Addendum 1
Invitation to Bid
Pavement Repairs and Site Improvements at Public Safety Building
This Addendum to the Invitation to Bid includes questions received through the end of day on May 7, 2026,
along with corresponding responses and clarifications. A subsequent addendum will be issued following
the question deadline of May 14, 2026.
Please review and acknowledge this addendum with an authorized signature below and include this signed
page with your submitted bid. Failure to do so may result in your bid being declared non-responsive.
__________________________________
COMPANY
__________________________________
SIGNATURE
__________________________________
PRINT NAME
_________________________________
DATE
_________________________________
TITLE
Pre-Bid Question Log
Project: Public Safety Pavement Repair and Site Improvements
Date: 5/8/2026
Question
Will you please provide more detail regarding “FDR Medium Duty” and
1 "FDR Heavy Duty”. For example a spread rate and or mix design?
Answer
See sheet C-501 of the design plans.
Also, what is your paving spec for “asphalt heavy duty” and “asphalt
2 medium duty”? Is this new full depth paving? If so where is this suppose to See sheet C-504 of the design plans.
be installed?
3
Do you have a set of plans to show the proposed phasing and site work?
The plans are available for download from the City's website and the Georgia
Procurement Registry.
Regarding the FDR, can the existing asphalt be removed prior to mixing? Or Full-depth reclamation (FDR) shall consist of pulverizing and mixing the existing asphalt in
4 is the intent to pulverize and mix all the existing material in place?
place.
5 Are there any utilities that may be impacted by construction?
Yes. The Contractor shall be responsible for locating and coordinating around existing
utilities. Note that electrical and irrigation lines run under the concrete sidewalks at the
front of the building. The contractor should use extreme caution in these areas, and if
any utilities are impacted, stop work immediately and contact the City of Duluth for
repairs.
6 Is any type of utility contractor license needed for this project?
No.
7 Does this project require General Contracting license?
Yes.
Any restrictions regarding the working days and hours that we should be Construction work will be allowed between 7:30 am and 6 pm on weekdays, and
8 aware of?
between 10 am and 6 pm on weekends/holidays.
Access to secured areas will be coordinated through the Police Department. The
9
How will the contractor access the secured areas behind the fence/gates?
Contractor shall coordinate scheduling and access requirements in advance.
10
Does the concrete work (including the stairs) at the entrance need to be
phased?
Yes. The Contractor shall phase the work as necessary to maintain continuous pedestrian
access to the front entrance throughout construction. The phasing plan shall be
submitted for review and approval by the Project Team by the selected contractor.
No. The existing Conex box will remain in place. The Contractor shall preserve and
11
Will the existing Conex box at the rear corner of the site be moved prior to
construction?
protect it from damage throughout construction and shall be responsible for any damage
resulting from construction activities.
The Contractor shall coordinate with the existing system installer/manufacturer for
12 Does the city have a preferred vendor for the detector loops at the gates? compatibility and integration requirements. The existing system was installed by ECA
Gate and Lock (https://ecagateandlock.com/).
In the case of a new firm, will relevant project experience held by the firm's For newly established firms, relevant project experience of principals and key team
13 principals or key team members be credited toward the firm's overall
members will be considered; however, the firm will be evaluated as a whole based on the
experience requirements?
qualifications and experience presented in its submittal.
Who is responsible for inspections and materials testing and the associated
14 fees? If the General Contractor is responsible for the testing, please provide This question will be addressed in a forthcoming addendum to be issued at a later date.
all the testing requirements for this project.
15 Does this project require any compaction test?
The Contractor shall be responsible for all required compaction and associated testing to
demonstrate compliance with project specifications. Testing should be completed in
accordance with GDOT specfications.
How would the owner want to address soft soils conditions, if
16 encountered?
This question will be addressed in a forthcoming addendum to be issued at a later date.
17 When is the anticipated start date?
The project team anticipates making a recommendation to City Council in early June.
Contract execution will follow pending Council approval.
18 Will weather days count against the project?
No. Bad weather days will be defined in accordance with GDOT specifications.
19 Does this project have a Force Majeure clause?
20 Can the contractor work on the weekends?
No.
See the response to question #8. Weekend work will need to be coordinated with the city
in advance so that access and supervision can be provided.
What are the requirements to safe-up the project site? Do you require
21 placement of chain-link fences, signages, and barricades?
Site security and safety measures shall be the responsibility of the Contractor. The
Contractor shall provide and maintain any necessary fencing, signage, barricades, and
other protective measures required to comply with applicable codes and ensure public
and worker safety.
The Contractor shall be responsible for vehicular and pedestrian traffic control as
Are there any requirements for vehicular traffic and/or pedestrian control? required for the project. The Contractor shall provide and maintain all necessary signage,
22 Are there any signages required?
barricades, and traffic control measures in accordance with applicable codes, regulations,
and safety standards.
Water and power may be available on site via a standard hose bibb and a typical 120-volt
Are there water and power available on site within proximity of the
23 construction locations?
electrical outlet; however, availability is not guaranteed and shall be coordinated with the
Police Department. The Contractor shall be responsible for providing any additional utility
needs required for the Work.
A portion of the existing parking lot may be made available for limited staging of
Any designated parking areas for construction personnel? Any designated dumpters and equipment, subject to coordination with and approval by the City. The
24 areas for dumpsters and equipment?
Contractor shall be responsible for complying with all requirements and applicable
restrictions associated with use of the staging area.
Are there any available staging areas for this project close by? What are
25 requirements for staging areas? If any?
A portion of the existing parking lot may be made available for limited staging, subject to
coordination with and approval by the City. The Contractor shall be responsible for
complying with all applicable requirements and restrictions associated with use of the
staging area.
Is there any existing irrigation system within the construction areas? If
26 there is, how would you want us to address it?
Yes. See the response to question 5.
27
Do we have to use the services of a private underground utility locator for
this project?
Yes. See the response to question 5.