4-Inch Submersible Solids Handling Pump

Location: Oklahoma
Posted: Jun 4, 2026
Due: Jun 24, 2026
Agency: City of Tulsa
Type of Government: State & Local
Category:
  • 43 - Pumps and Compressors
Solicitation No: IFB 26-541
Publication URL: To access bid details, please log in.
Bid ID: IFB 26-541
Addendum: 0
Bid Due Date: 6/24/2026
Description: 4-Inch Submersible Solids Handling
Pump
Bid Document: IFB 26-541 4-Inch Submersible Solids Handling Pump.pdf
Attachments:

Attachment Preview

EVENT DATE
IFB Issue Date 06/04/2026
Mandatory Pre-Bid Conference Virtual Teams Meeting Email rachelharders@cityoftulsa.org for invite 06/09/2026 at 10:00 AM CDT
Deadline for Questions Submitted to assigned buyer via email. 06/15/2026 10 Days prior to IFB due date
Bid Submission Date Either mailed or delivered to City Clerk address. Bids are open the day after the due date. 06/24/2026

City of Tulsa Finance Department
Invitation for Bid (IFB)
IFB 26-541
Supplies or Services Requested: 4-Inch Submersible Solids Handling
Pump
Department: Water and Sewer
NIGP Commodity Code(s): 720-40
Solicitation Schedule
EVENT DATE
IFB Issue Date 06/04/2026
Mandatory Pre-Bid Conference 06/09/2026 at 10:00 AM CDT
Virtual Teams Meeting
Email rachelharders@cityoftulsa.org for invite
Deadline for Questions 06/15/2026
Submitted to assigned buyer via email. 10 Days prior to IFB due date
Bid Submission Date 06/24/2026
Either mailed or delivered to City Clerk address. Bids
are open the day after the due date.
If You have any questions or need additional information, contact the Assigned Buyer:
Rachel Harders, Buyer | rachelharders@cityoftulsa.org
All questions should be emailed with IFB 26-541 on the subject line.
Submit Bids (sealed) to:
City of Tulsa - City Clerk's Office
175 E. 2ND St., Suite 260
Tulsa, OK 74103
Bids (2 total:1 original, 1 copy) must be sealed and either mailed or delivered.
Write the Bid Number, Supplies or Service requested (as listed above) and Bid
Opening Date on the lower left corner of the outside of Your Bid envelope. Feel
free to use included packing slip. No faxed or emailed Bids will be considered.
Barring certain circumstances (Section III-5), Bids received after the stated date
and time will not be accepted and will be returned to the Bidder unopened.

IFB 26-541 | 4-Inch Submersible Solids Handling Pump | Issue Date: 06/04/2026
I. STATEMENT OF PURPOSE:
1. Overview and Goals
The goal of this solicitation is to secure a source to purchase a 4-Inch Submersible Solids Handling
Pump for the Water and Sewer Department of the City of Tulsa.
2. Term of Contract
The City intends to award a one-year annual contract. The City may offer the Seller the opportunity
for additional one-year terms. The City also reserves the right to make multiple or partial awards. To
do business with the City, You must agree to the terms and conditions of the City's standard
Purchase Agreement, indicated by Your Authorized Agent's signature on the Purchase Agreement.
Capitalized terms used in this IFB and not defined in the Purchase Agreement shall have the
meanings as ascribed to them in Title 6, Chapter 4 of the Tulsa Revised Ordinances.
The entire Invitation for Bid (IFB), including any additional information submitted by Bidder and
Accepted by City will be included as part of the Agreement between Seller and City. All sheets of
this IFB (including Sections I-VI) must be submitted.
Authorized Agent
Several parts of the Bid (Affidavits, Purchase Agreement) must be signed by an "Authorized
Agent." An Authorized Agent means an agent who is legally authorized to bind the Seller under the
law of the state in which the Seller is legally organized. For instance, under Oklahoma law, the
Authorized Agent for each of the following types of entities is as stated below:
o Corporations - the president, board chair or board vice chair (or the vice president if the corporation
was formed in Oklahoma) can sign; others can sign if they have and provide the City with (i) a corporate
resolution giving them authority to bind the Seller, and (ii) a recent certificate of secretary indicating
the authority is still valid and was in full force and effect on the date of the signature. (See IFB Section
VI for sample of a Certificate of Secretary)
o General Partnerships - any partner can sign to bind all partners.
o Limited Partnerships - the general partner must sign.
o Individuals - no additional authorization is required, but signatures must be witnessed and notarized.
o Sole Proprietorship - the owner can sign. Any other person can sign if s/he provides a recent Power
of Attorney, signed by the owner, authorizing him/her to bind the sole proprietorship.
o Limited Liability Company (LLC) - any manager of the LLC elected by the members of the LLC, or
any member signing as manager of the LLC. All other signers will need a Consent of Members signed
by all the Members of the LLC authorizing their signature on or up to 30 days before the date of their
signature. (See Section VI for sample of a Consent of Members)
Entities organized in states other than Oklahoma must follow the law of the state in which they are
organized.
IFB Rev 02/2024 2

IFB 26-541 | 4-Inch Submersible Solids Handling Pump | Issue Date: 06/04/2026
II. SCOPE OF SERVICES AND SPECIFICATIONS
1. Scope of Services
The City is requesting Bids for a 4-Inch Submersible Solids Handling Pump for the Water and Sewer
Department.
Delivery Requirements
All prices quoted shall be based on delivery F.O.B. Tulsa, Oklahoma or to any other points as may
be designated in the Specifications, with all charges prepaid by Seller to the actual point of delivery.
Bids must state the number of Days required for delivery under normal conditions.
Absolutely no items over 500lbs. may be directly shipped to the City requiring the City personnel to
unload from the shipping truck or trailer. The City carries no responsibility for any damages incurred
during an unloading occurrence. All unloading shall be the responsibility of the Seller and/or shipping
entity.
2. Specifications
The Bid must meet or exceed the following Specifications.
Fairbanks Submersible D5432MV 4" Solids-Handling Pump or Acceptable
Equivalent
Part 1. General
1.01 This specification includes the supply of 1 (one) pull-up submersible solids-handling
pumping unit(s), UL Listed for explosion proof Class I, Division 1, Groups C and D
hazardous locations. The pumps shall be clockwise rotation and connect to the
discharge piping when lowered into place.
1.02 Quality Assurance
A. All pumping equipment furnished under this Section shall be of a design and
manufacture that has been used in similar applications, and it shall be
demonstrated to the satisfaction of the City of Tulsa Water and Sewer
Representative that the quality is equal to equipment made by that manufacturer
specifically named herein.
B. Unit responsibility. Pump(s), complete with motor and all other specified
accessories and appurtenances, shall be furnished by the Seller to ensure
compatibility and integrity of the individual components, and provide the specified
warranty for all components.
C. The pull-up submersible solids-handling pump(s) and motor(s) specified in this
section shall be furnished by and be the product of one manufacturer.
D. Pumps are to be engineered and manufactured under a written Quality Assurance
program. The Quality Assurance program is to be in effect for at least ten years,
to include a written record of periodic internal and external audits to confirm
compliance with such program.
E. Pump(s) are to be engineered and manufactured under the certification of ISO-
9001:2000.
IFB Rev 02/2024 3

Flow (GPM) TDH (ft.) Max. Pump Speed (RPM) Max. Solids Passage Max. Shutoff Head (ft.) Pump Discharge (inches)
Design Condition 810 70 1800 3" 104 4
Secondary Condition 800 70 1800 3" 104 4

IFB 26-541 | 4-Inch Submersible Solids Handling Pump | Issue Date: 06/04/2026
1.03 Performance
A. The pump(s) shall be designed for continuous operation and will be operated
continuously under normal service.
B. Operation Criteria
Max. Pump Max. Max. Pump
Flow TDH Speed Solids Shutoff Discharge
(GPM) (ft.) (RPM) Passage Head (ft.) (inches)
Design 810 70 1800 3" 104 4
Condition
Secondary 800 70 1800 3" 104 4
Condition
Part 2. Products
2.01 Pumps
A. Manufacturers
1. Pump(s) shall be the product of Fairbanks Morse Pump or acceptable
equivalent.
2. Manufacturers shall have installations of like or similar applications with a
minimum of 5 years' service for this pump size.
B. Design
1. Rotation
a. The pump will be clockwise rotation when viewed from the driver end
looking at the pump.
2. Impeller
a. Impeller shall be of the balanced non-clogging type matched to its constant
velocity equalizing pressure volute and be made of close-grained cast iron
conforming to ASTM A48 CL30. It shall be of one-piece construction,
single suction, enclosed (bladeless)(two-vane), radial flow design with
well-rounded leading vanes and then tapered toward the trailing edge for
a circular flow pattern to prevent the accumulation of solids and stringy
material.
b. The clearance between the impeller outside diameter and cutwater shall
be capable of passing a 2" sphere.
c. The impeller is to be balanced and secured to the shaft by means of a bolt,
washer, and key. The arrangement shall be such that the impeller cannot
be loosened from torque in either forward or reverse rotation.
d. Wiper vanes on the back impeller shroud are not allowed.
e. Impellers shall be trimmed to specifically meet the conditions of operation.
3. Volute/Casing
a. Volute is to be cast with extra thick walls made of close-grained cast iron
conforming to ASTM A48, Class 30. It is to be one-piece, constant velocity
equalizing pressure with smooth fluid passages large enough to pass any
size solid that can pass through the impeller.
b. The volute shall have an integral tapered suction inlet area to direct flow
to the impeller eye and have a centerline-flanged discharge. Volute
discharge shall be minimum 4" diameter as measured on the inside
diameter of the discharge flange opening.
c. A sliding bracket assembly shall be a part of the pumping unit constructed
so that when lowered to the discharge base/elbow, the knifing action of
the vertical metal-to-metal seal provides a self-cleaning, non-clogging,
non-sparking UL Listed explosion-proof assembly.
IFB Rev 02/2024 4

IFB 26-541 | 4-Inch Submersible Solids Handling Pump | Issue Date: 06/04/2026
4. Wear Rings
a. Wear rings shall be provided on both the impeller and fronthead so that
clearances can be maintained throughout the life of the rings and minimize
recirculation.
b. Impellers wear rings shall be of the axial- or face-type.
c. Fronthead wear rings shall be of the axial- or face-type.
d. Wear rings shall be attached to the impeller and fronthead using an
interference fit and Loctite.
e. Wear rings shall be stainless steel, with the impeller wear ring
approximately 50 Brinell softer than the fronthead wear ring.
f. Wear ring clearance adjustment shall be attained through impeller
adjustment shims.
5. Motor
a. Pump(s) shall be driven by completely sealed, electric submersible
squirrel cage induction motors with a maximum NEMA nameplate rating
of 25 HP, 1.15 service factor, 1760 RPM, 460 volts, 3-phase, 60 Hertz.
b. Submersible equipment shall be UL Listed for Class I, Division 1, Groups
C and D explosion-proof hazardous locations as defined by the National
Electric Code. All electrical parts shall be housed in an air-filled (or oil-filled
in 210 frame construction) cast iron, watertight enclosure which is sealed
using O-rings and rabbeted joints with extra-large overlaps.
c. The stator winding and lead shall be insulated with moisture-resistant
Class F insulation for continuous duty in 40 degree C ambient. The motor
shall be designed for continuous duty capable of ten (10) starts per hour.
Automatic reset, normally closed thermal overloads shall be imbedded in
the motor windings to provide overheating protection. Motor winding
thermostats must be connected to an electric controller per local and state
codes and the National Electric Code.
d. Motor shaft shall be one-piece, 416 stainless steel. Carbon steel shafts or
shaft sleeves are not acceptable. Rotor is to be dynamically balanced to
meet NEMA vibration limits; all external hardware is to be stainless steel.
e. Cable leads are to enter at the top of the motor and are to allow the cable-
to-motor connection to be accomplished in the field without soldering. All
power and control lead wires are to be double sealed as they enter the
motor in such a manner that cable-wicking will not occur. This sealing
system shall consist of a rubber grommet followed by epoxy that is high in
adhesive qualities and has a low coefficient of expansion. Each cable wire
is to have a small section of insulation removed to establish a window area
of bare wire and each wire is to be untwisted and surrounded by epoxy
potting material. A cable strain relief mechanism shall be an integral part
of this sealing system. Cable sealing system shall be capable of
withstanding an external pressure test of 1200 PSI as well as a cable
assembly pull test as required by Underwriters Laboratories. mSingular
grommet or other similar sealing systems are not acceptable. Motor shall
be supplied with 40 feet of multi-conductor type "SOW-A" or "W" power
cable and control cable. Cable sizing shall conform to NEC specifications
and be UL Listed.
f. Power and control leads shall be terminated on a sealed terminal board.
The terminal board and its bronze lugs shall be O-ring sealed.
IFB Rev 02/2024 5

IFB 26-541 | 4-Inch Submersible Solids Handling Pump | Issue Date: 06/04/2026
6. Shaft Seal Arrangement
a. Pump(s) shall be provided with two separate tandem-mounted mechanical
seals to prevent the pumped liquid from entering the rotor/stator cavity
area to ensure reliability of operation. The upper and lower seals are
mounted to rotate in the same direction.
b. The lower mechanical seal mating surfaces are to be immersed in an oil
bath, sealing the pump volute chamber from the oil cavity. Oil in this cavity
shall also lubricate the upper mechanical seal faces. Seal faces of both
the upper and lower mechanical seals shall be held in contact by
independent polymeric elastomer bellows, which act as a spring
mechanism. Seals require neither maintenance nor adjustment but shall
be easily inspected and replaced. Pressure generated by the pump assists
in sealing the mating surfaces of the lower seal.
c. Component material for the upper seal shall consist of a composite
elastomer body, carbon steel snap ring, Buna-N O-ring, carbon rotating
face and ceramic stationary face. Lower seal component construction shall
include a composite elastomer body, stainless steel clamp and set screws,
Buna-N O-ring, silicon carbide rotating face and tungsten carbide
stationary face.
d. Two moisture detection probes shall be installed so that they will detect
moisture in either the seal or stator cavity measuring resistivity between
the probes. They shall be wired internally to the control cable connection
at the top of the motor. Float type devices located in the rotor/stator area
or single probe-to-ground moisture detectors measuring continuity are not
acceptable. O-ring sealed inspection plugs shall be provided in the
mechanical seal oil chamber for ease of inspection, draining and filling of
oil.
7. The pump shall rotate on a grease lubricated-for-life thrust bearing (oil
lubricated in 210 frame) and grease lubricated radial bearing (oil lubricated in
210 frame). Lower shaft bearings shall be locked in place to prevent shaft
movement and to take thrust loads.
8. Fits and Hardware
a. All machined bolts, nuts, and capscrews shall be 316L stainless steel and
be of the hex-head type and will not require the use of any special tools.
b. A heavy-duty 316L stainless steel lifting bail shall be included and be of
adequate strength to lift the entire pump and motor assembly.
9. Testing
a. A certified factory performance test shall be performed on each pumping
unit in accordance with Hydraulic Institute Standards, latest edition. Tests
shall be sufficient to determine the curves of head, input horsepower, and
efficiency relative to capacity from shutoff to 150% of design flow. A
minimum of six points, including shutoff, shall be taken for each test. At
least one point of the six shall be taken as near as possible to each
specified condition.
b. Results of the performance tests shall be certified by a Registered
Professional Engineer and submitted for approval before final shipment.
10. Pumps shall be manufactured by companies whose management system is
registered to ISO-9001:2000.
IFB Rev 02/2024 6

If bidding an equivalent, You must include descriptive manufacturer's literature verifying the
information You provided in the Bidder's Response column with Your submission.

IFB 26-541 | 4-Inch Submersible Solids Handling Pump | Issue Date: 06/04/2026
In the Table below, the Bidder shall respond to each minimum requirement set forth in the
Specifications column by writing its response in the space provided under Section 2: Bidder's
Response column. Whenever asked to "describe", the description may include details such as size,
capacities, dimensions, materials used in construction, etc. A full and complete description is
required to reasonably evaluate the Bid, so all pertinent information is required. When referring to
attached literature as a means of not fully describing items, misinterpretations by the evaluator of the
Bid may occur. Your ability to present the City with enough information to reasonably understand the
item being bid and whether it meets the Specifications stated herein relies on the written information
provided.
You are required to describe Your proposed equipment in the Bidder's Response column, in terms
that correspond with the minimum Specifications shown. You may not answer in the space provided
as to whether You meet the Specifications by responding with terms as "yes", "meets", "same as",
"complies" or "similar" terms. If these terms are utilized, it shall result in Your Bid being
considered as non-responsive and being rejected.
If bidding an equivalent, You must include descriptive manufacturer's literature verifying the
information You provided in the Bidder's Response column with Your submission. Failure to
provide such literature shall result in Your Bid being considered as non-responsive and being
rejected. Any determination as to whether an item is equivalent that meets the Specifications shall
be made at the sole discretion of the City.
Seller shall ensure that each item and related parts are warranted by the manufacturer to be of good
material and workmanship and that manufacturer promptly replace any part or parts which by reason
of defective materials or workmanship shall fail under normal use, free of negligence or accident, for
a minimum of one (1) year from the date of delivery, unless otherwise stated. In addition, if such
failures take place outside the dealer's service area, which shall be defined as Tulsa city limits, the
Seller will be responsible for reimbursing the nearest manufacturer's authorized dealer in the city of
Tulsa for services rendered under this warranty.
The Seller shall respond within 72 hours of notification by the City of Tulsa, on when, where, and
how a warranty issue will be resolved. In the event there is no response within 72 hours, or if the
response is not acceptable to the City of Tulsa; the City will provide or arrange for repairs. The Seller
shall be responsible for reimbursing the nearest manufacturer's authorized dealer in the city of Tulsa
for services rendered under this warranty.
The Seller shall have the option to authorize the City of Tulsa to perform minor warranty
replacement and repairs and then reimburse the City for its labor and parts utilized to enact
the repair. The reimbursement for labor will be the same rate as that of the actual work
performed. Standard warranty information is to be supplied with the Bid.
TESTS AND ACCEPTABILITY OF MATERIAL:
All items included in the Bid are subject to a performance demonstration within 30 days of the Bid
date by the Bidder(s) at the discretion of the City of Tulsa. A like item of the type Bid that contains
all the safety concerns, horsepower ratings, accessories, dimensions or other features as deemed
appropriate by the City of Tulsa may be required to be demonstrated to the City of Tulsa personnel
prior to award of the Bid to establish if the item meets the requirements and Specifications of the City
of Tulsa.
IFB Rev 02/2024 7

SECTION 1: ITEM MINIMUM SPECIFICATIONS SECTION 2: BIDDER'S RESPONSE
General This specification is to provide for a new, latest production model of a 4-Inch Submersible Solids Handling Pump, Fairbanks 5430 Series Pump Model: D5432MV or Acceptable Equivalent Describe: Make: Model:
Pump 1. Discharge Size: 4-Inch 2. Suction Size (Standard): 4-Inch 3. Nominal Wear Ring (Axial) Clearance: 0.020-Inches Describe: 1. 2. 3.
Impeller Fastener 1. Size: 12-13-Inches 2. Tightening Torque: 80 Lbs.-Ft. Describe: 1. 2.
Impeller 1. Weight: 41.2 Lbs. 2. Inlet Area: 26.22 Sq. Inches 3. Sphere Size (Maximum): 3-Inches 4. Maximum Hydrostatic Test: 90 psi 5. Maximum Casing Working: 60 psi 6. Nominal Casing Thickness: 3/8-Inch 7. Maximum Operating Temperature: 104 degrees Fahrenheit 8. Anchor Bolt Size: 7/8-Inch Describe: 1. 2. 3. 4. 5. 6. 7. 8.

IFB 26-541 | 4-Inch Submersible Solids Handling Pump | Issue Date: 06/04/2026
SECTION 1: ITEM MINIMUM SPECIFICATIONS SECTION 2: BIDDER'S RESPONSE
This specification is to provide for a new, latest Describe:
production model of a 4-Inch Submersible Solids Make:
General
Handling Pump, Fairbanks 5430 Series Pump Model:
Model: D5432MV or Acceptable Equivalent
Describe:
1. Discharge Size: 4-Inch 1.
Pump 2. Suction Size (Standard): 4-Inch 2.
3. Nominal Wear Ring (Axial) Clearance: 3.
0.020-Inches
Describe:
Impeller Fastener 1. Size: 12-13-Inches 1.
2. Tightening Torque: 80 Lbs.-Ft. 2.
Describe:
1. Weight: 41.2 Lbs. 1.
2. Inlet Area: 26.22 Sq. Inches 2.
3. Sphere Size (Maximum): 3-Inches 3.
4. Maximum Hydrostatic Test: 90 psi 4.
Impeller
5. Maximum Casing Working: 60 psi 5.
6. Nominal Casing Thickness: 3/8-Inch 6.
7. Maximum Operating Temperature: 104 degrees 7.
Fahrenheit
8. Anchor Bolt Size: 7/8-Inch 8.
Failure to complete the table above as directed will disqualify
Your Bid and it shall be deemed non-responsive.
THE REMAINDER OF THIS PAGE HAS BEEN INTENTIONALLY LEFT BLANK
IFB Rev 02/2024 8

Attendance Requirement
Attendance at the Pre-Bid Conference is required to submit a Bid.

IFB 26-541 | 4-Inch Submersible Solids Handling Pump | Issue Date: 06/04/2026
III. BID SUBMISSION INSTRUCTIONS AND INFORMATION
1. Bidder Registration: To ensure timely updates and alerts about business opportunities with the
City, interested Bidders should register as a Bidder with the City. To register, interested Bidders
should complete the City's vendor registration form by contacting Andrea Evans at
purchasing@cityoftulsa.org or check the City's "Selling to the City" Website.
2. Pre-Bid Conference: If a pre-Bid conference is required, see the first page for time and location.
Attendance Requirement
Attendance at the Pre-Bid Conference is required to submit a Bid.
3. Questions and Concerns: As You prepare Your Bid response, You may have questions or points
of clarification around this Solicitation. Any questions or comments about this Invitation for Bid
must be sent via e-mail to the buyer listed on the first page "Assigned Buyer" and be received at
least 10 Days prior to the Bid Submission Date. Please include the IFB Bid number (as
indicated on the title page) on all communications. Bidders may only communicate with the City
through the Assigned Buyer - communication with other City staff could result in disqualification.
4. Issuing of Addenda: The City may addend or amend its IFB at any time before the Bid
Submission Date. In addition to registering as a Bidder with the City, Bidders can check the
"Purchasing Bid Opportunities & Results" page on the City Website for the latest updates (linked
here). Any such amendments shall become a part of the Agreement. You must acknowledge
receipt of any Addenda or Amendments by writing in the issued Addenda numbers on Exhibit A -
Delivery and Pricing. City may reject any Bid that fails to acknowledge any Addenda or
Amendments.
5. Submission and Receipt of Bids: The City requires two completed Invitation for Bids: 1 Original
and 1 Copy. Each must be clearly labeled on the front sheet indicating "Original" or "Copy." Use
the Bidder Checklist to ensure Your Bid includes all required components. If a copy on electronic
media is also required, the box below will be checked.
Electronic Copy also required.
Bids must be received no later than 5:00 PM (CST) on the Bid Submission Date (see first page)
and delivered to:
City of Tulsa - City Clerk's Office
175 East 2nd Street, Suite 260
Tulsa Oklahoma 74103
Bids must be sealed and either mailed or delivered. The package, container, or envelope should
contain both of Your completed Bids, the original and the copy. Please use the provided label on
the last page of this IFB to clearly write the Bidder's legal name and Bid number on the outside
of the package, container, or envelope. No faxed or emailed Bids will be considered.
Bids received after the stated date and time will not be accepted. The timestamp clock located
at the City Clerk's Office on the second floor of City Hall at 175 East 2nd Street, Suite 260, Tulsa,
Oklahoma, 74103 is the City's official bid clock for this IFB. Timeliness of Bid submittals will be
determined using only this clock.
IFB Rev 02/2024 9

IFB 26-541 | 4-Inch Submersible Solids Handling Pump | Issue Date: 06/04/2026
Exceptions to Timeliness Requirement
The Purchasing Agent, at his/her sole discretion, may make exceptions only for the following
reasons:
* City Hall closed for business for part or all of the day on the date the response was due;
* If the Purchasing Agent deems it appropriate due to large-scale disruptions in supply chains
and the transportation industry that may have prevented delivery as required;
* If documented weather conditions caused the late delivery. You must provide documentation
of such weather to the satisfaction of the Purchasing Agent.
In the event that the Bid submittal is delivered after the time specified and does not meet the
exceptions listed above, the Bid will not be accepted and the submittal envelope will not be
opened.
The City will not be liable for delays in delivery of Bids to the City due to handling by the U.S.
Postal Service, or any other type of delivery service. The City reserves the right to postpone the
date and time for submittal of Bids at any time prior to the Bid Opening Date or to delay or
reschedule the Bid Opening Date for its own convenience.
The City reserves the right to cancel, revise, or amend this IFB and associated bidding
documents up to the time specified for receipt of Bids.
6. Bid Opening: All Bid openings are public and take place at 8:30 a.m. Thursday, the day after
Bids are due. The Bid openings are held in the City of Tulsa Council Meeting Room, 175 East
2nd Street, 2nd Floor, Tulsa, Oklahoma.
IFB Rev 02/2024 1 0

This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

Follow KC-135 Center Console Refresh (CCR) Revision 2 Active Contract Opportunity Notice ID

DEPT OF DEFENSE

Bid Due: 9/15/2026

Bid Information Type Invitation For Bid Status Issued Number 10-2026 (Lake McMurtry Pump

City of Stillwater

Bid Due: 8/19/2026

Procurement #164796 Title Request for Sealed Bids -CNIT Fiber Distribution Relocation (Cherokee County)

Cherokee Nation

Bid Due: 8/19/2026

Follow Inventory Management and Material Support-Sole Source to Cherokee Nation Armored Solutions Active

DEPT OF DEFENSE

Bid Due: 8/11/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.