JD Cope / DC UPS System

Location: Georgia
Posted: Oct 28, 2026
Due: Nov 11, 2026
Agency: State Government of Georgia
Type of Government: State & Local
Category:
  • 65 - Medical, Dental, and Veterinary Equipment and Supplies
Solicitation No: PE-75553-NONST-2027-000000066
Publication URL: To access bid details, please log in.
Event ID Event Title Government Entity Start Date (ET) End Date (ET)
PE-75553-NONST-2027-000000066 JD Cope / DC UPS System Dalton Utilities
Oct 28, 2026 @ 04:15 PM
Nov 11, 2026 @ 05:00 PM
JD Cope / DC UPS System

Start Date: Oct 28, 2026 @ 04:15 PM ET

End Date:
Nov 11, 2026 @ 05:00 PM ET

Event ID: PE-75553-NONST-2027-000000066
Event Type: Non-State Agency
Event Status: Open
Purchase Type: Non-State Agency
Category Type: Goods
Government Type: city
Fiscal Year: 2027


Description


Dalton Utilities requests bids from qualified manufacturers and suppliers for the engineering, manufacture, testing, documentation, delivery, and specified field services for a complete DC/UPS system at the J.D. Cope Energy Facility. The attached Technical Specification 197347.5.5430, Rev. 0, including the equipment datasheets, governs the technical scope. All bids should be submitted to dkeaton@dutil.com

NIGP Codes
Code Description
28712 Batteries and Hardware For Electronic Equipment, Including Recycled Types
96737 Electrical and Electronic Products, Manufacturing Services
28569 Misc. Electrical Equipment and Supplies (Not Otherwise Classified)
BuyerContact:

David Keaton
dkeaton@dutil.com

706-529-202

Attachment Preview

Date Revision Issue Status Approved By
10/15/2026 0 Issued For Bid JCR

Dalton Utilities
J.D. Cope Energy Facility
Whitfield County, GA
BMCD PROJECT NO. 197347
BMCD Specification No. 5.5430
DC/UPS System
Technical Specification
Date Revision Issue Status Approved
By
10/15/2026 0 Issued For Bid JCR

Dalton Utilities
J.D. Cope Energy Facility
5.5430 - UPS and DC System
Project No. 197347
Burns & McDonnell Engineering Company, Inc.
DOCUMENT 00 01 05 - INDEX AND CERTIFICATION PAGE
SPECIFICATION INDEX
DOCUMENT/ NUMBER
DIVISION DESCRIPTION OF PAGES
Division 01 General Requirements 38
Division 26 Electrical 25
00 01 05 - 1

SECTION 00 01 05 - INDEX AND CERTIFICATION PAGE: continued
I hereby certify that specifications listed above were prepared by me or under my direct supervision and
that I am registered as a Professional Engineer under the laws of the State of Georgia.
Signature: _________________________
Typed or Printed Name:
Date: __________ Registration No.: ___________
00 01 05 - 2

Dalton Utilities
J.D. Cope Energy Facility
5.5430 - UPS and DC System
Project No. 197347
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
Section 01 11 04 - Summary of Work
Appendix 01 11 04-A - General Design Conditions
Section 01 32 04 - Project Meetings, Schedules, and Reports
Section 01 33 04 - Submittals
Appendix 01 33 04-A - Submittal Schedule
Appendix 01 33 04-B - Standard Submittal Descriptions
Appendix 01 33 04-C - Cover and Spine Labels
Appendix 01 33 04-D -Vendor Submittal Reference Document
Appendix 01 33 04-G - Equipment Databook Outline
Section 01 45 04 - Quality Control
Section 01 60 04 - Materials and Fabrication
Section 01 75 04 - Manufacturer's Field Services
Section 01 78 04 - Purchase Order Closeout
DIVISION 26 - ELECTRICAL
Section 26 00 02 - Electrical Equipment - General Technical Requirements
26 00 02-A - Exhibit A - Cable Spec Type Designations
26 00 02_SW-1.0 - Wire and Cable Specification Sheet
26 00 02_SW-1.1 - Wire and Cable Specification Sheet
Section 26 33 53 Batteries & Uninterruptible Power Systems
Section 26 33 53-A - Datasheet
Section 26 33 53-B - Data to be Submitted with Bid
REFERENCE DRAWINGS
197347-EE125.pdf
Battery Duty Cycle.pdf
END OF TABLE OF CONTENTS 00 01 10
00 01 10 - 1

SECTION 01 11 04 - SUMMARY OF WORK
PART 1 - GENERAL
1.01 SUMMARY:
A. The Project consists of a new electrical power generation plant utilizing 3 - 18.522MW
Reciprocating Engines totaling an output of 55.566MW.
B. Owner/Point of Delivery: Dalton Utilities 1232 V.D. Parrot Jr Pkwy/Dalton, GA 30721.
C. Engineer: The Contract Documents were prepared by Burns & McDonnell Engineering
Company, Inc., (9400 Ward Parkway, Kansas City, Missouri 64114.)
D. Purchase Order Identification: 5.5430 - DC/UPS System
1.02 SCOPE:
A. The Work of this Purchase Order includes but is not limited to the following:
1. Design, fabricate, and deliver DDP, specified "Point of Delivery" for the following
equipment as required to meet the temperature requirements defined in Purchase Order
Documents:
a. One (1) 125 VDC station battery with racks and spill containment
b. One (1) 125 VDC nominal, 250 VDC-rated battery fused disconnect switch
c. One (1) 125 VDC nominal, 250 VDC-rated station battery load test non-fused
disconnect switch
d. Two (2) redundant paralleling battery chargers
e. One (1) inverter with static transfer switch
f. One (1) manual bypass switch
g. One (1) isolation transformer/voltage regulator
h. One (1) 125 VDC nominal, 250 VDC-rated switchboard
i. One (1) battery monitoring system (meets NERC PRC-005-06)
j. One (1) battery lifting device
k. Two (2) 120VAC-rated Panelboards
l. Two (2) 125 VDC nominal, 250VDC-rated Panelboards
2. All Work shall be designed to meet the design data specified in Appendix 01 11 04-A
Site Design Conditions.
3. Provide submittals per Appendix 01 33 04-A.
4. Provide submittals and Equipment Data Books as defined in Section 01 33 04.
5. Performance of Manufacturer's Field Services as specified in Section 01 75 04.
6. Spare parts, special tools, lubricants, and consumables as specified in 1.03.
7. The Goods furnished under this Purchase Order shall be designed for indoor installation
and storage.
B. Conflicting Requirements: In the event that requirements specified within the technical
specification are found to be conflicting, Supplier shall notify Engineer before proceeding with
the work. In general, the following order of precedence shall be applied by the Supplier:
1. Technical Specification including all Equipment data sheets.
2. Other referenced industry codes/standards/specifications.
1.03 SPARE PARTS, SPECIAL TOOLS, LUBRICANTS AND CONSUMABLES:
A. Spare parts, special tools, hardware, lubricants, and other consumables required for complete
installation and commissioning shall be provided by Supplier. These shall be delivered to Site
with the Goods being provided under this Purchase Order.
01 11 04 - 1
197347.5.5430

SECTION 01 11 04 - SUMMARY OF WORK: continued
B. Supplier shall provide a list of manufacturer's recommended spare parts for: 1) first two (2)
years of operation; 2) installation and commissioning; 3) capital spares (spares not subject to
wear).
1. These lists shall be included with Supplier's proposal and shall also be provided during
execution as a formal submittal.
2. Supplier shall provide one consolidated, organized Excel spreadsheet that contains all the
spare parts information for all Equipment provided. The necessary Excel headings shall
be as follows: Description, Size, Type, Design Pressure & Temperature, Design Class,
Design Material, End-to-End, End Prep, Rating, Packing No., Manufacturer, Purchase
Order No., Vendor Name, Manufacturer Serial No, Model No., Drawing, Part No., ID
No., Exploded Drawing Numbers, Remarks, Rebuild Kit, Frame Size, RPM, Voltage,
Service Factor, Amps.
3. Unit Prices for spare parts shall be valid for purchase by Owner for two (2) years after
Substantial Completion.
C. Any spare parts shall be valid for purchase by Owner for two (2) years after Substantial
Completion.
D. Special tools which are required to maintain, inspect, disassemble, or operate the Materials
provided by the Supplier shall be provided by Supplier and will be turned over to Engineer
upon Substantial Completion. Examples include but are not limited to:
1. Maintenance tools shall include lifting beams, non-standard wrenches including offset
wrenches, special slings and chokers, electrical breaker lifting and racking mechanisms,
rotor stands, bolt tensioning tools, temporary structural supports, specialized electronic
test equipment, and the like. All maintenance tools shall be in new and unused condition.
Maintenance tools shall be shipped in separate, heavily constructed wooden boxes
provided with hinged covers and padlock hasps. Maintenance tools for each piece of
Equipment shall be boxed separately and the boxes shall be clearly stenciled with the
name of the project, Supplier's Equipment Purchase Order number, and the name of the
Equipment. All boxed special maintenance tools shall be turned over to the Owner for
storage upon delivery to site.
2. If a tool is a required specialty tool, and the supplier supplying the Materials provides the
tool directly with the Materials or offers it as an accessory to assist in the installation,
inspection, operation, repair, or disassembly, then it shall be considered by the supplier as
a supplier-supplied part. The supplier shall include all special tools supplied by the
manufacturers required for installing the Equipment which is not normally furnished by
equipment erection subcontractors. One complete set of new, unused special tools shall
be furnished with the Equipment for use by the purchaser during construction. Erection
tools shall be shipped in separate, heavily constructed wooden boxes provided with
hinged covers and padlock hasps. Erection tools for each piece of Equipment shall be
boxed separately and the boxes shall be clearly stenciled with the name of the project,
purchaser's Purchase Order number, and the name of the Equipment. Erection tools shall
not be boxed with maintenance tools. After completion of the work, the purchaser shall
turn over all special erection tools to the owner as requested or that will be required for
owner's future maintenance.
1.04 WORK SEQUENCE
A. Sequence of Work shall be determined by Supplier to meet all Purchase Order requirements.
END OF SECTION 01 11 04
01 11 04 - 2
197347.5.5430

APPENDIX 01 11 04 A GENERAL DESIGN PARAMETERS
1.01 FUNCTION:
A. Bidder shall use the criteria specified in this Section to develop the parameters and detailed
design necessary to specify, purchase, and supply equipment as specified to meet the
performance guarantees.
B. These criteria set the minimum standards acceptable. They are not intended to limit Bidder to a
single design approach.
C. The anticipated life that is required for Equipment and Materials furnished is 30 years.
Continuous operation will be required for the anticipated life with minimum scheduled
downtime for inspections and maintenance.
D. Materials specified are minimum requirements. Provide higher grade materials where required
to provide service life consistent with the life expectancy of utility power plant equipment and
structures.
E. General design criteria are specified in this Section. Additional design criteria for Equipment
and Materials are specified in other Sections.
1.02 APPLICABLE CODES AND STANDARDS:
A. Design in accordance with the following codes and standards:
1. Occupational Safety and Health Administration (OSHA)
2. International Building Code (IBC)
3. National Fire Protection Association (NFPA) Current Edition
4. National Electrical Code (NEC)
5. American Society of Mechanical Engineers (ASME)
6. American Society for Testing and Materials (ASTM)
7. American Water Works Association (AWWA)
8. Heat Exchange Institute (HEI)
9. Tubular Exchanger Manufacturer's Association (TEMA)
10. American National Standards Institute (ANSI)
11. Hydraulic Institute (HI)
12. Steel Structures Painting Council (SSPC)
13. Manufacturers Standardization Society (MSS)
14. Underwriters Laboratories, Inc. (UL)
15. FM Global
16. Pipe Fabrication Institute (PFI)
17. American Welding Society (AWS)
18. Midwest Insulation Contractors Association
19. American Gear Manufacturers Association (AGMA)
20. Plastic Pipe Institute (PPI)
21. International Organization for Standardization (ISO)
22. German Institute for Standardization (DIN)
23. International Electrotechnical Commission (IEC)
24. Institute of Electrical and Electronics Engineers (IEEE)
1.03 DESIGN PARAMETERS:
A. This article includes the basic Site/Project information and certain design criteria applicable to
the Project. This information is general in nature and may be additionally specified in other
Sections. In the event that additional specific information regarding the Project Site is
required, Bidder shall contact Engineer and Owner.
B. Site Conditions:
1. Ambient Conditions:
01 11 04-A - 1
197347.5.5430

HVAC Design Conditions
Location Dalton, Georgia ASHRAE Weather Station # 722154
Ambient Design Conditions
Summer (F) Winter (F) 50 Year Extreme Conditions (F)
0.4%, DB/MCWB 1%, DB/MCWB 99.6%, DB 99%, DB Min, DB Max, DB Max, WB
93.2/ 75.4 91.1 / 74.8 19.7 23.5 1.7 101.9 89.4
Dehumidification (F)
0.4%, DP/HR/MCDB 1%, DP/HR/MCDB4
77.4 / 146.4/ 83.7 75.3 / 136.1 / 82.6
HVAC Design Parameters
Building/Room Type Indoor Design Temperatures3 Outdoor Design Conditions System Type
Summer, F Winter, F Summer Winter
Occupied Areas
Offices (Admin) 2 78 70 1% 99% HVAC
Laboratories2
Critical Control Room2 77 70 Extreme Extreme HVAC
Equipment Areas, Unoccupied
Engine Hall 122 45 0.4% 99.6% HV
Mechanical Rooms4 110 110 45 0.4% 99.6% HV
Tank Building4 45 0.4% 99.6% HV
Battery Rooms1 77 77 0.4% 99.6% HVAC
Critical Elec. 77 70 Extreme Extreme HVAC
1 1% & 2% Hydrogen alarms, Dual Setpoint. 2 Design maximum relative humidity 65% at 1% Summer MCWB. 3 Indoor design temperature based on associated outdoor design conditions. 4 Design relative humidity is 30%.

APPENDIX 01 11 04 A GENERAL DESIGN PARAMETERS
a. Site Elevation: 710 feet Above Mean Sea Level.
b. Barometric Pressure: 14.11 psi-a
2. HVAC Design Criteria:
HVAC Design Conditions
Location Dalton, Georgia ASHRAE Weather Station # 722154
Ambient Design Conditions
Summer (F) Winter (F) 50 Year Extreme Conditions (F)
0.4%, 99%, DB Max,
1%, DB/MCWB 99.6%, DB Min, DB Max, DB
DB/MCWB WB
93.2/ 75.4 91.1 / 74.8 19.7 23.5 1.7 101.9 89.4
Dehumidification (F)
0.4%, 1%,
DP/HR/MCDB DP/HR/MCDB4
77.4 / 146.4/
83.7 75.3 / 136.1 / 82.6
HVAC Design Parameters
Indoor Design Outdoor Design
Temperatures3 Conditions System
Winter, F Type
Building/Room Type Summer, F Summer Winter
Occupied Areas
Offices (Admin) 2
78 70 1% 99% HVAC
Laboratories2
Critical Control
77 70 Extreme Extreme HVAC
Room2
Equipment Areas, Unoccupied
Engine Hall 122 45 0.4% 99.6% HV
110 45 0.4% 99.6% HV
Mechanical Rooms4
110 45 0.4% 99.6% HV
Tank Building4
Battery Rooms1 77 77 0.4% 99.6% HVAC
Critical Elec. 77 70 Extreme Extreme HVAC
1 1% & 2% Hydrogen alarms, Dual Setpoint.
2 Design maximum relative humidity 65% at 1% Summer MCWB.
3 Indoor design temperature based on associated outdoor design conditions.
4 Design relative humidity is 30%.
a. Extreme Ambient Dry Bulb Temperature:
(1) Maximum: 101.9 degreesF.
(2) Minimum: 1.7 degreesF.
(3) Minimum Design Metal Temperature (MDMT): 0 degreesF.
(4) Equipment located outdoors shall be designed for these extreme ambient dry
bulb and MDMT temperatures.
b. Rainfall:
(1) Annual Average: 56 inches.
01 11 04-A - 2
197347.5.5430

APPENDIX 01 11 04 A GENERAL DESIGN PARAMETERS
(2) 100-year, 24-hour total: 7.65 inches
c. Seismic Design shall be in accordance with the International Building Code, 2024
Edition, with Georgia Amendments.
(1) Risk Category: III
(2) Site Class: D
(3) Seismic Design Category: C
(4) Seismic Importance Factor: 1.25
(5) Spectral Response Acceleration at Short Period, S : 0.51g
S
(6) Spectral Response Acceleration at 1-Second Period, S : 0.12g
1
d. Wind Design shall be in accordance with the Georgia Building Code and the
following:
(1) Risk Category: III
(2) Basic Design Wind Speed: 112 mph
(3) Exposure Category: C
e. Snow Loading shall be in accordance with the Georgia Building Code and the
following:
(1) Risk Category: III
(2) Ground Snow Load: 29 psf
(3) Terrain Category: C
(4) Snow Importance Factor: 1.1
f. Site Frost Depth: 5 inches
3. Equipment and Materials for the Project shall comply with the OSHA Regulations and
Standards 29CFR1910. All Work performed on Site shall comply with OSHA
Regulations and Standards 29CFR1926 and 29CFR1926 Subpart R.
4. Equipment Sound Level Requirements: The maximum A-weighted sound level for
Equipment furnished under these Specifications shall not exceed 85 dBA free field
measured 3 feet horizontally from the base of the Equipment and 5 feet above floor level
or any personnel platforms under any normal operating condition. In addition, provide
sound level for all octave bands for each Equipment furnished. During re-pressurization,
the dryer will exceed 85 dBA for several seconds and is considered an abnormal
condition.
5. Asbestos material is strictly prohibited in the Equipment furnished under this Purchase
Order.
6. Coating/Painting:
a. Unless specified more explicitly in the technical specifications, all Equipment shall
be factory finish painted with system suitable for the intended final service
conditions and environment at the Project Site without any additional field painting
for a reasonable design and operating service life of no less than 10 years. All
equipment provided shall include manufacturer's standard surface preparation and
coating system.
b. Submit all factory finish painting information (surface preparation, number of
coats, thickness of each coat, general type and manufacturer's product
name/number of each coat, topcoat color name/number, and other applicable
information) for information and Owner's future use.
7. Standards of Design and Workmanship:
a. The finished Work and/or product shall be complete in all respects. All hardware
shall be manufactured, fabricated, assembled, finished, and documented with the
workmanship of the highest quality throughout, and all of the components shall be
new.
01 11 04-A - 3
197347.5.5430

APPENDIX 01 11 04 A GENERAL DESIGN PARAMETERS
b. The Work shall be carried out in accordance with Best Recognized Practices and
customary industry quality unless otherwise specified within the technical
specification Sections.
01 11 04-A - 4
197347.5.5430

This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

Event ID Event Title Government Entity Start Date (ET) End Date (ET) PE-67610-NONST-2027-000000106

State Government of Georgia

Bid Due: 12/03/2026

Event ID Event Title Government Entity Start Date (ET) End Date (ET) 84400-eRFQ-002163-2027

State Government of Georgia

Bid Due: 11/24/2026

Event ID Event Title Government Entity Start Date (ET) End Date (ET) PE-64400-NONST-2026-000000292

State Government of Georgia

Bid Due: 12/01/2026

27-015 INSTRUCTIONAL SUPPLIES BID 27-015.docx BID 27-015 WORKSHEET.xlsx Test Title Date Released: Bid

Houston County Board of Education

Bid Due: 12/03/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.