OF FUNDS - TERMINATION OF CONTRACTS ..................................SSP-1
    NCDOT GENERAL SEED SPECIFICATION FOR SEED QUALITY ................................SSP-2
    ERRATA..................................................................................................................................SSP-5
    PLANT AND PEST QUARANTINES ...................................................................................SSP-8
    MINIMUM WAGES ...............................................................................................................SSP-9
    TITLE VI AND NONDISCRIMINATION: .........................................................................SSP-10
    CONTRACT PROVISIONS FOR FEDERAL-AID CONSTRUCTION CONTRACTS ....SSP-18
    ON-THE-JOB TRAINING ....................................................................................................SSP-31
    MINIMUM WAGES (GENERAL DECISION for WAKE County) ....................................SSP-34

    DE00380 HL-0008G Wake County
    UNIT PROJECT SPECIAL PROVISIONS
    UTILITY CONSTRUCTION ................................................................................................... UC-1
    UTILITY BY OTHERS ......................................................................................................... UBO-1
    EROSION CONTROL ............................................................................................................. EC-1
    TRAFFIC SIGNALS .................................................................................................................TS-1
    FUEL USAGE FACTOR ADJUSTMENT FORM
    BID BOND
    BID FORM

    DE00380 HL-0008G Wake County
    INSTRUCTIONS TO BIDDERS
    PLEASE READ ALL INSTRUCTIONS CAREFULLY
    BEFORE PREPARING AND SUBMITTING YOUR BID.
    All bids shall be prepared and submitted in accordance with the following requirements.
    Failure to comply with any requirement may cause the bid to be considered irregular and
    may be grounds for rejection of the bid.
    For preparing and submitting the bid electronically, refer to Subarticle 102-8(B) of the Standard
    Specifications.
    Bidders that bid electronically on Raleigh Central-Let projects will need a separate request to bid
    from the approved electronic bidding website for Division Contracts.
    ELECTRONIC ON-LINE BID:
    1. Plans and the proposal can be found on the Connect NCDOT website.
    2. In accordance with Subarticle 102-8(B)(1) of the Standard Specifications, obtain an account
    and valid Digital Signature to bid with Bid Express (bidx.com)
    3. In accordance with Subarticle 102-8(B)(3) of the Standard Specifications, if bid bond is
    required and bid deposit is not chosen register bond with Surety2000 or Tinubu and submit
    with the online bid.
    4. In accordance with Article 102-3 of the Standard Specifications, registration on the Interested
    Parties List is required unless SP1 G02 Interested Parties List Not Required provision is
    included in the proposal.
    5. Prepare and submit a bid electronically using the approved electronic bidding provider website.
    6. Electronic bidding website necessary for electronic bidding can be found on the Bid Express
    website following the directions at: https://connect.ncdot.gov/letting/Pages/Electronic-
    Bidding.aspx.
    7. Questions should be emailed 7 calendar days prior to the bid opening to Division 5 Contracts
    at D05Contracts@ncdot.gov. Contact with any other NCDOT personnel concerning this
    project is strictly prohibited, unless otherwise noted, and may result in bids being considered
    non-responsive.

    DE00380 HL-0008G G-1 Wake County
    PROJECT SPECIAL PROVISIONS
    GENERAL
    DIVISION LET CONTRACT PREQUALIFICATION:
    (07-01-14)(12-1-16) SPD 01-410
    Any firm that wishes to bid as a prime contractor shall be prequalified as a Bidder or PO Prime
    Contractor prior to submitting a bid. Information regarding prequalification can be found at:
    https://connect.ncdot.gov/business/Prequal/Pages/default.aspx.
    Prior to performing the work, the prime contractor and/or subcontractor(s) shall be prequalified in
    the work code(s) which are identified as work items in the prime contractor's construction progress
    schedule that they will complete themselves. Any contractor identified as working outside their
    expertise may be considered in default of contract.
    BOND REQUIREMENTS:
    (6-1-16)(Rev.1-16-24) 102-8, 102-10 SPD 01-420A
    A Bid Bond is required in accordance with Article 102-10 of the Standard Specifications for Roads
    and Structures.
    Contract Payment and Performance Bonds are required in accordance with Article 103-7 of the
    Standard Specifications.
    HAUL ROADS:
    (7-16-24) 105 SP1 G04
    Revise the Standard Specifications as follows:
    Page 1-45, Article 105-15 RESTRICTION OF LOAD LIMITS, line 31, add the following after
    second sentence of the second paragraph:
    At least 30 days prior to use, the Contractor shall notify the Engineer of any public road proposed
    for use as a haul road for the project.
    BUILD AMERICA, BUY AMERICA (BABA):
    (11-15-22)(Rev. 7-16-24) 106 SP1 G05 A
    Revise the Standard Specifications as follows:
    Page 1-48, Article 106-1 GENERAL REQUIREMENTS, add the following after line 49:
    (C) Build America, Buy America (BABA)
    All manufactured products and construction materials permanently incorporated into any project
    must meet requirements of the Build America, Buy America (BABA) Act of the Infrastructure
    Investment and Jobs Act (IIJA). Before any material or product shown on the Department's Build
    America, Buy America (BABA) List is included for payment on a monthly estimate, the

    DE00380 HL-0008G G-2 Wake County
    Contractor shall furnish the Engineer with a notarized certification certifying that the items
    conform to the BABA Act. The Department's Build America Buy America (BABA) List can be
    found on the Department's website below.
    https://connect.ncdot.gov/letting/LetCentral/NCDOT%20BABA%20Materials%20List.pdf
    Each purchase order issued by the Contractor or a subcontractor for items on the BABA List to be
    permanently incorporated into any project shall contain in bold print a statement advising the
    supplier that the manufactured products and construction materials must be produced in the United
    States of America. The Contractor and all affected subcontractors shall maintain a separate file
    for BABA List items so that verification of the Contractor's efforts to purchase items produced in
    the United States can readily be verified by an authorized representative of the Department or the
    Federal Highway Administration (FHWA).
    CONTRACT TIME AND LIQUIDATED DAMAGES:
    (4-17-12)(Rev. 5-16-23) 108 SP1 G08 C
    The date of availability for this contract is November 12, 2026.
    The completion date for this contract is April 11, 2028.
    Except where otherwise provided by the contract, observation periods required by the contract will
    not be a part of the work to be completed by the completion date and/or intermediate contract times
    stated in the contract. The acceptable completion of the observation periods that extend beyond
    the final completion date shall be a part of the work covered by the performance and payment
    bonds.
    The liquidated damages for this contract are Two Hundred Dollars ($ 200.00) per calendar day.
    These liquidated damages will not be cumulative with any liquidated damages which may become
    chargeable under Intermediate Contract Time Number 1.
    INTERMEDIATE CONTRACT TIME NUMBER (1) AND LIQUIDATED DAMAGES:
    (7-1-95) (Rev. 2-21-12) 108 SP1 G13 A
    Except for that work required under the Project Special Provisions entitled Planting, Reforestation
    and/or Permanent Vegetation Establishment, included elsewhere in this proposal, the Contractor
    will be required to complete all work included in this contract and shall place and maintain traffic
    on same.
    The date of availability for this intermediate contract time is November 12, 2026.
    The completion date for this intermediate contract time is October 11, 2027.
    The liquidated damages for this intermediate contract time are One Thousand Six Hundred
    Dollars ($ 1,600.00) per calendar day.
    Upon apparent completion of all the work required to be completed by this intermediate date, a
    final inspection will be held in accordance with Article 105-17 and upon acceptance, the
    Department will assume responsibility for the maintenance of all work except Planting,

    DE00380 HL-0008G G-3 Wake County
    Reforestation and/or Permanent Vegetation Establishment. The Contractor will be responsible for
    and shall make corrections of all damages to the completed roadway caused by his planting
    operations, whether occurring prior to or after placing traffic through the project.
    INTERMEDIATE CONTRACT TIME NUMBER (2) AND LIQUIDATED DAMAGES:
    (2-20-07) 108 SP1 G14 A
    The Contractor shall complete the required work of installing, maintaining, and removing the
    traffic control devices for lane closures and restoring traffic to the existing traffic pattern. The
    Contractor shall not close or narrow a lane of traffic on SR 1375 (Lake Wheeler Road) or SR
    1393 (Hilltop Needmore Road) during the following time restrictions:
    DAY AND TIME RESTRICTIONS
    MONDAY THRU FRIDAY 6:00 A.M. TO 9:00 A.M.
    MONDAY THRU FRIDAY 3:00 P.M. TO 7:00 P.M.
    SUNDAY 6:00 A.M. TO 2:00 P.M.
    In addition, the Contractor shall not close or narrow a lane of traffic on SR 1375 (Lake Wheeler
    Road) or SR 1393 (Hilltop Needmore Road), detain and/or alter the traffic flow on or during
    holidays, holiday weekends, special events, or any other time when traffic is unusually heavy,
    including the following schedules:
    HOLIDAY AND HOLIDAY WEEKEND LANE CLOSURE RESTRICTIONS
    1. For unexpected occurrence that creates unusually high traffic volumes, as directed by the
    Engineer.
    2. For New Year's Day, between the hours of 6:00 A.M. December 31st and 7:00 P.M.
    January 2nd. If New Year's Day is on a Friday, Saturday, Sunday or Monday, then until
    7:00 P.M. the following Tuesday.
    3. For Easter, between the hours of 6:00 A.M. Thursday and 7:00 P.M. Monday.
    4. For Memorial Day, between the hours of 6:00 A.M. Friday and 7:00 P.M. Tuesday.
    5. For Independence Day, between the hours of 6:00 A.M. the day before Independence Day
    and 7:00 P.M. the day after Independence Day.
    If Independence Day is on a Friday, Saturday, Sunday or Monday, then between the hours
    of 6:00 A.M. the Thursday before Independence Day and 7:00 P.M. the Tuesday after
    Independence Day.
    6. For Labor Day, between the hours of 6:00 A.M. Friday and 7:00 P.M. Tuesday.
    7. For Thanksgiving Day, between the hours of 6:00 A.M. Tuesday and 7:00 P.M. Monday.

    DE00380 HL-0008G G-4 Wake County
    8. For Christmas, between the hours of 6:00 A.M. the Friday before the week of Christmas
    Day and 7:00 P.M. the following Tuesday after the week of Christmas Day.
    9. For events that are significant traffic generators from one (1) hour before the event to one
    (1) hour after the event, as directed by the Engineer.
    Holidays and holiday weekends shall include New Year's, Easter, Memorial Day, Independence
    Day, Labor Day, Thanksgiving, and Christmas. The Contractor shall schedule his work so that
    lane closures will not be required during these periods, unless otherwise directed by the Engineer.
    The time of availability for this intermediate contract work shall be the time the Contractor begins
    to install all traffic control devices for lane closures according to the time restrictions listed herein.
    The completion time for this intermediate contract work shall be the time the Contractor is required
    to complete the removal of all traffic control devices for lane closures according to the time
    restrictions stated above and place traffic in the existing traffic pattern.
    The liquidated damages are Two Hundred Fifty Dollars ($250.00) per fifteen minutes or portion
    thereof.
    INTERMEDIATE CONTRACT TIME NUMBER (3) AND LIQUIDATED DAMAGES:
    (2-20-07) (Rev. 6-18-13) 108 SP1 G14 H
    The Contractor shall complete the work required of Phase I as shown on Sheet(s) TMP-6 &
    TMP-7 and shall place and maintain traffic on same.
    The date of availability for this intermediate contract time is the date the Contractor elects to begin
    the work.
    The completion date for this intermediate contract time is the date which is Thirty (30) consecutive
    calendar days after and including the date the Contractor begins this work.
    The liquidated damages are One Thousand Dollars ($ 1,000.00) per calendar day.
    INTERMEDIATE CONTRACT TIME NUMBER (4) AND LIQUIDATED DAMAGES:
    (5-21-13) 108 SP1 G14 I
    The Contractor shall complete the work required of installing each new inductive loop after the
    removal of each existing loop by the milling, patching or resurfacing operations and shall place
    and maintain traffic on same.
    The date of availability for this intermediate contract time for each inductive loop installation will
    be the date when the Contractor elects to disturb the existing inductive loop.
    The completion date for this intermediate contract time for each inductive loop installation will be
    the date which is seven (7) consecutive calendar days after the date of availability.
    The liquidated damages are Five Hundred Dollars ($ 500.00) per calendar day.

    DE00380 HL-0008G G-5 Wake County
    PERMANENT VEGETATION ESTABLISHMENT:
    (2-16-12)(Rev. 1-16-24) 104 SP1 G16
    Establish a permanent stand of the vegetation mixture shown in the contract. During the period
    between initial vegetation planting and final project acceptance, perform all work necessary
    to establish permanent vegetation on all erodible areas within the project limits, as well as,
    in borrow and waste pits. This work shall include erosion control device maintenance and
    installation, repair seeding and mulching, supplemental seeding and mulching, mowing,
    and fertilizer topdressing, as directed. All work shall be performed in accordance with the
    applicable section of the Standard Specifications. All work required for initial vegetation planting
    shall be performed as a part of the work necessary for the completion and acceptance of the
    Intermediate Contract Time (ICT). Between the time of ICT and Final Project acceptance,
    or otherwise referred to as the vegetation establishment period, the Department will be responsible
    for preparing the required National Pollutant Discharge Elimination System (NPDES) inspection
    records.
    Once the Engineer has determined that the permanent vegetation establishment requirement has
    been achieved at an 80% vegetation density (the amount of established vegetation per given area
    to stabilize the soil) and no erodible areas exist within the project limits, the Contractor will be
    notified to remove the remaining erosion control devices that are no longer needed. The Contractor
    will be responsible for, and shall correct any areas disturbed by operations performed in permanent
    vegetation establishment and the removal of temporary erosion control measures, whether
    occurring prior to or after placing traffic on the project.
    Payment for Response for Erosion Control, Seeding and Mulching, Repair Seeding, Supplemental
    Seeding, Mowing, Fertilizer Topdressing, Silt Excavation, and Stone for Erosion Control will be
    made at contract unit prices for the affected items. Work required that is not represented by
    contract line items will be paid in accordance with Articles 104-7 or 104-3 of the Standard
    Specifications. No additional compensation will be made for maintenance and removal of
    temporary erosion control items.
    MAJOR CONTRACT ITEMS:
    (2-19-02)(Rev. 1-16-24) 104 SP1 G28
    The following listed items are the major contract items for this contract (see Article 104-5 of the
    Standard Specifications):
    Line # Description
    Asphalt 16-18

    This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
    Daily notification on new contract opportunities

    With GovernmentContracts, you can:

    • Find more opportunities and win more business
    • Receive daily alerts for all new bid opportunities
    • Get contract opportunities matched to your business
    ONE WEEK FREE TRIAL

    See also

    ...DD00534 BP4.R033.3 POC GRADING, PAVING, DRAINAGE AND STRUCTURE BP4.R033_GEO_CULV_INV.pdf Doc. Type...: Contract Information ...

    Division of Highways

    Bid Due: 10/27/2026

    ...Solicitation Number: 274-SM-2022-0016R Project Title: Drainage Assistance Program - Lord Ashley... of existing ...

    State Government of North Carolina

    Bid Due: 10/29/2026

    ...Project: 9832 Grasmere Drive Storm Drainage Improvement Project Ref. #: FY27-ITBCON-25 Department.... Storm ...

    City of Charlotte

    Bid Due: 11/05/2026

    ...Project: Collective Storm Drainage Improvement Project - Series Q Ref. #: FY27-ITBCon-27...

    City of Charlotte

    Bid Due: 11/03/2026

    * Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.