Mckinley, Hazelton & Elmwood Playgrounds Project - IFB 26-06 Addendum #1

Location: California
Posted: Oct 9, 2026
Due: Oct 20, 2026
Agency: Stockton Unified School District
Type of Government: State & Local
Category:
  • B - Special Studies and Analyses - Not R&D
Publication URL: To access bid details, please log in.
  • Mckinley, Hazelton & Elmwood Playgrounds Project - IFB 26-06

    LLB RFQP - Mckinley, Hazelton & Elmwood Playgrounds

    LLB Contract - Mckinley, Hazelton & Elmwood Playgrounds

    Drawings - Elmwood Playground

    Drawings - LCAP Hazelton Playground

    Drawings - Mckinley Burned Playground

    Drawings - LCAP Mckinley Playground

    Project Manual - Elmwood Playground

    Project Manual - LCAP MCkinley Playground

    Project Manual - Mckinley Burned Playground

    Project Manual - LCAP Hazelton Playground

    Project Labor Agreement

    Job Sign-In Sheet

    Addendum #1 McKinley, Hazelton & Elmwood Playgrounds Project - IFB 26-06

  • Attachment Preview

    Project Name: Hazelton LCAP Playground Project Mckinley LCAP Playground Project Mckinley Burned Elmwood Playground Project
    Playground
    Replacement Project
    Location 535 W. JEFFERSON ST. , STOCKTON CA, 95206 30 W. Ninth St. Stockton, CA 95206 30 W. Ninth St. Stockton, CA 95206 840 S CARDINAL AVENUE, STOCKTON CA.95215
    Arch 2024-06H 2024-06M 2025-06 2025-07
    Project
    No.
    DSA 02-124154 02-123447 02-123616 02-124201
    APPL No.
    DSA PTN: 68676-372 68676-373 68676-387 68676-405
    Project
    Name:
    Hazelton LCAP
    Playground Project
    Mckinley LCAP
    Playground Project
    Elmwood Playground
    Project
    56 S Lincoln St.
    Stockton, CA 95203

    LLB Playground Projects at Hazelton, McKinley, and 2024-06, 2025-06, 2025-07
    Elmwood Elementary Schools
    STOCKTON UNIFIED SCHOOL DISTRICT 10/26
    ADDENDUM #1
    FROM : ARCHITECHNICA
    555 W. BENJAMIN HOLT DRIVE
    SUITE 423
    STOCKTON, CA 95207
    (209) 952-5850 FAX (209) 952-2442
    REF. # : District Project No. #IFB 26-06
    DSA FILE # 39-69
    Project Hazelton LCAP Mckinley LCAP Mckinley Burned Elmwood Playground
    Name: Playground Project Playground Project Playground Project
    Replacement Project
    Location 535 W. JEFFERSON 30 W. Ninth St. 30 W. Ninth St. 840 S CARDINAL
    ST. , STOCKTON CA, Stockton, CA 95206 Stockton, CA 95206 AVENUE,
    95206 STOCKTON
    CA.95215
    Arch 2024-06H 2024-06M 2025-06 2025-07
    Project
    No.
    DSA 02-124154 02-123447 02-123616 02-124201
    APPL No.
    DSA PTN: 68676-372 68676-373 68676-387 68676-405
    OPSC NO. : n/a
    OWNER : Stockton Unified School District
    56 S Lincoln St.
    Stockton, CA 95203
    DATE : October 9, 2026
    NOTICE TO ALL BIDDERS
    IT IS THE PURPOSE AND INTENT OF THIS ADDENDUM TO MODIFY AND/OR CLARIFY THE
    DRAWINGS AND SPECIFICATIONS FOR THIS PROJECT AND THIS ADDENDUM SHALL BECOME
    A PART OF THE CONTRACT DOCUMENTS. THESE CHANGES AND/OR INTERPRETATIONS
    SHALL BE INCORPORATED INTO YOUR BID.
    REFER TO PROJECT PLANS AND SPECIFICATIONS PREPARED BY ARCHITECHNICA, DSA
    APPROVED JULY 13, 2026 (HAZELTON LCAP PLAYGROUND PROJECT DSA# 02-124154),
    OCTOBER 28, 2025 (MCKINLEY LCAP PLAYGROUND PORJECT DSA# 02-123447), NOVEMEBR 5,
    2025 (MCKINLEY BURNED PLAYGROUND REPLACMENT PROJECT DSA # 02-123616), AND
    AUGUST 20, 2026 (ELMWOOD PLAYGROUND PROJECT DSA #02-124201).
    ITEM 1 Job Walk Sign-In Sheet
    Attached is the Sign-in Sheet for the Mandatory Job Walk that took place on
    Thursday, October 1, 2026 at 10:00 AM. Only the general contractors that
    attended the Mandatory may bid on the project. Sign in sheets can also be
    found at https://www.stocktonusd.net/projects-out-to-bid.
    Page 1 of 6 pages

    LLB Playground Projects at Hazelton, McKinley, and 2024-06, 2025-06, 2025-07
    Elmwood Elementary Schools
    STOCKTON UNIFIED SCHOOL DISTRICT 10/26
    ADDENDUM #1
    ITEM 2 Questions from Proposer
    Q: May I please request the engineer's estimate for this project?
    A: Per Appendix A in LLB RFQP - McKinley, Hazelton & Elmwood Playgrounds
    document available from the District's Website, the project estimate is
    $3,000,000 (Three Million Dollars) to $4,000,000 (Four Million Dollars).
    Q: Can you please tell me the duration of the project?
    A: The duration of the project will be at least 120 Calendar Days.
    Q: When is the project expected to start and be completed?
    A: Approval of the LLB GMP is expected in January 2027. Completion of the project
    is anticipated to be July 16, 2027.
    ITEM 3 Questions from Proposer
    Reference: Facilities Lease, Exhibit D, Sections 1.8.9, 6.14.7 and 6.16.1 (pages 10,
    21 and 23); Facilities Lease, Section 15.1.5.1, Builder's Risk (page 19); RFQ/P
    Appendix A. Section 1.8.9 keeps title to new materials and equipment "and attendant
    liability for its protection and safety" with the Developer "until incorporated in the
    Work of the Contract Documents and accepted by District," and Section 6.14.7
    states "All Work shall be solely at Developer's risk." Section 15.1.5.1 requires
    Builder's Risk that includes "vandalism and/or malicious mischief (both without any
    limitation regarding vacancy or occupancy)" and "theft."
    Q: Please confirm the Developer bears theft, vandalism and fire losses to the
    playground equipment and shade structures it procures under Appendix A,
    and to installed Work at all three schools, until final acceptance, including
    the Builder's Risk deductible on each occurrence.
    A: Yes.
    Q: Please confirm the maximum Builder's Risk deductible the District will
    accept for theft and vandalism losses.
    A: $100,000.00 (One Hundred Thousand Dollars and no cents).
    Page 2 of 6 pages

    LLB Playground Projects at Hazelton, McKinley, and 2024-06, 2025-06, 2025-07
    Elmwood Elementary Schools
    STOCKTON UNIFIED SCHOOL DISTRICT 10/26
    ADDENDUM #1
    ITEM 4 Question from Proposer
    Reference: RFQ/P Appendix A, McKinley Burned Playground Replacement;
    Facilities Lease, Exhibit D, Sections 6.14.1 and 6.7.2.1.9 (pages 21 and 17);
    McKinley LCAP drawings, sheet TO1, Demolition Notes 1, 6 and 7; sheets ER1
    (Elmwood, McKinley LCAP, McKinley Burned). Appendix A calls for "Replacement of
    existing play structure burned in a fire" at McKinley, and Section 6.14.1 makes the
    Developer responsible for "safety of all persons and property during performance of
    the Work" "continuously and not be limited to normal working hours." Section
    6.7.2.1.9 requires "Daily verification the Project is properly secured from the public
    and unauthorized entry," while McKinley sheet TO1 directs "CONTRACTOR TO
    REMOVE EXISTING GATE," "CONTRACTOR TO REMOVE SLIDING GATE" and
    "CONTRACTOR TO REMOVE CHAIN LINK FENCE."
    Q: Please confirm the Developer must keep each of the three school work
    areas, including the "STORAGE / MAINTENANCE / AND FUELING
    AREA" shown on the ER1 sheets, secured against unauthorized entry
    during all non-working hours, including nights, weekends and school
    breaks, from mobilization until final acceptance.
    A: Yes.
    ITEM 5 Questions from Proposer
    Reference: RFQ/P Appendix C-4, Allowable General Condition Costs, Temporary
    Facilities, items 9, 18 and 19; RFQ/P Tab 8, Pricing and Contingency (page 13).
    Appendix C-4 lists "Temporary Fencing/Enclosures," "Security (Guards, Cameras)"
    and "Watchman Service (Fire/Utility watch)" as General Conditions costs, and Tab 8
    evaluates each Respondent's "general conditions cost."
    Q: Please confirm Respondents should carry Appendix C-4 item 18, Security
    (Guards, Cameras), in their general conditions cost for all three schools
    through the July 16, 2027 completion date.
    Q: If not, please confirm whether the District would carry construction site
    security as an allowance within the GMP.
    A: Security shall be included in the General Conditions Cost.
    ITEM 6 Questions from Proposer
    Per RFQ/P document, each submittal is limited to 30 single-sided pages excluding
    front and back covers, tabs, certificates, schedule charts, and comments under Tab
    11.
    Q: Can we also exclude the following in the total page count:
    Page 3 of 6 pages

    LLB Playground Projects at Hazelton, McKinley, and 2024-06, 2025-06, 2025-07
    Elmwood Elementary Schools
    STOCKTON UNIFIED SCHOOL DISTRICT 10/26
    ADDENDUM #1
    a. Resumes of Key Personnel under Tab 4, Respondent Information.
    b. List of Projects under Tab 6, Prior Relevant Experience.
    A: Yes. Please include in an Appendix
    ITEM 7 Questions from Proposer
    Q: Can an Appendix Section that doesn't count towards the page limit be
    used for other attachments and information relevant to the response.
    A: Yes
    ITEM 8 Question from Proposer
    Q: Please confirm whether team member resumes are intended to be
    included within the 30-page limit, or if resumes may be submitted as
    supporting materials outside of the page count.
    A: Please see Item 6.
    ITEM 9 Questions from Proposer
    Q: Will the District accept proposal materials such as site logistics plans and
    detail schedules submitted on 11x17 inch pages?
    A: Yes.
    Q: If permitted, please confirm whether these exhibits may be excluded from
    the 30-page limit as well.
    A: Yes. Please include in the Appendix.
    ITEM 10 Question from Proposer
    Q: Please confirm whether the appendices included in Tab 4 (C-1, C-2, C-3)
    are intended to be included within the 30-page limit, or if they may be
    excluded as supporting materials.
    A: They may be excluded from the 30-page limit and included in the
    Appendix.
    Page 4 of 6 pages

    LLB Playground Projects at Hazelton, McKinley, and 2024-06, 2025-06, 2025-07
    Elmwood Elementary Schools
    STOCKTON UNIFIED SCHOOL DISTRICT 10/26
    ADDENDUM #1
    ITEM 11 Question from Proposer
    Q: Tab 4.l requests Certificates of Insurance, while Tab 9 requests an
    Insurance Carrier/Broker Letter of Insurability. Please confirm whether the
    Tab 9 Insurance Letter is excluded from the 30-page limit alongside the
    Certificate of Insurance.
    A: Please remove Tab 4.l and include the Certificates of Insurance in the
    Appendix. The Insurance Carrier/Broker Letter of Insurability shall be
    included under Tab 9 and it counts towards the 30-page limit.
    ITEM 12 Question from Proposer
    Q: Please confirm whether the Table of Contents required under Tab 2 in
    intended to be included within the 30-page limit or may be excluded from
    the page count.
    A: The Table of Contents may be excluded from the 30-page limit page
    count.
    ITEM 13 Question from Proposer
    Q: Please provide the approximate construction start date to help identify
    Preconstruction Duration and Construction Start.
    A: Please see Item 2
    ITEM 14 Question from Proposer
    Q: Please confirm Tab 8 - Pricing and Contingency, item 4 - Respondent's
    Fee is to include Builders Risk for the Project.
    A: The District will allow the deferral of Builders Risk to time of GMP.
    ITEM 15 Question from Proposer
    Q: Tab 8 - Pricing and Contingency, Item 3 - Is it acceptable to submit the
    General Conditions as a Monthly Cost? Start dates sometimes
    change/adjust.
    A: General Conditions Cost shall be provided as a monthly cost only.
    Page 5 of 6 pages

    LLB Playground Projects at Hazelton, McKinley, and 2024-06, 2025-06, 2025-07
    Elmwood Elementary Schools
    STOCKTON UNIFIED SCHOOL DISTRICT 10/26
    ADDENDUM #1
    ITEM 16 Question from Proposer
    Q: Tab 8 - Pricing and Contingency, Item 5 - Construction Contingency. For
    the purposes of evaluation, what percentage % should be include for the
    evaluation of this RFP? Is there a standard percentage we should show?
    And can this be shown as a percentage %?
    A: The percentage will be negotiated with the awarded Developer and
    included in their GMP.
    ITEM 17 Question from Proposer
    Q: Tab 8 - Pricing and Contingency, Item 6 - Can you please clarify if there
    are any Allowances the District wants us to carry at this time? Often there
    are negotiated at time of GMP development. Please confirm.
    A: Any Allowances will be determined and negotiated with the awarded
    Developer and included in their GMP.
    ITEM 18 Question from Proposer
    Q: Will the Award have all 3 projects under one contract agreement or
    because there are three sites there may be three agreements/leases?
    A: The 4 projects will be awarded to one developer as one agreement and
    one site lease. Each project has its own DSA number and each project will
    need to be priced and tracked for funding and DSA purposes.
    END OF ADDENDUM #1
    ARCHITECHNICA
    By
    Timothy Dearborn, AIA
    Architect
    Attachments: None
    Page 6 of 6 pages

    This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
    Daily notification on new contract opportunities

    With GovernmentContracts, you can:

    • Find more opportunities and win more business
    • Receive daily alerts for all new bid opportunities
    • Get contract opportunities matched to your business
    ONE WEEK FREE TRIAL

    See also

    Project Summary Project ID: TDS0001709 Federal No: HSIPL 5953(759) Project Name: San Gabriel

    La County

    Bid Due: 11/24/2026

    Bid No. 008-26/27 - Asphalt Improvement Project at Multiple Sites Notice Inviting Proposal

    Glendale Unified School District

    Bid Due: 11/17/2026

    Bid Title: EXTENDED: RFP for the Operation of a Homeless Services Facility Category:

    City of Patterson

    Bid Due: 11/05/2026

    Reference #: 26-07353. Name: American Sign Language Services Description: IEHP's Procurement Department is

    Inland Empire Health Plan

    Bid Due: 10/27/2026

    * Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.