Q25002422 DLNR-DAR Kaunakakai Molokai Baseyard ImprovementsGeneral InformationSolicitation Number
Q25002422Status
ReleasedDepartmentLand & Natural ResourcesDivisionEngineeringIslands (where the work/delivery is to be performed)
MolokaiCategoryConstructionRelease Date 04/22/2025Offer Due Date & Time04/30/2025 02:00 PMDescriptionThe contractor is to provide all labor, materials, equipment, and incidentals to complete the following work per Exhibit A.
1. Raise DAR Office Container Bldg:
(1) Raise Field Office to approx. same level as existing adjacent Office Trailer [18" +(-)].
(2) Secure (tie down) building with anchors (12 each).
(3) Construct 4" wide steps at entry door.
(4) Construct a 4' wide x 15' long, 1:10 slope ADA ramp with a 5' x 5' landing on the right side of the Office Container from the chain link entry gate toward the front of the Office Container.
(5) Continue to construct a 4' wide x 5' +(-) long, 1:10 ADA ramp with 5' x 5' landing below Window A.
(6) Provide 42" high 2" x 4" wooden guard rail on both sides of the ramp.
(7) Provide 36" high, 1.25" Dia. galvanized steel handrail on both sides of the ramp.
(8) Install one(1) overhead electrical cable from the existing electrical panel box at the Office Trailer to the existing electrical panel box at the Office Container.
(9) All woods should be exterior, termite treated.
(10) Painting by others.
2. Repair/Reroof Existing Office Trailer & Covered Patio:
(1) Remove, repair, and replace any damaged or rotten wooden framing & decking of existing covered patio.
(2) Remove and replace existing asphalt roofing of covered patio & Office Trailer.
(3) Provide Asphalt coating with mineral surface roofing.
(4) Painting by others.Contact PersonLee, Bing HinEmail
binghin.lee@hawaii.gov
Phone808-587-0273General Comments1. The Request for Proposal with Scope of Work and photos, Exhibit A, and Interim Conditions are attached as PDF files.
2. Contract start date and contract end date are only estimates and will vary depending on the Notice to Proceed date and construction duration.
3. All questions will addressed via addendum.Procurement OfficerDickey H. LeeAttachments
7 DLNR Interim General Conditions Oct 1994.pdf
EXHIBIT A _Request for Proposal to DLNR Aquatics Molokai Baseyard.pdf
AG-008 103D General Conditions (1.10.23).pdf
Download All
Direct all questions regarding this Solicitation, and any questions or Issues relating to the accessibility
of this Solicitation (Including the appendices and exhibits to this Document, and any other document related
to this Solicitation), to:
Lee, Bing Hin.