B502--Air Emissions Survey Inventory Aleda E. Lutz VA Medical Center
| Location: |
Federal |
| Posted: |
Mar 24, 2025 |
| Due: |
Mar 28, 2025 |
| Agency: |
VETERANS AFFAIRS, DEPARTMENT OF |
| Type of Government: |
Federal |
| Category: |
- B - Special Studies and Analyses - Not R&D
|
| Solicitation No: |
36C25025Q0410 |
| Publication URL: |
To access bid details, please log in. |
B502--Air Emissions Survey Inventory Aleda E. Lutz VA Medical Center
Active
Contract Opportunity
Department/Ind. Agency
VETERANS AFFAIRS, DEPARTMENT OF
Sub-tier
VETERANS AFFAIRS, DEPARTMENT OF
Office
250-NETWORK CONTRACT OFFICE 10 (36C250)
Looking for contract opportunity help?
General Information View Changes
-
Contract Opportunity Type: Solicitation (Updated)
-
Updated Published Date: Mar 24, 2025 10:30 am EDT
-
Original Published Date: Mar 17, 2025 11:25 am EDT
-
Updated Date Offers Due: Mar 28, 2025 08:00 am EDT
-
Original Date Offers Due: Mar 28, 2025 08:00 am EDT
-
Inactive Policy: Manual
-
Updated Inactive Date: Apr 27, 2025
-
Original Inactive Date:
May 27, 2025
-
Initiative:
Classification
-
Original Set Aside:
-
-
Product Service Code: B502 - SPECIAL STUDIES/ANALYSIS- AIR QUALITY
-
NAICS Code:
-
541620 - Environmental Consulting Services
-
Place of Performance:
Description View Changes
Questions and Answers from RFQ 36C25025Q0410
Question: Does the VAMC have an existing air emissions permit and if so, can a copy be provided for review?
Answer: Â The facility currently has 2 existing air emissions permits. (See attached)
Question: Does the VAMC have a mandated timeline by which it needs to obtain an air emissions permit that is, is an older permit expiring? If so, please clarify the timeline, including specifying any due dates for permit application documents to be submitted to Michigan Department of Environment, Great Lakes, and Energy (MI EGLE).
Answer: This is an air emissions inventory to determine if any additional permits are required and to update the list of air emissions sources within the facility. The facility s permits are current.
Question: Task 1 specifically indicates that only one site visit is requested. Task 2 mentions a face-to-face permit strategy meeting with VAMC staff. Please confirm that this permit strategy meeting may occur via videoconference.
Answer: Onsite activities are required for the evaluation of the air emission sources. The permit strategy meeting can be via videoconference.Â
Question: Given that permit application review and permit issuance by MI EGLE may take several months or more, given that the VA expects work (e.g., development of emissions tracking tools and staff training) to occur after permit issuance, and given that this solicitation is an SDVOSB set-aside, would the VA be amenable to a milestone payment schedule, rather than a single lump sum payment, so that a small business does not have to wait many months to invoice and receive payment for work completed?
Answer: Yes, invoicing may be done monthly in arrears.
Question: Does the scope require applying for a permit or only the permitting strategy? Task 2. says It is for the Permitting Strategy but does not state how to apply for the permit. Although the Project Scope introduction states, Complete all documentation to apply for applicable permits, work on the Aleda E. Lutz VA Medical Center behalf to negotiate permit conditions
Answer: The scope is to complete application process if permit conditions are met or adjustments to current permits are necessary. Â
Question: Section E Solicitation Provisions states that Offers shall be assembled by the following Sections; each section shall be easily identified. (Sections A-D), but the evaluation states Technical, Past Performance, and Price. The instructions reference a technical quote. Do you want a technical quote submission and price submission, or do you want a separate submission per section outlined? Which section do you want the references for our past performance?
Answer: Please refer to pg. 26 of RFQ 36C25025Q0410 for guidance. Specifically, Section A- Offer Form (Standard Form 1449) shall be signed and dated. Any amendments to RFQ 36C25025Q0410 shall also be signed, dated, and returned. The offeror shall also complete Section B.2 Price/Cost Schedule. All pricing shall be in accordance with the guidance on page 26 of RFQ 36C25025Q0410. The offeror should provide evidence of capability of servicing this requirement. Please refer to pages 32 and 33 of RFQ 36C25025Q0410. Lastly, offeror shall provide evidence of past performance on active and physically completed contracts. Please refer to page 33 of RFQ 36C250250410 for descriptions of past performance examples.
Attachments/Links
Contact Information
Contracting Office Address
-
VISN 10 CONSOLIDATED CONTRACTING 4100 WEST 3RD STREET
-
DAYTON , OH 45428
-
USA
Secondary Point of Contact
History
Daily notification on new contract opportunities
With GovernmentContracts, you can:
- Find more opportunities and win more business
- Receive daily alerts for all new bid opportunities
- Get contract opportunities matched to your business
ONE WEEK FREE TRIAL
See also
Follow 53--SPRING,HELICAL,COMP Active Contract Opportunity Notice ID SPE7LX26U7952 Related Notice Department/Ind. Agency DEPT
DEPT OF DEFENSE
Bid Due: 6/11/2026
Follow 42--BACKFRAME ASSEMBLY Active Contract Opportunity Notice ID SPE8E626T3061 Related Notice Department/Ind. Agency
DEPT OF DEFENSE
Bid Due: 6/08/2026
Follow 48--VALVE,SAFETY RELIEF Active Contract Opportunity Notice ID SPE7MC26T038U Related Notice Department/Ind. Agency
DEPT OF DEFENSE
Bid Due: 6/08/2026
Follow Repair of e/CPDG Active Contract Opportunity Notice ID FA825126R0018 Related Notice Department/Ind.
DEPT OF DEFENSE
Bid Due: 6/26/2026
* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.