Specifications for
City of Effingham
EFFINGHAM TIF EICHE & KREKE WATER MAIN
REPLACEMENT
Kreke Avenue. - Banker Street to Park Street
Eiche Avenue - Banker Street to Fourth Street
Effingham, IL
Project No. 02600811.001
JuLY 2026
City of Effingham
Effingham TIF Eiche & Kreke Water Main Replacement
TABLE OF CONTENTS
DIVISION 0 - BIDDING DOCUMENTS
PAGE
Section 00100 – Advertisement for Bids................................................................................ 00100: 1-2
EJCDC C-200 – Instructions to Bidders .............................................................................. 00200: 1-13
EJCDC C-410 – Bid Form ..................................................................................................... 00410: 1-8
EJCDC C-430 – Bid Bond ..................................................................................................... 00430: 1-2
EJCDC C-510 – Notice of Award............................................................................................... 00510: 1
EJCDC C-520 – Agreement Form (Contract) ........................................................................ 00520: 1-7
EJCDC C-550 – Notice to Proceed ............................................................................................ 00550: 1
EJCDC C-610 – Performance Bond....................................................................................... 00610: 1-4
EJCDC C-615 – Payment Bond ............................................................................................. 00615: 1-5
EJCDC C-620 – Contractor’s Application for Payment ...................................................... 00620: 1-12
EJCDC C-625 – Certificate of Substantial Completion.............................................................00625: 1
EJCDC C-700 – General Conditions.................................................................................... 00700: 1-70
EJCDC C-800 – Supplementary Conditions................................................................ ……00800: 1-10
EJCDC C-940 – Work Change Directive……………………………………………………..00940: 1
EJCDC C-941 – Change Order ................................................................................................. .00941: 1
DIVISION 1 - GENERAL REQUIREMENTS
Section 01010 – Summary of Work ....................................................................................... 01010: 1-2
DIVISION 2 – SITE WORK
Section 02660 – Water Distribution………………………………………….…………....02660: 1-13
Section 02680 – Horizontal Directional Drilling for Water Main……………………..……02680: 1-3
EXHIBIT 1 – City of Effingham – Public Works Department – Water Division
Water Service Line Material Survey……………………………………………………….………...1
i
ADVERTISEMENT FOR BIDS
CITY OF EFFINGHAM
Effingham Eiche & Kreke Water Main Replacement
General Notice
The City of Effingham (Owner) is requesting Bids for the construction of the following Project:
Effingham Eiche & Kreke Water Main Replacement
Bids for the construction of the Project will be received by the office of the City Clerk located at 201 E.
Jefferson, Effingham, IL 62401, until Tuesday, August 11, 2026 at 11:00 AM local time. At that time the
Bids received will be publicly opened and read in the Council Chambers.
The Project includes the following Work:
The work generally consists of furnishing and installation of water system piping, fittings, valves, and
appurtenances for potable water. Installation will consist of 6”-10” PVC RJ Yelomine HDD and 6”-10”
PVC SDR-21 Water Main along design route. Contractor is responsible for installation of the proposed
main as shown on the plans, installing valves, hydrants, casing, fittings, connections, services, service
relocations, lead/galvanize service removal, and disconnections. This work also includes surface
restoration with various pavements and curbing as detailed in the plans and specifications titled “City
of Effingham Eiche & Kreke Water Main Replacement 2026.” The proposed water main is being
installed to replace an existing older and smaller water main.
Additional considerations shall be as detailed and described in the plans and specifications titled “City
of Effingham Eiche & Kreke Water Main Replacement 2026” prepared by Farnsworth Group, Inc.
Provided the Contractor furnishes proof of proper insurance and bonding in a timely manner, it is
anticipated that a Notice of Award of contract will be issued within 30-to-60 days of the date bids are
opened and that a Notice to Proceed will be issued within 10 days of the date of the Notice of Award.
This Project shall reach Substantial Completion by February 28, 2027, and Final Completion by March
30, 2027. Completion dates and requirements are further outlined in the Agreement, document C-520.
Obtaining the Bidding Documents
Information and Bidding Documents for the Project can be found at the following designated website:
https://www.effinghamil.com/bids-and-tabulations/
Bidding Documents may be downloaded from the designated website. The designated website will be
updated periodically with addenda and other information relevant to submitting a Bid for the Project. All
official notifications, addenda, and other Bidding Documents will be offered only through the designated
website. Neither Owner nor Engineer will be responsible for Bidding Documents, including addenda, if
any, obtained from sources other than the designated website.
The Issuing Office for the Bidding Documents is also the office of the Engineer for this project:
Farnsworth Group, Inc.
400 W. Jefferson Avenue, Suite A
Effingham, IL 62401
EJCDC® C-111, Advertisement for Bids for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,
and American Society of Civil Engineers. All rights reserved.
Page 1 of 2
Prospective Bidders may examine the Bidding Documents at the Issuing Office Monday through Friday
between the hours of 8:00 AM and 5:00 PM.
Each proposal shall contain the name of every person or firm interested in the same and shall be
accompanied by bid bond, certified check, bank draft, or cashier's check payable to the order of the
Treasurer, City of Effingham, in an amount not less than 5% of the proposal.
The City of Effingham reserves the right to reject any or all bids, waive or not waive any informality in the
bids, and to accept any bid which it deems most favorable to the City.
It is agreed that this bid may not be withdrawn for a period of 45 days from opening thereof or it will be
subject to forfeit the 5% Bid Bond provided with the bid.
It is anticipated that a Notice of Award of a contract will be issued within 30-to-60 days of the date bids
are received and that a Notice to Proceed will be issued within 10 days of the date of the Notice of Award
if contractor provides proper insurance and bonding in a timely manner.
Work on this project is subject to the Prevailing Wage Act (820 ILCS 130). Prevailing Wages, as
determined by the Illinois Department of Labor and the current Prevailing wage ordinance approved by
the City Council, shall be paid. The contractor shall be responsible for submitting all certified payrolls for
the awarded project and for any subcontractor work to the IDOL website pursuant to Public Act 100-
1177. Work on this project is subject to the Illinois Substance Abuse Prevention on Public Works Project
Act (820 ILCS 265) as enacted by P.A. 95-0635.
Pre-bid Conference
There will not be a pre-bid conference for this Project.
Instructions to Bidders.
For all further requirements regarding bid submittal, qualifications, procedures, and contract award,
refer to the Instructions to Bidders that are included in the Bidding Documents.
This Advertisement is issued by:
Owner: City of Effingham
By: Steve Miller
Title: City Administrator
Date: 7/21/26
EJCDC® C-111, Advertisement for Bids for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,
and American Society of Civil Engineers. All rights reserved.
Page 2 of 2
INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT
TABLE OF CONTENTS
Page
Article 1— Defined Terms............................................................................................................................. 1
Article 2— Bidding Documents ..................................................................................................................... 1
Article 3— Qualifications of Bidders ............................................................................................................. 2
Article 4— Pre-Bid Conference ..................................................................................................................... 2
Article 5— Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;
Other Work at the Site.................................................................................................................................. 3
Article 6— Bidder’s Representations and Certifications............................................................................... 4
Article 7— Interpretations and Addenda ..................................................................................................... 4
Article 8— Bid Security ................................................................................................................................. 5
Article 9— Contract Times ............................................................................................................................ 5
Article 10— Substitute and “Or Equal” Items............................................................................................... 5
Article 11— Subcontractors, Suppliers, and Others ..................................................................................... 6
Article 12— Preparation of Bid ..................................................................................................................... 6
Article 13— Basis of Bid ................................................................................................................................ 7
Article 14— Submittal of Bid......................................................................................................................... 8
Article 15— Modification and Withdrawal of Bid......................................................................................... 8
Article 16— Opening of Bids ......................................................................................................................... 9
Article 17— Bids to Remain Subject to Acceptance ..................................................................................... 9
Article 18— Evaluation of Bids and Award of Contract ................................................................................ 9
Article 19— Bonds and Insurance............................................................................................................... 10
Article 20— Signing of Agreement.............................................................................................................. 10
Article 21— Sales and Use Taxes ................................................................................................................ 11
Article 22— Contracts to Be Assigned ........................................................................................................ 11
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,
and American Society of Civil Engineers. All rights reserved.
TOC Page1 of 1