H342--RFQ Life Safety Statement of Conditions Inspection Services
| Location: |
Federal |
| Posted: |
Feb 4, 2026 |
| Due: |
Feb 9, 2026 |
| Agency: |
VETERANS AFFAIRS, DEPARTMENT OF |
| Type of Government: |
Federal |
| Category: |
- H - Quality Control, Testing, and Inspection Services
|
| Solicitation No: |
36C24926Q0091 |
| Publication URL: |
To access bid details, please log in. |
H342--RFQ Life Safety Statement of Conditions Inspection Services
Active
Contract Opportunity
Department/Ind. Agency
VETERANS AFFAIRS, DEPARTMENT OF
Sub-tier
VETERANS AFFAIRS, DEPARTMENT OF
Office
249-NETWORK CONTRACT OFFICE 9 (36C249)
Looking for contract opportunity help?
General Information View Changes
-
Contract Opportunity Type: Solicitation (Updated)
-
Updated Published Date: Feb 04, 2026 10:49 am EST
-
Original Published Date: Jan 26, 2026 11:20 am EST
-
Updated Date Offers Due: Feb 09, 2026 12:00 pm EST
-
Original Date Offers Due: Feb 09, 2026 12:00 pm EST
-
Inactive Policy: Manual
-
Updated Inactive Date: Mar 11, 2026
-
Original Inactive Date:
Apr 10, 2026
-
Initiative:
Classification
-
Original Set Aside:
-
-
Product Service Code: H342 - INSPECTION- FIRE FIGHTING/RESCUE/SAFETY EQUIPMENT; ENVIRON PROTECT EQUIPMENT/MATLS
-
NAICS Code:
-
541350 - Building Inspection Services
-
Place of Performance:
Description View Changes
Questions & Answers
Can we have more detail and respectfully request clarification regarding the project schedule, as multiple sections appear to contain differing completion requirements. Section B.2.A.4 (pg. 5) states completion by March 30, 2026, or within 30 days of the site visit, whichever comes first. Site visits shall occur at least 60 days from Award Date and the Final Product shall be completed 90 days after Award Date.
Section F (pg. 8) states completion within 12 weeks of contract issuance or June 30, 2026, whichever comes first. See response from Question 1
Section B.3 (pg. 10) repeats the 12 weeks of contract issuance or June 30, 2026, whichever comes first requirement. See response from Question 1
Amendment Section F (pg. 6) also states within 12 weeks of contract issuance or June 30, 2026, whichever comes first. See response from Question 1
Can you please clarify which schedule requirement governs? Additionally, please confirm whether the use of whichever comes first is intentional, as a late contract award could result in an extremely compressed or impractical performance period. Prefer to schedule a site visit within 2 months (60 days) from Award Date, and have the final product about a month out from that (90 days).
In Amendment 0001 Section A. General Information #4 Performance Period states "The contractor shall complete the work required under this SOW by March 30, 2026, or within 30 days of completion of site survey, whichever comes first. Work at the government site shall not take place on Federal holidays unless directed by the Contracting Office." However, the original solicitation states that the PoP is 03/01/2026-06/30/2026. Please confirm what the PoP is for this effort. Period of Performance (PoP) date is subject to change, pending award date. The requirement shall be completed up to 90 days after the Award Date.
Do any of the buildings have identified deviations without a current corrective action that the contractor will be required to take over before arriving on site? No, any deviations or deficiencies that are found should be documented, but corrective actions will be addressed by VA staff and/or a separate contract if appropriate.
Is the contractor permitted to split the effort into several site visits? Or should the contractor perform the inspection consecutively? Consecutive would be ideal, but we would allow for splitting up the work if needed depending on time constraints.
Please confirm the requirement for 10 references of similar projects. See Amendment 0001 SOW changes Section J.
Is the contract able to be modified for partial payments based upon an agreed payment schedule? This contract shall NOT provide partial payments. This contract will provide payment upon completion and acceptance of Service.
END OF AMENDMENT
Attachments/Links
Contact Information
Contracting Office Address
-
VISN 9 CONSOLIDATED ACQUISITION 3400 LEBANON ROAD
-
MURFREESBORO , TN 37129
-
USA
Secondary Point of Contact
History
Daily notification on new contract opportunities
With GovernmentContracts, you can:
- Find more opportunities and win more business
- Receive daily alerts for all new bid opportunities
- Get contract opportunities matched to your business
ONE WEEK FREE TRIAL
See also
Follow Y--VOYA 335009 N191 REHAB RAINY AND ASH Active Contract Opportunity Notice ID
INTERIOR, DEPARTMENT OF THE
Bid Due: 6/09/2026
Follow 20--CYLINDER,DUPLEX Active Contract Opportunity Notice ID N0010426QYA76 Related Notice Department/Ind. Agency DEPT
DEPT OF DEFENSE
Bid Due: 7/31/2026
Follow F--Snake River Area Office Weed Control Active Contract Opportunity Notice ID 140R1726Q0025
INTERIOR, DEPARTMENT OF THE
Bid Due: 6/12/2026
Follow Z1DA--646-21-101 UD SPS AHU & RO Upgrade (VA-26-00036217) Active Contract Opportunity Notice
VETERANS AFFAIRS, DEPARTMENT OF
Bid Due: 6/11/2026
* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.