Project Description
The Cates Utility Plant, combined with the Yarbrough Utility Plant, supply steam, chilled water, and electricity to support the North and Central Campus Precincts (~7,250,000 gsf). This project will expand the Cates Utility Plant to support short- and long-term university growth and ensure utility redundancy as the North and Central Campus Precincts grow. Phase I will address the building expansion and install a heat recovery chiller plant, providing low temperature hot water to campus. Phase II will prepare for the next large centrifugal chiller installation.
Project Funding
The total project budget is expected to be $32,500,000. The project is currently funded for advance planning and will be identifying additional funding to begin this phased project.
Project Scope
The University seeks the professional services of a Construction Manager at Risk (CMR) to join the team in the design development phase to provide services for the project through design, construction and post acceptance.
Project Schedule
Design Start 4/15/26
Schematic Phase Document Submittal 6/24/26
Design Development Phase Document Submittal 12/9/26
Final Bid Document Submittal 6/9/27
Bid Opening 10/4/27
Construction Start 9/1/27
Submittal Requirements
Interested firms can participate in the process by submitting a proposal that addresses all the information requested by the Qualifications Questionnaire for CM at Risk. The Questionnaire will be available on July 6, 2026 through the Project Manager or on the website .Please note that the length of the proposal should be limited to twenty (20) pages on both sides. This limitation does not include the Cover Sheet, Tabs or Financial Statements.Firms are requested to submit electronic proposals at the email address listed below by July 31, 2026 .
Critical Selection Factors
Critical selection factors include the following:
CMR Selection Process
Following the receipt of proposals, a University Interview Committee, appointed by the Secretary to the University Board of Trustees’ Building and Property Committee, will shortlist three (3) firms, interview and make a recommendation of selection to the University Board of Trustees’ Buildings and Property Committee. The selected firm will contract with the State of North Carolina through the University and coordinate services with Design and Construction.
CMR Contract
The contract will be negotiated with the CMR in two parts. Part one of the contract is pre-construction services. The second part of the contract is for bidding, construction, and close-out services.
CMR Pre-Submittal Meeting
A Pre-submittal Meeting will be held July 14, 2026 at 3:00 pm in Conference Room 101 of the Admin III Building at 2601 Wolf Village Way on the NC State University campus. Attendance at the CMR Pre-Submittal Meeting is mandatory. Obtain parking permits from NCSU Transportation, located in Administrative Services I, at 2721 Sullivan Drive.
In order to offer Construction Manager at Risk services in the response to this solicitation, the proposer must be licensed as a general contractor in the state of North Carolina.
Questions/Proposal Submittal
In order that the selection process be as objective as possible, do not contact members of the Board of Trustees, or any university officials other than the project manager. All questions and project submittals are to be directed to:
David Hammock, PE, Project Manager
NC State University, Design and Construction
Box 7520, 2601 Wolf Village Way
Raleigh, North Carolina 27695-7520
Phone 919-515-2030
david_hammock@ncsu.edu
Q&A Links: Available for Download:
00-CMR Qualifications Questionnaire
Published in
Advertisements
.
| RFP DATA SHEET Utility Plant Building Expansion - Cates Chiller Plant | |
|---|---|
| Item | Datum |
| Short Description of Project | The Cates Utility Plant, combined with the Yarbrough Utility Plant, supply steam, chilled water, and electricity to support the North and Central Campus Precincts (~7,250,000 gsf). This project will expand the Cates Utility Plant to support short- and long-term university growth and ensure utility redundancy as the North and Central Campus Precincts grow. Phase I will address the building expansion and install a heat recovery chiller plant, providing low temperature hot water to campus. Phase II will prepare for the next large centrifugal chiller installation. |
| Issuing Office | NCSU Facilities Division, Design and Construction |
| Department, Agency/Institution, Location where the Project will be constructed | The project is to be located on the Central Campus of North Carolina State University, Raleigh, NC. |
| Project Overview | The University seeks the professional services of a Construction Manager at Risk (CMR) to join the team in the Design Development Phase to provide services for the project through design, construction and post acceptance. |
| Website address (URL) for posting of notices regarding this project | https://facilities.ofa.ncsu.edu/category/ads/ |
| Expected Date of Completion of Design | Design Development (Phases 1&2) - October 2026 Phase 1 - June 2027 Phase 2 - TBD |
| Project Designer & Consultants | Lead Designer: RMF Engineering |
| Construction Manager at Risk Selection Schedule | Qualifications Questionnaire available: July 6, 2026 Pre-Submittal Conference (Mandatory): July 14, 2026 - Conf Rm 101, Admin III, 2601 Wolf Village Way Proposals due: 5:00pm July 31, 2026 Shortlist Developed: August 2026 Pre-Interview Meeting (Interview Logistics): August/September 2026 Interviews scheduled: (tentatively) September 2026 Selection announced: (tentatively) September 2026 |
| Construction Management Fee (Section II Paragraph E.2) | The Construction Management Fee will be a fixed number based on a percentage of the Cost of Work. |
| Project Construction Cost | Total Project Budget: $32,500,000 less costs including, but not limited to: Design Fees Owner's Contingency Estimated Available for Construction (GMP) Estimated Construction Management Fee Estimated CMR Contingency |
RFP DATA SHEET
Utility Plant Building Expansion - Cates Chiller Plant
Item Datum
Short Description of Project The Cates Utility Plant, combined with the Yarbrough Utility Plant,
supply steam, chilled water, and electricity to support the North and
Central Campus Precincts (~7,250,000 gsf). This project will expand
the Cates Utility Plant to support short- and long-term university
growth and ensure utility redundancy as the North and Central
Campus Precincts grow. Phase I will address the building expansion
and install a heat recovery chiller plant, providing low temperature
hot water to campus. Phase II will prepare for the next large
centrifugal chiller installation.
Issuing Office NCSU Facilities Division, Design and Construction
Department, Agency/Institution, The project is to be located on the Central Campus of North
Location where the Project will Carolina State University, Raleigh, NC.
be constructed
Project Overview The University seeks the professional services of a Construction Manager
at Risk (CMR) to join the team in the Design Development Phase to
provide services for the project through design, construction and post
acceptance.
Website address (URL) for
posting of notices regarding this https://facilities.ofa.ncsu.edu/category/ads/
project
Expected Date of Completion of Design Development (Phases 1&2) - October 2026
Design Phase 1 - June 2027
Phase 2 - TBD
Project Designer & Consultants Lead Designer: RMF Engineering
Construction Manager at Risk Qualifications Questionnaire available: July 6, 2026
Selection Schedule Pre-Submittal Conference (Mandatory): July 14, 2026 - Conf Rm 101,
Admin III, 2601 Wolf Village Way
Proposals due: 5:00pm July 31, 2026
Shortlist Developed: August 2026
Pre-Interview Meeting (Interview Logistics): August/September 2026
Interviews scheduled: (tentatively) September 2026
Selection announced: (tentatively) September 2026
Construction Management Fee The Construction Management Fee will be a fixed number based on
(Section II Paragraph E.2) a percentage of the Cost of Work.
Project Construction Cost Total Project Budget: $32,500,000 less
costs including, but not limited to:
Design Fees
Owner's Contingency
Estimated Available for Construction (GMP)
Estimated Construction Management Fee
Estimated CMR Contingency

With GovernmentContracts, you can:
...Solicitation Number: 1012-26-075 Construction Manager at Risk (CMAR) Services Project Title...: Construction Manager ...
State Government of North Carolina
Bid Due: 8/12/2026
...Construction Improvements Advertisement 298-FY27-CAM-BID-MUNIAPDREHAB Request for Bids 298-FY27-CAM-BID...
City of Asheville
Bid Due: 9/08/2026
...Solicitation Number: 298-FY27-CAM-BID-MUNIAPDREHAB Project Title: MUNI 4th Floor Construction... Improvements Description: Request for ...
State Government of North Carolina
Bid Due: 9/08/2026
...Project: FY27 ADA Corridors Phase 1 Unspecified Construction Ref. #: 269-2027-001 Department: City...
City of Charlotte
Bid Due: 8/18/2026