City of
Tega Cay, South Carolina
www.tegacaysc.org
7725 Tega Cay Drive
Phone: 803.548.3512
Tega Cay, SC 29708
Fax: 803.548.1400
DATE: May 22, 2026
ADDENDUM 4
1. The rate schedule Form: To confirm the total number of curbside solid waste noted
in Section 3. a.i., (5,100) is the combination of 4,300 + 850 outlined on the Rate
Schedule?
That is the combined approximation for the 5100 total. The current vendor estimated
800-850 utilizing the service so 850 would capture the maximum number.
2. Section 13.g.iii. References Sections 4.9.3 and 4.9.4. – Where are these sections in the
RFB?
This is an error and is covered in this section:
iv. If the Contractor fails to initiate proactive measures necessary to reduce the frequency
and severity of vehicle leaks or spills, including those listed in Sections 6.4.a to 6.4.c, the
Contractor shall, in addition to the Damages described above, be subject to the following
Damages:
1. One thousand dollars ($1,000) for each leak or spill during any one- (1) month
period in which there were two (2) to five (5) leaks or spills;
2. One thousand five hundred dollars ($1,500) for each leak or spill during any
one (1) month period in which there were six (6) or more leaks or spills.
3. Section 13.g.iv.: References Sections 6.4.a to 6.4.c. – Where are these sections in the
RFB?
This is an error and is covered in this section:
iv. If the Contractor fails to initiate proactive measures necessary to reduce the frequency
and severity of vehicle leaks or spills, including those listed in Sections 6.4.a to 6.4.c, the
Contractor shall, in addition to the Damages described above, be subject to the following
Damages:
1. One thousand dollars ($1,000) for each leak or spill during any one- (1) month
period in which there were two (2) to five (5) leaks or spills;
City of
Tega Cay, South Carolina
www.tegacaysc.org
7725 Tega Cay Drive
Phone: 803.548.3512
Tega Cay, SC 29708
Fax: 803.548.1400
2. One thousand five hundred dollars ($1,500) for each leak or spill during any
one (1) month period in which there were six (6) or more leaks or spills.
4. Section 21. Insurance: Is the COI required to be submitted with the bid submission?
This would only be required by the successful Offeror.
5. Section 22. Bond & Section Bid Submission Specification and Requirements
Performance bond “may” be required. Please clarify if this will be required by the
Contractor. Also, the 100% of Contract Amount, please confirm that this will be 100% of
the “Annual” Contract Amount not the total five-year contract amount.
The performance bond is required and would need to include 100% of the annual contract
amount.
6. Section 24.ii. Basis and Method of Payment – Landfill Charges, Fee, Taxes: Any
request for rate adjustment shall include detailed supporting documentation, including but
not limited to fuel cost data tied to the defined Diesel Index, landfill fee changes
supported by official rate schedules or invoices, and any other applicable cost drivers.
Respectfully request removal of this section from Section 24.ii. This highlighted Section
is not applicable to landfill disposal increases/decreases as charged by the third-party
landfill and is directly outside the Contractor's control.
The contractor would still need to provide proof of the fee increases.
7. Bid Submission Specification and Requirements 1.a. The return of the addenda, if any,
signed and filled out as required. Is there a form for this acknowledgment?
Currently, no addendum required additional information completed by an Offeror. A
statement of acknowledgement and including the Addendums would fulfill the
requirement.
8. General Terms and Conditions: 1.a. Sealed bids will be received and opened. Will the
opening be held in public, with any of the Contractor present?
There will not be a public bid opening, a bid tabulation form will be posted online within
2 business days of the bid opening.