Helene Streambank & Restoration RFQ response to questions:
The RFQ identifies the submission deadline as October 5, 2026, at 2:00 p.m. ET, but refers
to October 5 as a Thursday. Please confirm that the controlling deadline is Monday, October
5, 2026, at 2:00 p.m. ET. Yes, the deadline is Monday, October 5th, 2026 at 2:00 P.M. ET.
Does the County anticipate awarding One contract covering all identified sites, Multiple site-
specific contracts, or a master services agreement with work authorized through individual
task orders? The County will award one contract covering all identified sites.
Please confirm whether the selected firm will provide design, permitting, bidding/procurement
support, construction administration, and completion certification only, or whether any
construction or design-build responsibility is anticipated. The selected firm will be responsible
for all design, permitting, bidding, procurement support, construction administration, and
completion certification.
Will the County consider stream restoration projects completed through mitigation banking?
As long as the work performed demonstrates experience in the types of projects that
services are requested for in the RFQ.
Must all three references relate to projects physically installed in Western North Carolina, or
will the County consider references for comparable work elsewhere in North Carolina when
supplemented by Western North Carolina project experience? The county would prefer the
references to relate to work performed in Western North Carolina, but this is not a
requirement.
What level of documentation does the County expect for demonstrating that previous
projects were completed on time and within budget? A baseline versus reality pertaining to
budget and deadlines, completion certificates, etc. A good picture of the companies track
record and examples of how you handle project baselines.
Which specific NRCS Conservation Practice Standards, specifications, or funding-program
requirements are expected to apply to the work? The majority of the work will fall under
NRCS CPS 326 and 580.
Is there a preferred page limit, file-size limit, font requirement, or organizational format for the
Statement of Qualifications? No
Is there any landslide work associated with this RFQ/project? No
Can we get a copy of the Damage Survey Reports? The selected firm will be provided with
a copy of the Damage Survey Reports.
Will you be distributing your addendum via email on the 28th? You can find the addendum on
the county website under the Bid Opportunities tab.

With GovernmentContracts, you can:
Follow DEVCOM ARMY RESEARCH LABORATORY BROAD AGENCY ANNOUNCEMENT FOR FOUNDATIONAL RESEARCH Active Contract
DEPT OF DEFENSE
Bid Due: 11/20/2027
Follow DEVCOM ARMY RESEARCH LABORATORY BROAD AGENCY ANNOUNCEMENT FOR FOUNDATIONAL RESEARCH Active Contract
DEPT OF DEFENSE
Bid Due: 11/20/2027
Follow DEVCOM ARMY RESEARCH LABORATORY BROAD AGENCY ANNOUNCEMENT FOR FOUNDATIONAL RESEARCH Active Contract
Federal Agency
Bid Due: 11/20/2027
Bid Title: ITB: Ocean Ridge Reclaimed Waterline Category: Public Utilities Status: Open Description:
Brunswick County
Bid Due: 11/19/2026