CITY OF RALEIGH Engineering Services Department
Fleet Management Operations Division
Neuse River Resource Recovery Facility
INFORMAL BID DOCUMENTS FOR
Neuse River Resource Recovery Facility - 2K Above Ground Storage
Tank (AST) Replacement
Date of Issue: Friday May 22nd, 2026
1
CITY OF RALEIGH
Neuse River Resource Recovery Facility - 2K Gallon AST Replacement
Index
• Index.................................................................................................. Page 2
• Advertisement For Bid....................................................................... Page 3-7
• Instructions to Bidders....................................................................... Page 8-15
• Bid Proposal Form............................................................................. Page 16-18
• Procedure for reporting NC Sales Tax Expenditures ......................... Page 19-21
• Minority and Owned Business Enterprise Program (MWBE)............ Page 22-26
• Acknowledgment of MWBE Policy ........................................................ Page 27
• Identification of MWBE Participation ...................................................... Page 28
2
CITY OF RALEIGH
Neuse River Resource Recovery Facility - 2K Gallon AST Replacement
CITY OF RALEIGH – ADVERTISEMENT FOR BID (INFORMAL BID)
PROJECT: Neuse River Resource Recovery Facility - 2K AST
Replacement
PROJECT LOCATION: Neuse River Resource Recovery Facility, 8500 Battle Bridge Road
Raleigh, NC 27610
Informal Bid #:
Owner and Contact:
274-7235-111
City of Raleigh, Fleet Management Operations
2501 N. Raleigh Blvd
Raleigh, North Carolina 27604
Project Manager Contact: George Francis
e-mail: George.Francis@raleighnc.gov
NOTE: Do not refer or use previously published bid documents.
Pursuant to the General Statutes of North Carolina, Section 143-128 et. seq, contractors
are invited to submit Sealed Single Prime Construction bids providing labor, material, and
equipment for entering into a Single Prime Contract. The scope of work includes but is not
limited to the following:
The replacement of the existing 2000-gallon AST. Install new 2000-gallon UL 2085 Fireguard DW
AST 8500 Battle Bridge Road Raleigh, NC 27610.
Cost Specifications:
The total cost of this project will be included within the bid package. All labor, materials, new
equipment and permitting fees in relation to the purpose of this project are to be included.
Project Overview & Scope:
Project Overview:
Provide equipment and labor to remove existing 2000-gallon AST.
Install new 2000-gallon UL 2085 Fireguard Double Walled AST; install 3" fill piping for remote fill;
install product piping; install Wayne dispenser supplied by customer and connect to existing fuel
controller. Haul and dispose of all debris.
3
CITY OF RALEIGH
Neuse River Resource Recovery Facility - 2K Gallon AST Replacement
Tank Requirements:
Capacity: 2000 Gallons
Type: Double Wall AST UL 2085
Brand: No specific brand has been identified
Must be NEW – refurbished or used equipment will not be accepted
Must meet all local inspection codes.
Scope:
1. Removal
• Disconnect and remove existing 2,000 Gallon Above Ground Storage Tank.
• Properly dispose of the old AST per local regulations.
• Remove existing electrical sub-panel at fuel island.
2. AST Replacement
• Supply a new 2,000-gallon AST that is UL 2085 compliant.
• Transportation of AST and equipment to the site, and storage of AST and equipment
on site are the responsibility of the contractor.
3. Installation:
• Install the new UL 2085 AST in the same physical location.
• Install 3" fill piping for remote fill; install product piping;
• Install Wayne dispenser supplied by customer and connect to existing fuel controller
• Install shielded cable from new tank to existing tank monitor for probe.
• Install Emergency Fuel shutoff at fuel island.
• All work to meet electrical code.
• Haul and dispose of all debris.
4. Instrumentation
• Furnish and install new tank gauge that will integrate with the E.J. Ward Fuel
Management system (Omntec Tank Monitor).
5. Commissioning & Testing:
• Perform startup and performance testing.
• Coordinate with facility management for final acceptance testing.
6. Documentation:
• Provide complete warranty information to city staff.
7. Work Hours
• All work is to be performed during normal business hours (Monday to Friday from
7:30 am to 3:30 pm) unless otherwise specified.
Notes:
- A site visit is required prior to bidding to verify all field conditions, including dimensions,
logistics, and access for removal and installation of the new tank.
- The new AST must closely match the dimensions and connection points of the existing unit
to avoid significant modifications to the AST pad, power conduit, and piping.
Proposal Requirements:
Your proposal must include a detailed, itemized quote including:
4
CITY OF RALEIGH
Neuse River Resource Recovery Facility - 2K Gallon AST Replacement
• Cost of the new AST and Materials
• Labor Costs
• Lead Time and Estimated Project Duration
Warranty Information (Manufacture equipment and workmanship)
Bidders will be required to show evidence that they are licensed to perform the work in the Bidding
Documents as required by North Carolina General Statute, Chapter 87 and the Instruction to Bidders.
Sealed bids: Bidders are responsible for ensuring delivery by shipping or hand delivery.
Do not send via United States Postal Services (USPS). Bids will not be accepted by
email or fax.
Bids will be received by:
Time:
Date:
Mail Delivery:
3:30 pm
Tuesday June 23, 2026
City of Raleigh, Fleet Management Operations
2501 N. Raleigh Blvd
Raleigh, North Carolina 27604
Drop off Times:
7:30 am – 3:30 pm
2501 N. Raleigh Blvd
Raleigh, North Carolina 27604
Pre-Bid meeting Tuesday June 2, 2026 will be held at each project site. Attendance
is mandatory. Pre-bid attendance may be used to validate bid submissions.
Attendance to the pre-bid will be documented by the City.
Date: June 2nd, 2026
Time: 9:00 - 11:00am
Location: Neuse River
Resource Recovery
Facility, 8500 Battle
Bridge Road Raleigh, NC