Pre Bid Conference:
|
Mandatory pre-bid conference will be held on May 12, 2025 at 9:00 am via Microsoft Teams. See Division A. Prospective Bidders must attend this virtual meeting.
|
|
Bulletin Desc:
|
The work to be done consists primarily of, but is not limited to, furnishing and installing Dura-Line MicroDucts and MiniXtend Fiber in existing and new conduit. New conduit will be installed via horizontal directional boring method, with one section requiring open trench. There will also be placement of new fiber vaults in the sidewalk and parkway. Restoration of potholing and excavation in street, sidewalk and parkway as needed. Bids are required for the entire Work.
|
|
Amendments:
|
|
Amendment #
|
Amendment Date
|
Amendment Note
|
1
|
05/15/2025 02:41:12 PM
|
See Addendum 1 for changes to Division C and Division H. Item 1 1. Quantity changed from "1" to "75.0". 2. Description changed from "Remove existing pull box" to "Remove and replace damaged/undersized pull boxes". Item 2 1. Description changed from "Furnish and install new #6T pull box with 2 extensions (Channell Bulk 4 series (36" depth, Super Bulk Lid, and L-Bolt Security System)" to "Furnish and install new #6T pull box with 2 extensions (Channell Bulk 4 series - 36" depth, Super Bulk Lid, and L-Bolt Security System to be used in lieu of #6T pull box)". Item 3 1. Quantity changed from "320" to "380.0". 2. Description changed from "Furnish and install new #6E pull box with 2 extensions (Channell Bulk 4 series (36" depth, Shield X Lid, and L-Bolt Security System)" to "Furnish and install new #6E pull box with 2 extensions (Channell Bulk 4 series - 36" depth, Shield X Lid, and L-Bolt Security System to be in lieu of #6E pull box)". Item 4 1. Quantity changed from "59" to "16.0". 2. Description changed from "Furnish and install new N48E pull box (Channell Bulk 7 series (36" depth, Shield X Lid, and L-Bolt Security System)" to "Furnish and install new N48E pull box (Channell Bulk 7 series - 36" depth, Shield X Lid, and L-Bolt Security System to be used in lieu of N48E pull box)". Item 6 1. Description changed from "Furnish and install 7-way Dura-Line FuturePath 16/12 conduit with tracer wire direct buried in sidewalk/pavement/soil per boring method." to "Furnish and install 7-way Dura-Line FuturePath 12.7/10mm conduit with tracer wire direct buried in sidewalk/pavement/soil per boring method.". Item 10 1. Quantity changed from "3" to "100.0". Item 11 1. Description changed from "Furnish and install new 1-way Dura-Line FuturePath 16/13 direct installed in new/existing conduit with tracer wire and pull tape" to "Furnish and install new 1-way Dura-Line FuturePath 12.7/10mm direct installed in new/existing conduit with tracer wire and pull tape". Item 12 1. Description changed from "Furnish and install new 2-way Dura-Line FuturePath 16/13 direct installed in new/existing conduit with tracer wire and pull tape" to "Furnish and install new 2-way Dura-Line FuturePath 12.7/10mm direct installed in new/existing conduit with tracer wire and pull tape". Item 13 1. Description changed from "Furnish and install new 4-way Dura-Line FuturePath 16/13 direct installed in new/existing conduit with tracer wire and pull tape" to "Furnish and install new 4-way Dura-Line FuturePath 12.7/10mm direct installed in new/existing conduit with tracer wire and pull tape". Item 14 1. Description changed from "Furnish and install new 7-way Dura-Line FuturePath 16/13 direct installed in new/existing conduit with tracer wire and pull tape" to "Furnish and install new 7-way Dura-Line FuturePath 12.7/10mm direct installed in new/existing conduit with tracer wire and pull tape". Item 21 1. Quantity changed from "1" to "450.0". Item 31 1. Description changed from "Entry Hub Site - Furnish and install 288F fiber (fiber furnished by City), plenum DuraLine (16/13, 7-way), risers, wall penetrations, and pathways from vault or conduit at exterior walI, to rack FTU per approved design. Complete and terminate all fibers." to "Entry Hub Site - Furnish and install 288F fiber (fiber furnished by City), plenum DuraLine (12.7/10mm, 7-way), risers, wall penetrations, and pathways from vault or conduit at exterior walI, to rack FTU per approved design. Complete and terminate all fibers.". Item 32 1. Description changed from "Entry Service Location - Furnish and install 24F fiber (fiber furnished by City), plenum DuraLine (16/13, 2-way), risers, wall penetrations, and pathways from vault or conduit at exterior walI, to enclosure FTU per approved design. Complete and terminate all fibers." to "Entry Service Location - Furnish and install 24F fiber (fiber furnished by City), plenum DuraLine (12.7/10mm, 2-way), risers, wall penetrations, and pathways from vault or condui
|
2
|
05/16/2025 10:39:48 AM
|
R-7231 Pre-bid conference sign-in sheet Attachment File Changes: Header 1. File 'Pre-bid conference sign-in sheet': File 'Pre-bid conference sign-in sheet' added .
|
3
|
06/04/2025 10:06:45 AM
|
R-7231 Questions released on 06/04/2025. Attachment File Changes: Header 1. File 'R-7231 Questions 06042025': File 'R-7231 Questions 06042025' added .
|
4
|
06/06/2025 09:03:44 AM
|
R-7231 Addendum 2 to extend the due date to 6/23/25 at 3:00 p.m. (PT). Header 1. Bid Opening Date changed from "06/09/2025 03:00:00 PM" to "06/23/2025 03:00:00 PM". Attachment File Changes: Header 1. File 'R-7231 Addendum 2': File 'R-7231 Addendum 2' added .
|
|