| Location: | Maryland |
|---|---|
| Posted: | Aug 28, 2026 |
| Due: | Sep 4, 2026 |
| Agency: | COMMERCE, DEPARTMENT OF |
| Type of Government: | Federal |
| Category: |
|
| Solicitation No: | 1333ND26QNB610465 |
| Publication URL: | To access bid details, please log in. |
APEX Accelerators are an official government contracting resource for small businesses. Find your local APEX Accelerator (opens in new window) for free government expertise related to contract opportunities.
APEX Accelerators are funded in part through a cooperative agreement with the Department of Defense.
The APEX Accelerators program was formerly known as the Procurement Technical Assistance Program (opens in new window) (PTAP).
Amendment 1to RFQ 1333ND26QNB610465
Clarification questions:
Vendor Question 1:
Could you please confirm the solids content (TSS) of the water? If this is clean water, with less than 2% TSS, please let us know so we can determine the appropriate unit for the application.
NIST Response:
This water is moderately clean, not a slurry (2% TSS is closer to wastewater) but not filtered
Vendor Question 2:
The factory has confirmed that no software is required to configure the meter, as very few ultrasonic meters require software for configuration.
NIST Response:
PC-based data logging is a nice-to-have but not a necessity.
Vendor Question 3: (clarification on the following process conditions for the primary and secondary cooling systems)
Operating temperature of the process fluid (or pipe surface temperature) at the measurement points, for both the primary and secondary cooling loops. This determines whether standard or high-temperature transducers are required.
NIST Response:
No higher than 114 degrees Fahrenheit.
Vendor Question 4: (clarification on the following process conditions for the primary and secondary cooling systems)
Operating pressure of the cooling water at the measurement points (primary and secondary).
NIST Response:
No higher than 10 psia.
Vendor Question 5: (clarification on the following process conditions for the primary and secondary cooling systems)
Confirmation of the process fluid — the SOW references cooling water; please confirm it is treated water with no significant entrained solids or aeration that could affect ultrasonic signal transmission.
NIST Response:
Primary – Heavy water, purified. Secondary - Water with minimal solids. Some algae to be expected but not significant.
As defined in the attached Combined Synopsis Solicitation, Statement of Work and RFO Provisions and Clauses.
| Aug 21, 2026 | [Combined Synopsis/Solicitation (Original)] 7 Ultrasonic Flowmeters |

With GovernmentContracts, you can:
...assessment is a collaborative initiative of the Division of Housing and the Local ...
Queen Anne County
Bid Due: 9/16/2026
...on the System for Award Management (SAM) database via the website https://sam.gov/content/home with ...
DEPT OF DEFENSE
Bid Due: 9/18/2026
...the needs of the CPSC. CPSC requires online learning (aka course) content to ...
CONSUMER PRODUCT SAFETY COMMISSION
Bid Due: 9/18/2026
..., editorial infrastructure, project management, creative services, and other support necessary to carry ...
HEALTH AND HUMAN SERVICES, DEPARTMENT OF
Bid Due: 9/16/2026