MnDOT Contract No. 1062380
Exhibit C: Specification, Duties, and Scope of Work
1 Introduction and Background Information
1.1 General Statement of Scope of Work
Work with State as the Design-Build Verification Consultant (DBVC), which will be called the
Contractor throughout this scope of work. The State Staff and Contractor are collectively known as the
Design-Build Verification Team (DBVT) for the State Project (SP) 1901-207 on Trunk Highway (TH) 13 &
Nicollet Design-Build Project (Project). Contractor will provide design verification, construction
verification, and environmental compliance for the Project. The goal of the DBVC contract is that State
receives assistance in performing the tasks necessary to verify that the Design Build Construction
contractor (DB contractor) is meeting all requirements of the Design Build Conformed Contract for the
Project. Contractor will attend conferences or meetings necessary for close coordination during day-to-
day progress of the work or as required to carry out the Project. Contractor will notify State’s Project
Manager immediately of any unanticipated Project conditions. Contractor will maintain a record of
design submittals, approvals, changes, and modifications using State’s Document Control System
(Microsoft SharePoint). Contractor will collect, properly label or identify, and deliver to State all original
calculations, drawing and sketches, electronic design files, records, reports, and other documents
prepared by the DB contractor in the performance of the work as described in this contract upon
completion or termination of the Project. Contractor will provide interpretations of the plans,
specifications and contract provisions. Contractor will consult with State’s Project Manager when an
interpretation involves complex issues or may have an impact on the cost of performing the work. When
warranted, State’s Project Manager may request an interpretation from the Contractor.
1.2 Co-location
This project will be a partial co-location project. The Contractor must meet the following
requirements:
1.2.1
1.2.2
1.2.3
1.2.4
1.2.5
1.2.6
1.2.7
1.2.8
1.2.9
DB Project Manager. Locate in the co-located facility one day per week, plus available as
needed for face-to-face meetings.
Change Management/Contract Engineer. Locate in the co-located facility one day per week, plus
available as needed for face-to-face meetings. Must be physically present at the project office or
on-Site daily during active construction.
Construction Manager. Must be physically present at the project office or on-Site daily during
active construction. Must remain involved with constructability and other reviews during the
design phase of the project.
Design Manager. Locate in the co-located facility one day per week for the duration of the
design, plus available as needed for face-to-face meetings.
Utility Coordination Lead: Locate in the co-located facility 50 percent during design and then co-
located 75 percent of the time once construction starts.
Design Team (Lead Structural Engineer, Lead Roadway Engineer, Lead Drainage Engineer, Traffic
Engineer, Maintenance of Traffic Engineer, Americans with Disabilities Act (ADA) Engineer,
Geotechnical Engineer, Retaining Wall Engineer, Intelligent Transportation Systems (ITS)
Engineer). Locate in the co-located facility one day per week for the duration of the design, plus
available as needed for face-to-face meetings.
Environmental Compliance Manager. Locate in the co-located facility 75 percent of the time
during design and 50 percent of the time for the duration of the Project.
Erosion Control Stormwater Pollution Prevention Plan (SWPPP) Inspector. Locate in the co-
located facility one day per week, plus available as needed for face-to-face meetings.
Office and Document Control Manager. Locate in the co-located facility full time during design,
1
MnDOT Contract No. 1062380
Exhibit C: Specification, Duties, and Scope of Work
and one day per week during the construction of the Project.
Throughout this scope of work, some roles of the DBVT are designated as being co-located and
others are not. Co-located personnel are expected to be physically located in the project office for the
time indicated for each role. Co-located personnel will have a physical workspace, computer, phone and
other common office supplies at the co-location office. Keep in mind, all personnel on the DBVT are
obligated to meet the requirements of the Flexible Workforce section of this scope.
In order to effectively manage the budget for the DBVT, co-located personnel will be expected to
inform the Verification Consultant Project Manager and the State Project Manager, if co-location
requirements are excessive based on the current verification activities of that role. If, in agreement with
the State’s Project Manager, it is decided that the co-located role can be just as effectively performed
partly from the team member’s home office then it may be determined that the co-location
requirements be temporarily relaxed.
Personnel that are not to be co-located at the project office can perform their role from their home
office. However, non-co-located personnel are required to report to the project office or project site as
needed for specific meetings, over the shoulder reviews, inspections, and other duties in a timely and
efficient manner to fulfill the obligations of their roles on the DBVT.
It is incumbent upon all DBVT members to utilize current web-conferencing best practices to be an
effective resource to the DBVT and the DB contractor during meetings, over the shoulder reviews and
questions that arise from the DB contractor for the DBVT. The purpose of a co-location office is to
minimize difficulty of communication between the DBVT and the DB contractor, so technology cannot
be a hindrance in this relationship. If web-conferencing is not working efficiently to communicate
between the two teams, the role member will be expected to be present at the co-location office as
needed so the DB contractor is not unduly delayed. It is important that any phone or web conference
technical difficulties be minimized or eliminated so that co-location can be effectively minimized for
each role.
1.3 Project Letting
The Design Build Project letting is August 19th, 2026.
1.4 Project Scope
The project is located in the City of Burnsville Dakota County, Minnesota. The project limits extend
a total of 1 mile from I-35W to Portland Ave along both TH 13 and Nicollet Ave.
The project scope is to design and construct TH 13 and Nicollet including roadway, bridges, traffic
signals and bicycle and pedestrian facilities. The project scope also includes the construction of drainage
infrastructure, traffic signals, utilities, etc.
Approximate Project cost: $55 million.
To find additional project information related to the Project, refer to the project website located at:
https://www.dot.state.mn.us/designbuild/hwy13-nicollet/index.html
Project information such as design files, layouts and more can be found on the Project design build
sharepoint site. Download and review all files at the following link:
https://wsbeng.sharepoint.com/sites/Hwy13atNicolletAvenueInterchangeDB/SitePages/CollabHom
e.aspx?clickparams=eyAiWC1BcHBOYW1lIiA6ICJNaWNyb3NvZnQgT3V0bG9vayIsICJYLUFwcFZlcnNpb24iI
DogIjE2LjAuMTg1MjYuMjA2NjAiLCAiT1MiIDogIldpbmRvd3MiIH0%3D&CID=6bd5dea1-3073-0000-1557-
707be85f66a2&cidOR=SPO
1.5 Verification Team Organization Chart
2
MnDOT Contract No. 1062380
Exhibit C: Specification, Duties, and Scope of Work
Attachment A is the DBVT organization chart and shows how the State will staff the DBVT for this
project. It graphically shows the chain of command. It also shows how the Contractor staff described in
this contract interacts with the State staff.
2 Project Management
Perform all work necessary to manage this DBVC Contract and its personnel. Perform all work
necessary to assist with managing the DB Conformed Contract.
2.1 DBVC Project Manager
The responsibilities of the DBVC Project Manager are as follows:
(A) Management of the contract including budget and performance management. The Contractor
will be expected to proactively review and manage the performance of Contractor team
members without State involvement.
(B) Assist State on strategy and high level project management and assist with implementation of
nationwide Design-Build best practices and lessons learned.
(C) Assist with Independent Cost Estimating for Change Order negotiation purposes. It is expected
that this will be required infrequently.
(D) Claims and litigation support as requested by State.
It is otherwise expected that the DBVC Project Manager’s involvement in day to day project issues
will be limited.
2.1.1 Preparation for Dispute Resolution or Litigation
Assist State in preparing for dispute resolution or litigation regarding the Project. This may require
assembling documents for review by others and tracking status of dispute or litigation and writing
letters as needed. Review and investigate all disputes or litigation. Review and investigation includes all
work necessary to confirm that the dispute or litigation is accurate and may involve review of plans,
review of site conditions, review of calculations, review of DB Contractor allegations and claims, etc.
Will also need to verify the claims being made or provide an alternative solution. This verification will be
done by creating independent cost estimates to be used as a comparison to the DB Contractor’s claims.
The Contractor will use all Contractor staff described in this contract as needed to assist with this work.
(A) Deliverable: Assembled documents with letters with independent cost estimates.
(B) Format: Microsoft Word or PDF
(C) Due: As needed as determined by the State.
(D) Standard: Conformed Contract and Minnesota Department of Transportation (MnDOT)
Contract Administration Manual.
(E) State Review: Five business days.
(F) Contractor Update: Five business days.
2.1.2 Staffing Requirements
Supply one person, in total, to perform the duties of the DBVC Project Manager.
2.1.3 Co-location
Locate in the co-located facility one day per week, plus available as needed for face-to-face
meetings.
2.2 Change Management/Contract Engineer
3
MnDOT Contract No. 1062380
Exhibit C: Specification, Duties, and Scope of Work
2.2.1 Evaluation of Value Engineering (VE) Proposals
Assist with the evaluation of VE Proposals and analysis of Project changes.
Deliverable: Evaluation of Value Engineering Proposals
(A) Format: Electronic Microsoft Word 2013 document (docx extension), hard copies, and Adobe
PDF.
Due: As needed.
Standard: Conformed Contract and MnDOT Contract Administration Manual.
State Review: Five business days of receipt of Contractor deliverable.
Contractor Update: Five business days of receipt of State review of deliverable.
2.2.2 Change Order Management
Assist the Construction Manager as needed in the creation, management, and investigation of DB
contract change order documents. Track the status of each change order and send documents to the
correct recipients as the process dictates. Inform the State’s Project Manager if the due dates at each
step in the process are not being met. Review and investigate all change orders. Review and
investigation includes all work necessary to confirm that the change order is accurate and may involve
review of plans, review of site conditions, review of calculations, review of DB Contractor allegations and
claims, etc. Will also need to verify the claims being made or provide an alternative solution. This
verification will be done by creating independent cost estimates to be used as a comparison to the DB
Contractor’s claims. The Contractor will use all Contractor staff described in this contract as needed to
assist with this work.
Deliverable: Change Orders.
Format: Electronic Microsoft Word 2013 document (docx extension), hard copies, and Adobe
PDF.
Due: As needed.
Standard: Conformed Contract and MnDOT Contract Administration Manual.
State Review: Five business days of receipt of Contractor deliverable.
Contractor Update: Five business days of receipt of State review of deliverable.
Preparation for Dispute Resolution or Litigation
Assist State in preparing for dispute resolution or litigation regarding the Project. This may require
assembling documents for review by others and tracking status of dispute or litigation and writing letters
as needed. Review and investigate all disputes or litigation. Review and investigation includes all work
necessary to confirm that the dispute or litigation is accurate and may involve, review of plans, review of
site conditions, review of calculations, review of DB Contractor allegations and claims, and etc. Will also
need to verify the claims being made or provide an alternative solution. This verification will be done by
creating independent cost estimates to be used as a comparison to the DB Contractor’s claims. The
Contractor will use all Contractor staff described in this contract as needed to assist with this work.
Deliverable: Assembled documents with letters with independent cost estimates.
Format: Electronic Microsoft Word 2013 document (docx extension), hard copies, and Adobe
PDF.
Due: As needed as determined by the State.
Standard: Conformed Contract and MnDOT Contract Administration Manual.
State Review: Five business days.
Contractor Update: Five business days.
4
MnDOT Contract No. 1062380
Exhibit C: Specification, Duties, and Scope of Work
2.2.3 Staffing Requirements
Supply one person, in total, to perform the duties of the Change Management/Contract Engineer.
2.2.4
Co-location
Locate in the co-located facility one day per week, plus available as needed for face-to-face
meetings. Must be physically present at the project office or on-Site daily during active
construction. The co-located office is expected to be located within one mile of the TH 13 and
Nicollet.
2.3 Construction Manager
The responsibilities of the Construction Manager are as follows:
Supply one person to perform the duties of the Construction Manager. This person is assigned the
overall responsibility for verifying that the DB Contractor is meeting all requirements of the DB’s Quality
Management System (QMS) and requirements of the DB Conformed Contract and will:
(A) Verify that the DB Contractor is training workers in the operation of the QMS,
(B) Monitor that the QMS is being properly implemented and used,
(C) Report to the State Project Manager on the QMS effectiveness and performance, and
(D) Identify problems with the QMS and make recommendations to the State Project Manager
for revisions to improve the QMS.
(E) Advise MnDOT staff on DB construction documentation.
(F) Review project documentation.
The Construction Manager has no responsibilities in the production of the Work, technical review
of design documents, or performance of construction inspection.
2.3.1 Co-location
Must be physically present at the project office or on-Site daily during active construction. Must
remain involved with constructability and other reviews during the design phase of the project.
2.3.2 Flexible Workforce
DBVC personnel approved by the State’s Project Manager are considered by the State to be
committed to performing services for the durations listed in this scope of work. Any changes will
require written approval from the State’s Project Manager and include both adding additional staff and
reducing staff.
Contractor will be advised of the official Notice of Award of the DB Conformed Contract and will be
ready to fully staff all personnel on the DBVT for the project within one week after notification. No
personnel will be assigned until written notification by the State’s Project Manager has been issued.
If the DB Contract is suspended for any reason, the Contractor’s forces will be adjusted to
correspond with the type of cessation, either complete or partial suspension. Contractor will
continuously look ahead to fully understand what type of staff are needed and in what numbers. The
Contractor’s schedule will be dictated by the DB contractor’s schedule. Contractor will provide a flexible
work force so that only those staff that can be fully utilized during any given project activity are present
and billing hours to the contract.
Contractor will continuously monitor all activity to ensure that all work carried out is within the
agreed scope and completed with resources that can complete the work as budgeted. In the event it
becomes necessary to complete work outside the original scope of work, the Contractor’s Project
Manager will notify State’s Project Manager immediately before proceeding. No work outside the
5
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.