DA00645 Addendum #1
3) How are the floating barges to be relocated to the Mann's Harbor shipyard?
Answer: After dewatering, floating barges may be transported via land or water. The Contractor shall
determine the means and method for transporting. The proposed method will need to be pre-approved by
the Ferry Division. Note that barges may be broken apart into smaller segments prior to relocating,
which must occur prior to use of Shipyard crane (see question 4, below).
4) When will laydown and staging areas be available?
Answer: All staging areas will become available on September 14, 2026. At Hatteras, the smaller area
within the access gate can be made available sooner; access and date must be coordinated with the Ferry
Division in advance. Note, Contractor will be responsible for repairing any damage to the facilities,
including asphalt.
5) What are the access and coordination requirements for Silver Lake?
Answer: Perimeter fencing is not present at Silver Lake. However, similar to Hatteras, all work will
require prior coordination with the Ferry Division.
6) What are the access and coordination requirements for removing the existing materials from South
Dock?
Answer: This is within a secure area; prior coordination with the Ferry Division and a TWIC card will be
required.
7) Which items from South Dock, if any, are to be delivered to the Mann's Harbor Shipyard?
Answer: The aluminum railings currently located at South Dock must be disconnected from the existing
barges and delivered to the Shipyard. All other items identified for removal will become the property of
the Contractor.
Submitted Questions:
8) Concrete-Related Questions:
A. To allow for longer concrete placement window, is it acceptable to use retarder?
B. With the distance from the plant for both of these locations, [Supplier] will not be held liable for out
of spec concrete related to time or temp... NCDOT is generally good about making concessions on
these
C. It will be challenging placing concrete at the Ocracoke side due to travel time. If concrete cannot be
put to sleep is it acceptable to use bagged concrete?
Answer to Grouping of Above Three Questions: Hydration controlling admixtures (not retarders), such as
Sika-440, may be allowable to put the concrete "to sleep" for up to 6 hours. Contractor will be required
to submit this as part of mix design process post-award. Volumetric trucks are also approved but for
Class B only. Bagged mixes are not acceptable for structural applications. Time and temperature
acceptance will be at the discretion of the Engineer.
Page 2 of 7
DA00645 Addendum #1
9) Are test piles/ lateral load testing of the fender piles required?
Answer: No, these are not required.
10) Can a vibratory hammer be used to install piles or will piles be required to be impacted?
Answer: In accordance with the Special Provisions, a sufficiently sized vibratory or impact hammer shall
be used to install piles. All pile installations shall be attempted first with a vibratory hammer. The need
for an impact hammer is not anticipated, but it may be required to install piles to the target tip elevation.
The special provision requires that the contractor prepare and submit a wave equation analysis and report
that shall be used to assess the capability of the proposed driving system to install the piles.
11) Can you provide information on the King pile to be demolished?
Answer: Piles to be demolished are the existing floating dock guide and king piles. Guide piles are 30" in
diameter, have tip elevation of -60.5' NAVD88 and are filled with sand. King piles are 24" in diameter,
have a tip elevation of -58.0' NAVD88 and are filled with sand.
12) Ocracoke sheet M-301 calls out railing as wood. Sheet M-502 calls for Aluminum.
Answer: Aluminum is the correct material to be used; a revised sheet M-301 will be issued in a
subsequent addendum.
13) What portion of the steel pipe pile is to be coated?
Answer: At a minimum, steel pipe piles shall be coated as follows: Ocracoke - from cutoff elevation to
15'-0" MLLW, Hatteras - from cutoff elevation to -17'-0" MLLW.
14) Can you provide a supplier for the piles and lumber? My suppliers cannot meet the requirements for .60
cca, kiln dried MC-19, nor can they provide Dense/Select piles.
Answer: Unfortunately, we are not able to specify suppliers. However, this question was only received by
a single bidder.
15) Is the top rail aluminum? Dimension on drawing says" 2-5/8" in text but 3" in section. Which one? 2-5/8"
is available.
Answer: 2-5/8" is the correct dimension for the aluminum top rail. A revised detail will be issued in a
subsequent addendum.
16) Can we use 2" X 2" rail posts? No readily available top bar for 2-1/2" posts.
Answer: Yes, the 2" x 2" rail posts can be used. 2-1/2" posts were specified because they are generally
commercially available and preferred; please note, this question was only received by a single bidder.
17) What is the finish for the railings? Powder coated? Mill?
Answer: The railing finish shall be baked-on powder coated.
18) Ocracoke M-102 Bumper Piles, please confirm lengths are correct.
Answer: Lengths for bumper piles (6 total locations) were incorrect and have been updated. Plumb piles
have a length of 64.00' and batter piles a length of 64.22'.
Page 3 of 7
DA00645 Addendum #1
19) Sheet G-002 Steel Pile Note 3. Where can I find Technical Specification Section 31 62 16?
Answer: Technical Specification Section 31 62 16 is not applicable to this project. Refer to Ferry Special
Provisions (Steel Fender Piles) included in contract documents.
20) Questions Related to Spoil Site:
A. Please specify where the offload/ offshore site is.
B. Please specify where the spoil site is (offshore and inshore).
Answer to Grouping of Above Two Questions: The upland disposal site for the dredged material is located
on the north end of Ocracoke. Exhibit 1 has been posted to the project file on the Division 1
advertisement page indicates a location map for the disposal site. The specific location within the
disposal site where spoils are to be placed will be determined at the time of dredging due to ongoing
dredging operations prior to project; coordination with Ferry Division will be required prior to placement.
21) Will special accommodation be available to utilize vehicle ferry for concrete placement days? Can these
occur at night or off hours?
Answer: Ferry Division will accommodate construction vehicle travel based on the published ferry
schedule.
22) Is dredge material hazardous?
Answer: To our knowledge, none of the dredge material is hazardous. NCDOT permitted spoil site does
not require hazardous material testing.
23) Has a soil test of the dredge material been performed to confirm no contaminated soils?
Answer: Borings were taken from basin during monopile design project but were not explicitly tested for
contamination. However, testing is not required for dredge spoils on this project.
24) What is the vehicle weight limit of the ferry?
Answer: If a vehicle is a typical road-legal weight, it can be accommodated on the published vehicle
schedule. Ferries can accommodate overweight vehicles if they meet the road-legal requirements of
overweight vehicles. If vehicles are overweight, additional scheduling accommodation will be required;
coordination with Ferry Division will be needed. This is in addition to standard overweight permits
needed for roadway travel.
25) Is it acceptable to take material deliveries i.e. piles, lumber etc. from existing bulkhead?
Answer: At Hatteras, materials can be delivered from land to water via the bulkhead. However, at
Ocracoke, access is more limited; unloading at Silver Lake will need to occur from the parking lot
immediately in front of passenger ferry docking location. Delivery from water to land is also acceptable
at both locations with the above consideration for Silver Lake.
26) Is there Environmental Permit TOYR for in-water work?
Answer: Yes, there are time of year restrictions for in-water work from April 1 through September 30
each year. The project schedule has been developed with this in mind, and these restrictions are therefore
not anticipated to impact the project's availability.
Page 4 of 7
DA00645 Addendum #1
27) Nationwide permit in bid documents expired 3/14/26. Has permit been renewed?
Answer: Permit is valid through 03/14/2027.
28) Can you provide the geotechnical report by Caitlin Engineers to bidders?
Answer: Yes; the reports have been posted to the project file on the Division 1 advertisement page.
29) Floating Barge Weight Questions:
A. What is the bare weight of the Poseidon barge?
B. Can the plans/specs and weights for the existing temporary floating dock/barges be provided?
The following answer applies to the above-two questions: Please reference the Poseidon plan sheets that
have been posted to the project file on the Division 1 advertisement page.
30) Will basin area be closed off to boat traffic during dredging? If not, how is contractor to manage turbidity
curtain and monitoring?
Answer: Basin will not be closed to all boat traffic during dredging operations. However, the Ferry
Division will coordinate with the contractor to allow for operations to occur and to accomplish project
goals. Placement and maintenance of turbidity curtains will be coordinated at that time. Note that the
project is occurring outside of peak ferry schedules.
31) Please confirm where temporary floating docks are to be taken to? Are these going to be unloaded by
NCDOT or the contractor?
Answer: Floating docks are to be delivered to the NCDOT Ferry Division Shipyard located at 8550
Shipyard Rd, Manns Harbor, NC 27953. The Shipyard will use its existing crane to unload the barges.
The barges must be broken apart into smaller segments and dewatered prior to use of the Shipyard crane,
which has a maximum capacity of 50 TON.
32) The permitted dredge depth and design dredge depth are both 10' MLLW. Typically, a tolerance is
provided between the max permitted and design depths to accommodate unavoidable inaccuracies in the
dredging process. Will the State consider raising the design dredge depth to 9' MLLW with 1' of
allowable and payable overdepth.
Answer: In accordance with the Special Provisions to facilitate dredging down to the required depth, the
Contractor may disturb one (1) foot below the required dredging depth provided. Refer to the Special
Provisions (Dredging) for additional information.
33) Is hydraulic dredging acceptable, and if so, can a disposal line be run from the dredge to an approved
offshore disposal site?
Answer: If the Contractor can identify and permit an offshore disposal site within the project timeline,
hydraulic dredging would be acceptable and a disposal line could be run with agency approval.
Contractor would also be responsible for determining acceptability of material for offshore disposal.
Page 5 of 7
DA00645 Addendum #1
34) Measurement of payment indicates dredge material will be paid based on truck measurements. If
contractors means and methods doesn't involve trucks to carry material to the disposal site, will a pre and
post survey be performed by the owner to verify quantities for payment?
Answer: Yes, NCDOT will conduct a pre- and post-dredging survey at the fill site as means of payment if
alternative methods are used. If an offshore spoil site is utilized, a bathymetric or hydro survey will be
utilized.
35) Please specify if buy America(n) is required for this project.
Answer: Project has federal funding; therefore, Buy American is required. This is addressed in project
special provisions.
36) Can equivalent fenders be used in lieu of Trelleborg?
Answer: Yes, but fenders shall meet the requirements indicated in the Special Provisions. Fender material
shall be new vulcanized rubber.
37) Will survey data be provided to bidders?
Answer: Survey of the Hatteras Basin is available from 2024 and has been posted to the project file on the
Division 1 advertisement page.
38) Can you provide bidders with a map showing location of dredge spoils area and transfer area, from barge
to truck, on Ocracoke? Is there are particular area within the pit that these materials are to be placed? Will
any other dredge project be using this spoil site during this contract?
Answer: No other projects are anticipated to use the spoil site at this time, but emergency dredging
operations may arise; in these cases, Ferry Division will coordinate with the Contractor.
39) Regarding the permitted dredge material disposal area at the South Dock Spoil Site, can more
information be provided for this site such as location, proposed transfer area, capacity, effluent
management devices, and tipping fees, if any?
Answer: Exhibit 1 has been posted to the project file on the Division 1 advertisement page which
indicates the disposal site and transferred area. The proposed transfer area is envisioned to occur at South
Dock at the location where the old ramp section is to be removed; Contractor may propose alternative
locations and approaches. Capacity of spoil site will be greater than quantity of material dredged.
Effluent management will not be applicable to this project, unless pumping slurry from hopper barge to
the spoil site. In this case, contractor shall propose management practices. Contractor will not be
responsible for tipping fees.
40) Please highlight contractor laydown.
Answer: Exhibit 2 and Exhibit 3 have been posted to the project file on the Division 1 advertisement
page which indicates the lay-down areas for the Ocracoke and Hatteras site, respectively.
41) Is concrete testing required to be handled by the contractor?
Answer: NCDOT will perform concrete testing.
Page 6 of 7
DA00645 Addendum #1
42) As we are currently soliciting quotes from various subcontractors and awaiting their responses, would it
be possible to extend the bid date by one to two weeks? This extension would allow sufficient time to
receive accurate and competitive pricing.
Answer: The Department will maintain the current let schedule (bids remain due at 2:00pm on April 15,
2026).
Reference materials are available in the project folder under 'Additional Information, Referenced in Addendum
1.zip'.
https://connect.ncdot.gov/letting/Pages/Letting-List.aspx?let_type=1&let_status=Advertised
Sincerely,
Mark S. Winslow
Division Contract Engineer
Cc: R. K. Sawyer, PE
M. B. Gill, PE
B. N. Braswell, PE
D. B. Otts, PE
C. A. Spear, PE
J. E. Dixon
C. D. Peele
Page 7 of 7
REVISED 4/09/2026
DA00645 FF-0001A FEDERAL
TABLE OF CONTENTS
COVER SHEET
PROPOSAL SHEET
PROJECT SPECIAL PROVISIONS
MANDATORY PRE-BID CONFERENCE (Prequalifying To Bid): ...................................................... G-1
BIDS OVER LIMIT: ................................................................................................................................ G-2
DIVISION LET CONTRACT PREQUALIFICATION: .......................................................................... G-2
BOND REQUIREMENTS: ...................................................................................................................... G-2
CONTRACTOR CLAIM SUBMITTAL FORM: .................................................................................... G-2
BUILD AMERICA, BUY AMERICA (BABA): ..................................................................................... G-2
CONTRACT TIME AND LIQUIDATED DAMAGES: ......................................................................... G-7
INTERMEDIATE CONTRACT TIME NUMBER 1 AND LIQUIDATED DAMAGES: ...................... G-7
INTERMEDIATE CONTRACT TIME NUMBER 2 AND LIQUIDATED DAMAGES: ...................... G-7
PROSECUTION OF WORK: ................................................................................................................... G-8
MAJOR CONTRACT ITEMS: ................................................................................................................ G-8
SPECIALTY ITEMS: ............................................................................................................................... G-8
STEEL PRICE ADJUSTMENT: .............................................................................................................. G-8
DISADVANTAGED BUSINESS ENTERPRISE (DIVISIONS): ......................................................... G-20
CERTIFICATION FOR FEDERAL-AID CONTRACTS: .................................................................... G-34
RESTRICTIONS ON ITS EQUIPMENT AND SERVICES: ................................................................ G-34
USE OF UNMANNED AIRCRAFT SYSTEM (UAS): ........................................................................ G-34
EQUIPMENT IDLING GUIDELINES: ................................................................................................. G-35
U.S. DEPARTMENT OF TRANSPORTATION HOTLINE: ............................................................... G-36
COOPERATION BETWEEN CONTRACTORS: ................................................................................. G-36
TWELVE MONTH GUARANTEE: ...................................................................................................... G-36
NOTES TO CONTRACTOR: ................................................................................................................ G-37
TRANSPORTATION WORKER IDENTIFICATION CREDENTIAL (TWIC) CARD: ..................... G-37
ROADWAY .............................................................................................................................................. R-1
STANDARD SPECIAL PROVISIONS
AVAILABILITY OF FUNDS - TERMINATION OF CONTRACTS ............................................... SSP-1
NCDOT GENERAL SEED SPECIFICATION FOR SEED QUALITY ............................................. SSP-2
ERRATA .............................................................................................................................................. SSP-5
PLANT AND PEST QUARANTINES ................................................................................................ SSP-8
TITLE VI AND NONDISCRIMINATION: ......................................................................................... SSP-9
MINORITY AND FEMALE EMPLOYMENT REQUIREMENTS.................................................. SSP-18
REQUIRED CONTRACT PROVISIONS FEDERAL-AID CONSTR CONTRACTS ..................... SSP-21
ON-THE-JOB TRAINING ................................................................................................................. SSP-35
MINIMUM WAGES .......................................................................................................................... SSP-38
UNIT PROJECT SPECIAL PROVISIONS
FERRY DIVISION SPECIAL PROVISIONS ....................................................................................... FD-1
PERMITS ................................................................................................................................................. P-1
PROPOSAL ITEM SHEET
ITEM SHEET(S)
REVISED 4/09/2026
DA00645 FF-0001A G-37 FEDERAL
routine maintenance activities (i.e. mowing grass, debris removal, ruts in earth shoulders,) are
not parts of this guarantee.
Appropriate provisions of the payment and/or performance bonds shall cover this guarantee for
the project.
To ensure uniform application statewide the Division Engineer will forward details regarding the
circumstances surrounding any proposed guarantee repairs to the Chief Engineer for review and
approval prior to the work being performed.
NOTES TO CONTRACTOR:
(8-19-25) SP1G999B
COMMITMENTS FROM PROJECT DEVELOPMENT AND DESIGN
*Any construction associated with the project will follow the U.S. Fish and Wildlife Service (USFWS)
Raleigh Field Office "Guidelines for Avoiding Impacts to West Indian Manatee" to avoid impacts to the
manatee.
*NCDOT will continue to coordinate with the National Park Service (NPS) throughout the development
and implementation of the project to obtain a Special Use Permit and ensure compliance with NPS
policy/regulations.
*Should construction unearth cultural resources, work will be stopped in the area of
discovery and the park will consult with the State Historic Preservation Officer and the in
accordance with 36 CFR 800.13, Post Review Discoveries. In the unlikely event that
human remains are discovered during construction, provisions outlined in the Native
American Graves Protection and Repatriation Act (1990) will be followed
*-Per Green Sheet Commitments.
TRANSPORTATION WORKER IDENTIFICATION CREDENTIAL (TWIC) CARD:
Contractor personnel requiring unescorted access to secure or restricted areas of ferry vessels or
facilities shall possess a valid Transportation Worker Identification Credential (TWIC) card in
accordance with 49 CFR Part 1572, Transportation Security Administration (TSA), and U.S.
Coast Guard requirements. Personnel without a TWIC card may access these areas only when
properly escorted in accordance with facility security protocols.

With GovernmentContracts, you can:
Follow Multiple Building Fire Exhaust Systems Repairs Active Contract Opportunity Notice ID N4008526R9059
DEPT OF DEFENSE
Bid Due: 8/05/2026
Follow 43d Air Mobility Squadron_ Request for Proposal_FA445226R0012_B753 Kitchen Renovation Active Contract Opportunity
DEPT OF DEFENSE
Bid Due: 8/05/2026
Follow Multiple Base-wide Location Fencing Repairs Active Contract Opportunity Notice ID N4008524R9072 Related
DEPT OF DEFENSE
Bid Due: 8/20/2026
Project: Federal Pipe Video Contracts Ref. #: 269- 2026-235 Department: City Procurement Type:
City of Charlotte
Bid Due: 8/24/2026