Renovation of the Residence Hot/Cold Water/Sewer System for US Embassy TBILISI Residence

Location: Federal
Posted: Oct 15, 2025
Agency: STATE, DEPARTMENT OF
Type of Contract: Awards
Type of Government: Federal
Category:
  • Y - Construction of Structures and Facilities
  • Z - Maintenance, Repair or Alteration of Real Property
Solicitation No: 19GG8025P0682
Publication URL: To access bid details, please log in.
Follow
Renovation of the Residence Hot/Cold Water/Sewer System for US Embassy TBILISI Residence
Active
Contract Opportunity
Notice ID
19GG8025P0682
Related Notice
Contract Line Item Number
Department/Ind. Agency
STATE, DEPARTMENT OF
Sub-tier
STATE, DEPARTMENT OF
Office
US EMBASSY TBILISI
Award Details
  • Contract Award Date: Sep 26, 2025
  • Contract Award Number: 19GG8025P0682
  • Task/Delivery Order Number:
  • Contractor Awarded Unique Entity ID: NQS1GGBJC9P1
  • Contractor Awarded Name: Rapid Solutions Georgia LLC
  • Contractor Awarded Address: Tbilisi GEO
  • Base and All Options Value (Total Contract Value): $48,700.00
General Information View Changes
  • Contract Opportunity Type: Award Notice (Updated)
  • Updated Published Date: Oct 15, 2025 08:43 am EDT
  • Original Published Date: Oct 15, 2025 08:40 am EDT
  • Inactive Policy: Manual
  • Updated Inactive Date: Mar 01, 2026
  • Original Inactive Date: Mar 01, 2026
  • Initiative:
    • None
Classification
  • Original Set Aside:
  • Product Service Code:
  • NAICS Code:
    • 2361 - Residential Building Construction
  • Place of Performance:
    GEO
Description

The U.S Embassy Tbilisi would like to renovate the domestic hot/cold water/sewer systems at the Residence by replacing the existing old pipes. This renovation aims to enhance the functionality, safety, and energy efficiency of the residence.

Work is to be performed at Tbilisi, Georgia, 26 Nikoloz Beradze str. Dighomi 9, Tbilisi, Georgia. The contract type is firm-fixed price.

B. SCOPE OF WORK

The Contractor shall perform the work per details specified herein.

• The Embassy will host a pre-bid meetings and all interested parties must attend.

• The existing pipes will be renovated in accordance with technical requirements. The

contractor is responsible for providing renovation services according Design, Specification and

Explanatory Notes.

• Provide renovation sequences planning (staging plan) to meet the requirements indicated in

the Scope of Work and Design Project (should be done by contractor).

• Provide sufficient technical information (e.g. materials, shop drawings for temporary waiting

area and construction, etc.) for approval prior to renovation.

• Provide a complete set of as-built drawings of the project after completion.

Specific scope of works:

Project completion date estimate 30 calendar days.

Sanitary Facilities and Utility Areas (APPENDIX #2 with photo examples):

• Basement Level - 1 bathroom, laundry room, boiler room.

• Ground Floor: 2 bathrooms, kitchen with 2 connection points.

• Second Floor: 3 bathrooms and bar area.

• Third Floor: 1 bathroom.

1. Preparation Works:

• Development and approval of the working project.

• Arrangement of temporary water supply in the basement.

5

2. Dismantling Works:

• Removal of existing screed in bathrooms.

• Dismantling of old cold and hot water supply pipelines, as well as sewer

lines (in agreed areas).

• Disposal of construction waste and dismantled pipes.

3. Preparation of Routes for New Utilities:

• Wall chasing and floor cutting for pipe routing.

• Drilling of holes for pipe passage through slabs and walls.

• Creation of openings and embeds in the basement for main pipelines (core

drilling).

4. Installation of New Utilities:

• Installation of cold water, hot water, and hot water recirculation mains

(risers and floor distribution).

• Installation of sewer pipes on floors (excluding basement).

• Installation of regulating valves (if required).

• Installation of shut-off valves for independent isolation of each bathroom

and water supply branch (valves visible to users must be provided with decorative

covers).

• All sanitary fixture connection nodes must be fixed properly.

• Installation of pipe thermal insulation (in basement and shafts).

• Sealing of penetrations through walls and slabs.

5. Testing and Commissioning:

• Hydraulic pressure testing of cold and hot water supply systems.

• Testing of sewer system for tightness and correct slope.


Attachments/Links
Contact Information View Changes
Contracting Office Address
  • DEPARTMENT OF STATE, 2201 C ST NW
  • WASHINGTON , DC 20520
  • USA
Primary Point of Contact
Secondary Point of Contact
History
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

...improvements: REPLACEMENT OF EXISTING WASTEWATER LIFT STATION NO. 1 AND NEW FORCE MAINS ...

MPN

Bid Due: 6/13/2077

...and Specs Order Form Project Name: 2023 CWSRF Sanitary Sewer Rehabilitation Plan Deposit: ...

Goodwyn Mills Cawood(GMC)

Bid Due: 6/18/2026

..., or USPS delivery directly to Kade Campbell, P.E. , The Water Works ...

Goodwyn Mills Cawood(GMC)

Bid Due: 6/11/2026

...for the construction of approximately 6,503 linear feet of 8-inch gravity sanitary sewer ...

San Antonio Water System

Bid Due: 6/23/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.