| Location: | North Dakota |
|---|---|
| Posted: | Dec 10, 2024 |
| Due: | Dec 17, 2024 |
| Agency: | TRANSPORTATION, DEPARTMENT OF |
| Type of Government: | Federal |
| Category: |
|
| Solicitation No: | 697DCK-25-R-GFKATC |
| Publication URL: | To access bid details, please log in. |
APEX Accelerators are an official government contracting resource for small businesses. Find your local APEX Accelerator (opens in new window) for free government expertise related to contract opportunities.
APEX Accelerators are funded in part through a cooperative agreement with the Department of Defense.
The APEX Accelerators program was formerly known as the Procurement Technical Assistance Program (opens in new window) (PTAP).
Introduction: The Federal Aviation Administration (FAA), Central Service Area – Terminal Acquisition Office is seeking qualified vendors to construct an FAA Airport Traffic Control Tower, Base Building, parking lot, detention pond, south access road, perimeter security, and appurtenances located at the Grand Forks International Airport, 2301 Airport DR, Grand Forks, ND 58203.
This market survey is issued, in accordance with FAA Acquisition Management System (AMS) paragraph, 3.2.1.2.1 to solicit statements of interest and capabilities from vendors who are capable of performing the work outlined. In order to assist with acquisition strategy development and to gain a better understanding of the commercial marketplace, all interest businesses are encouraged to submit a response to this market survey.
Disclaimer: The announcement is NOT A SCREENING INFORMATION REQUEST (SIR) OR REQUEST FOR PROPOSAL (RFP). The FAA is not seeking or accepting unsolicited proposals. The responses to this market survey will be used for informational purposes only and must not be construed as a commitment or a promise to contract by the Government. The Government is not liable for costs associated with the preparation, submittal of inquiries or responses for these announcements and will not reimburse any firm for costs incurred in responding to this public announcement. Responses will not be returned.
North American Industry Classification (NAICS) Code: The NAICS code projected for this project is 236220 Commercial and Institutional Building Construction with a size standard of $45 million.
Submittal Requirement for Market Survey:
Summary of Work:
The project consists of construction of an Airport Traffic Control Tower (196ft AGL to top of structure) and an approximately 22,000 square foot one story base building. The project site is about 3 acres located at 2715 Airport Drive, Grand Forks, North Dakota. All work shall be performed in accordance with the specifications and drawings and shall be completed in strict accordance with the manufacturer’s guidelines.
All site work and infrastructure, ATCT, Base Building, including Link Structure
650 square foot eight sided cab.
The total duration of this upgrade construction project is estimated at 520 work days with a completion date not to exceed July 2027.
All construction will be per the FAA Terminal Facilities Standard Design Drawings, Terminal Facilities Design Standard l and Minimum BIM Requirements Specification. In addition, construction will include Whole Building Commissioning and will be incompliance with High Performance Sustainable Building Requirement (HPSB)
Delivery of Submittals: Submittals to this market survey shall be e-mailed to Erin Crabtree (Contracting Officer) at Erin.M.Crabtree@faa.gov no later than 5:00 p.m. CST December 17, 2024.

With GovernmentContracts, you can: