Request for Quotations-Torringford School Replacement Chiller and Commissioning Services Addendum No. 1

Location: Connecticut
Posted: Jun 4, 2026
Due: Jun 9, 2026
Agency: Torrington Public School
Type of Government: State & Local
Category:
  • C - Architect and Engineering Services - Construction
Publication URL: To access bid details, please log in.

Request for Quotations-Torringford School Replacement Chiller and Commissioning Services

Attachment Preview

ADDENDUM NO. 1
Project: Torrington Board of Education—REQUEST FOR QUOTATIONS FOR TORRINGFORD
ELEMENTARY SCHOOL AIR-COOLED SCREW CHILLER REPLACEMENT
Purpose of this Addendum The purpose of this document is to answer requests for information, provide
Exhibit F, remove the heat trace tape from the bid to owner responsibility, clarify the amount of butterfly
valves, and clarify the BMS system responsibilities.
1. Requests for Information (RFI) Answers
●​ Question: Is a DAS prequalification certificate and bid statement required? Answer: No.
●​ Question: What is the retainage? Answer: 5% of each progress payment.
●​ Question: Are we required to provide preventative maintenance once the job is done? If so, for
how long? This would be separate from our 1-Year Workmanship Warranty. Answer: Not
required.
●​ Question: Under Commissioning and start up: System Flushing: Confirming the water loop was
properly flushed to prevent debris from clogging the chiller's heat exchangers. Typically this is
done for new systems unless there are existing issues. This could increase the cost. Can this be
added as an add on? Answer: Every component of the water loop and interconnected systems
accessed or impacted during this replacement—including all new piping, isolation valves, and the
boiler room's hydraulic assembly—must be properly flushed. This ensures the entire system is
clear of debris before the new chiller is commissioned to prevent clogging the heat exchangers.
2. Scope of Work Clarifications & Changes
●​ Valve Clarification: The contractor must furnish and install two (2) new gear-driven butterfly
valves for isolation on the lines going to the chiller unit barrel.
●​ Scope Removal: Remove from the scope of work: furnish and install new self-regulating heat
trace tape on the outside supply and return lines to the chiller unit barrel.
3. BMS System Clarification
Owner's/SNE BMS Responsibility:
●​ To provide a BACnet connection to the chiller.
●​ All low-voltage electrical work for the BMS connection.
●​ All programming and interfacing with the chiller and graphics.
●​ Provide startup assistance to the chiller manufacturer.
The RFQ bid shall include:
●​ Flow switches installed. Wired by SNE.
●​ BACnet card provided by manufacturer—interface connection by SNE.
●​ All coordination with SNE.
4. Exhibits
●​ Exhibit F: Provided (Form of Contract).
DESIGN-BUILD AGREEMENT AND GENERAL CONDITIONS
BETWEEN OWNER AND DESIGN-BUILDER
TABLE OF ARTICLES
1. ​ AGREEMENT
2. ​ GENERAL PROVISIONS
3. ​ DESIGN-BUILDER’S RESPONSIBILITIES
4. ​ OWNER’S RESPONSIBILITIES
5. ​ SUBCONTRACTS
6. ​ CONTRACT TIME
7. ​ CONTRACT PRICE
8. ​ CHANGES IN THE WORK
9. ​ PAYMENT
10. ​INDEMNITY, INSURANCE, AND BONDS
11. ​SUSPENSION, NOTICE TO CURE, AND TERMINATION
12.​ DISPUTE MITIGATION OR RESOLUTION
13.​ MISCELLANEOUS
14. ​CONTRACT DOCUMENTS
ARTICLE 1 AGREEMENT
This Agreement (“Agreement”) is made this [___] day of [MONTH] in the year 2026 (“Effective Date”) by and between the
OWNER (“Owner”): ​
TORRINGTON BOARD OF EDUCATION
50 MAJOR BESSE DRIVE
TORRINGTON, CT 06790
and the
DESIGN-BUILDER (“Design-Builder”): ​
[NAME]
[ADDRESS]
for services in connection with the following
PROJECT: Turnkey design, construction and installation, commissioning and start-up by Design-Builder of and for a new
air-cooled screw chiller unit (the “Chiller Unit”) for the Torringford Elementary School building (“Facility”), at the
Worksite
(as defined in Section 2.4.28) located 800 Charles Street, Torrington, CT 06790 (the “Property”).
ARTICLE 2 GENERAL PROVISIONS
2.1. TEAM RELATIONSHIP Design-Builder and Owner agree to proceed with the Project on the basis of trust, good faith,
and fair dealing. Design-Builder agrees to furnish or procure, as permitted by Applicable Law, the architectural and
engineering services set forth in this Agreement and the construction and administration of the Work.
2.1.1. Neither Design-Builder nor any of its agents, employees, or Subcontractors, shall act on behalf of or in the name of
Owner unless authorized in writing by Owner’s Representative.
2.2. ETHICS The Parties shall perform their obligations under this Agreement with integrity, and shall, at a minimum: (a)
avoid conflicts of interest; (b) promptly disclose to the other Party any conflicts of interest which may arise. Each Party
warrants that it has not and shall neither pay nor receive any contingent fees or gratuities to or from the other Party, including
its agents, officers and employees, Design Professional, Subcontractors, Sub-subcontractors, Suppliers or Separate
Contractors, or others for whose acts or omissions they may be liable, to secure preferential treatment.
1
2.3. DESIGN PROFESSIONAL Architectural and engineering services shall be provided or procured by licensed,
independent design professionals retained by Design-Builder, or furnished by licensed employees of Design-Builder, as
permitted by Applicable Law. The person(s) or entity(ies) providing architectural and/or engineering services shall be
referred to in this Agreement, collectively, as “Design Professional.” If a Design Professional is an independent design
professional, the architectural services and/or engineering services shall be procured pursuant to a separate written agreement
between Design-Builder and Design Professional.
2.3.1. STANDARD OF CARE Design Professional shall furnish and provide the architectural services and/or
engineering services necessary to design the Project in accordance with Owner’s requirements, as outlined in Owner’s
Program and other relevant data defining the Project. The architectural services and/or engineering services shall be
performed in accordance with the standard of professional skill and care required for a Project of similar size, scope, and
complexity, during the time in which the Services are provided.
2.4. DEFINITIONS
2.4.1. “Agencies” or an “Agency” mean and include the Connecticut Office of Policy and Management (“OPM”), the
Connecticut Commission on Human Rights and Opportunities (“CHRO”), and all other governmental authorities having
regulatory or administrative jurisdiction over the Work and/or the Project, and all representatives or designees of DAS,
CHRO, and such other governmental authorities.
2.4.2. “Agreement” means this Design-Build Agreement and General Conditions Between Owner and Design-Builder,
amendments, exhibits, addenda, and attachments made part of this Agreement upon its execution and/or upon the
execution of any amendment to this Agreement.
2.4.3. “Applicable Law” and “Applicable Laws” mean and include all federal, state, and local laws, statutes, regulations,
ordinances, codes, building codes, rules, and/or permits, and lawful orders enacted, promulgated or issued by any
governmental body or public or quasi-public authority having jurisdiction over the Work, Design-Builder, and/or the site
of the Project that are applicable to the Work, and with which Design-Builder must comply. “Applicable Law” shall
include, without limitation, those relating to equal opportunity, labor, wages and employment laws, statutes, ordinances,
codes, rules and regulations, and all guidelines, standards and conditions of funding imposed on the Work and/or Project
by the Agencies or otherwise applicable to the Project, the Agreement, any Subcontract and/or the performance of the
Work.
2.4.4. “Business Day” means all days, except weekends and official federal or state holidays where the Project is located.
2.4.5. A “Change Order” is a written order signed by Owner and Design-Builder after execution of this Agreement,
indicating changes in the scope of the Work or Contract Time, including substitutions proposed by Design-Builder and
accepted by Owner.
2.4.6. “Construction Schedule” is the document prepared by Design-Builder that specifies the dates on which
Design-Builder plans to begin and complete various parts of the construction phase services Work, and the Project,
including dates on which information and approvals are required from Owner.
2.4.7. The “Contract Documents” consist of those documents identified in section 14.1.
2.4.8. The “Contract Time” is the period of time beginning on and including the Date of Commencement through the
total time within which Design-Builder is required to achieve Substantial Completion established in Section 6.2.
2.4.9. “Day” and “day” mean calendar day.
2.4.10. “Date of Commencement” is as provided for in section 6.1.
2.4.11. “Defective Work” is any portion of the Work that is not in substantial conformance with the requirements of the
Contract Documents.
2.4.12. “Final Completion” occurs on the date when Design-Builder’s obligations under this Agreement are complete
and accepted by Owner, and final payment becomes due and payable.
2
​ 2.4.12.1 “Final Completion Time” is period of time beginning on the Date of Substantial Completion through the
total time within which Design-Builder is required to achieve Final Completion established in Section 6.2.
2.4.13. “Hazardous Material” means and includes a substance or material identified now or in the future as hazardous
under any Applicable Laws, or any other substance or material which is considered hazardous or otherwise subject to
statutory or regulatory requirements governing handling, disposal or clean-up. “Hazardous Material” does not mean or
include any substance or material that is specified or foreseeably required to be removed, disposed of, or used as part of
or in the performance of the Work by Design-Builder notwithstanding that such substance or material is otherwise
identified as hazardous under Applicable Laws, is considered hazardous, or is otherwise subject to statutory or regulatory
requirements governing handling, disposal or clean-up.
2.4.14. “Construction Change Directive” is any written order containing Work instructions directed by Owner for
changes to the scope of the Work required to performed or provided by Design-Builder pursuant to this Agreement,
which is signed by Owner after execution of this Agreement and before Substantial Completion of the Work.
2.4.15. “Separate Contractors” means other contractors engaged by Owner performing construction work or providing
construction services at the Project site as part of the Project, other than Design-Builder, its Subcontractors, and its
Suppliers.
2.4.16. “Overhead” shall mean (a) payroll costs and other compensation of Design-Builder’s employees in
Design-Builder’s principal and branch offices; (b) general and administrative expenses of Design-Builder’s principal and
branch offices including charges against Design-Builder for delinquent payments; and (c) Design-Builder’s capital
expenses, including interest on capital used for the Work.
2.4.17. The “Owner” is the person or entity identified in ARTICLE 1 and includes Owner’s representative(s).
2.4.18. The “Owner’s Program” is a description of Owner’s objectives, budgetary and time criteria, space requirements
and relationships, and if applicable to the Project, flexibility and expandability requirements, special equipment and
systems, and site requirements. The Owner’s Program may include preliminary Design Documents which shall include
drawings, and may include outline specifications and other conceptual documents illustrating the Project’s basic
elements, scale, and their relationship to the Worksite.
2.4.19. The “Parties” are collectively Owner and Design-Builder.
2.4.20. The “Project,” as identified in ARTICLE 1, is the facility and other improvements for which Design-Builder is to
perform the Work under this Agreement. The Project may also include improvements to be undertaken by Owner or
Separate Contractors.
2.4.21. “Project Schedule” A schedule that shows the timing and sequencing of the design and construction required to
meet the time criteria set forth in the Owner’s Program. The Project includes the Construction Schedule and is
coordinated with design phase service activities.
2.4.22. A “Subcontractor” is a person or entity retained by Design-Builder as an independent contractor to provide the
labor, materials, equipment, or services necessary to complete a specific portion of the Work. The term Subcontractor
does not include the Design Professional, or any Separate Contractor employed by Owner or any Separate Contractor’s
subcontractors.
2.4.23. “Substantial Completion” of the Work occurs on the date when construction is sufficiently complete in
accordance with the Contract Documents so that Owner can occupy or utilize the Project for the use for which it is
intended, without unscheduled disruption. The date on which Substantial Completion is achieved shall be the date set
forth in and confirmed in and through a certificate of Substantial Completion signed by Owner and Design-Builder (the
Date of Substantial Completion”). The certificate shall state the respective responsibilities of Owner and
Design-Builder for security, maintenance, heat, utilities, damage to the Work, and insurance. The certificate shall also list
the items to be completed or corrected by Design-Builder, and establish the time for completion and correction of such
items within the timeframe, if any, established in subsection 6.2.3 for the Final Completion Time.
2.4.24. A “Sub-subcontractor” is a party or entity who has an agreement with a Subcontractor or other
Sub-subcontractor, or Supplier to perform any portion of the Work or to supply material or equipment as part of the
Work.
3
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

Yard Waste Grinding and Removal Services This RFP is being posted to this

State Government of Connecticut

Bid Due: 6/24/2026

Installation & Revision of Traffic Control Signals - Various Cities/Towns in D3 Start

State Government of Connecticut

Bid Due: 7/01/2026

Follow New Haven Harbor Improvement Dredging, New Haven, CT Active Contract Opportunity Notice

DEPT OF DEFENSE

Bid Due: 7/01/2026

Single Family Housing Rehabilitation - 169 Rood The Community Development Office at the

State Government of Connecticut

Bid Due: 6/18/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.