Pre-Proposal Conference - Questions and Answers
The City of Lakeway conducted a pre-proposal question-and-answer meeting to provide
prospective respondents an opportunity to ask questions regarding the above-referenced
solicitation.
The following questions and responses are provided as clarification of the solicitation
requirements. Responses below are intended to supplement the RFP. All other
requirements, terms, and conditions remain unchanged unless specifically modified by
this addendum.
Certain technical, operational, and infrastructure-related questions require additional review
by City staff. The City will provide further clarification through a subsequent addendum.
Respondents should continue to monitor the City's procurement website for all solicitation
updates and addenda.
REVISED PROCUREMENT SCHEDULE
Anticipated Issuance of Final Addendum: November 24, 2026
Revised Proposal Submission Deadline: December 3, 2026, at 2:00 p.m. CST
The City of Lakeway hereby extends the proposal submission deadline for RFP No. 27-1002 –
Information Technology Support Services from November 24, 2026, to December 3, 2026, at
2:00 p.m. CST.
This extension is intended to provide respondents additional time to review the City's
clarifications and prepare their proposals in consideration of the Thanksgiving holiday.
Contract award is anticipated at the January 2027 City Council meeting, subject to completion
of the evaluation and approval process.
The City reserves the right to issue additional addenda and further extend the proposal
submission deadline if deemed necessary.
SECTION 1-SUBMISSION REQUIREMENTS AND PROPOSAL FORMAT
Question 1: Will the City accept electronic proposal submissions via email or an electronic
portal instead of physical delivery?
Response: At this time, the City requires one (1) original, five (5) printed copies, and one
(1) electronic flash drive. Proposals must be delivered in accordance with the submission
instructions in the RFP.
Question 2: Are required compliance forms, the Conflict-of-Interest Questionnaire (CIQ),
cost summary form, and staff resumes included in the 30-page proposal limit?
Response: The 30-page limit excludes the cover, table of contents, and divider sheets.
Required forms identified in Part 5, Form 1295, and resumes submitted as supporting
documentation are also excluded from the 30-page limit.
Question 3: Are financial statements required with the proposal?
Response: Financial statements are not required with the proposal. The City reserves the
right to request additional financial information during the evaluation process or contract
negotiations.
SECTION 2 - PROJECT OBJECTIVES AND CONTRACT EXPECTATIONS
Question 4: What are the City's primary goals for this engagement?
Response: The City's primary objectives are to maintain or improve the current level of IT
support and service delivery to City employees while consolidating the scope of services to
obtain better value and more clearly defined service expectations.
The City is seeking a more focused and efficient managed IT support arrangement rather than
an unnecessarily broad scope of services.
Question 5: Has the City established an estimated annual budget for this engagement,
including optional services under Scenarios B and C?
Response: The City indicated that approximately $100,000 is identified in the current budget
as an upper planning amount. Respondents should provide pricing for the services proposed
under the applicable scenarios. The City will consider the proposed services and associated
costs.
The City's annual budget planning process typically begins in May–June. The City's fiscal year
begins October 1.
Question 6: Is the City currently utilizing an incumbent managed service provider (MSP)?
Response: Yes. The City currently has an MSP, Imagine Solutions, providing services. The
anticipated transition to a new provider is expected to occur following contract award.
Question 7: What is the anticipated contract start date and transition timeline?
Response: The City anticipates a potential start date around February 2027, subject to
completion of the evaluation and award process. Historically, approximately one month has
been needed for transition and onboarding, although the final transition schedule will be
coordinated with the selected provider.
Question 8: Is the City seeking one provider or multiple providers?
Response: The City anticipates selecting a single managed service provider for this
engagement.
Question 9: Does the City anticipate mandatory subcontracting goals?
Response: No mandatory subcontracting goals have been established. Respondents may
identify additional or specialized services they offer for the City's consideration.
SECTION 3 - ON-SITE AND REMOTE SUPPORT
Question 10: Does the City have a preferred day of the week or shift structure for on-site
support?
Response: The City does not require a specific day of the week. The schedule may be mutually
coordinated between the City and the selected provider. The City is also open to adjusting
the scheduled day when necessary.
Question 11: May the minimum one day per week of on-site support be scheduled for the
same day each week?
Response: Yes. The City is agreeable to establishing a consistent weekly schedule with the
selected provider. Changes may be coordinated when unforeseen circumstances arise.
Question 12: Does the four-business-hour on-site response requirement for Priority 1
incidents apply to all City locations, including the Police Department and Justice Center?
Response: Yes. The four-business-hour on-site response requirement applies to all City
locations.
SECTION 4 - CITY IT ENVIRONMENT AND INFRASTRUCTURE
Question 13: Can the City confirm the number of end users and devices supported,
including mobile devices, tablets, printers, and Police Department equipment?
Response: The City currently has approximately 150 workstations and laptops. The scope also
includes applicable printers, QNAP devices, wireless access points, and Police Department
equipment. The City estimates approximately 130 City staff users, with additional devices
assigned to City Council members and boards and commission members. The total supported
user population is estimated to be no more than 150 users.
Question 14: Is a ticketing system mandatory for the selected provider?
Response: Yes. The City expects the selected provider to maintain a ticketing system that
provides visibility into service requests, ticket status, response times, resolution, and service
reporting.
Question 15: Is the City utilizing Microsoft Government Cloud?
Response: No. The City currently uses standard Microsoft 365 business licensing and is not
operating in the Government Cloud environment.
Question 16: Which firewall models are currently deployed?
Response: The City currently utilizes Cisco Firepower 1150 firewalls at the Police
Department and SonicWall TZ-series firewalls at City Hall and other municipal locations.
The SonicWall models include the TZ 570 and TZ 370 series.
SECTION 5 - BACKUP, STORAGE, AND THIRD-PARTY SOFTWARE
Question 17: What is the City's current responsibility for cybersecurity monitoring and
remediation?
Response: The City currently utilizes CrowdStrike Falcon Complete and maintains primary
responsibility for cybersecurity management and coordination with its security provider. The
incumbent MSP provides notifications and assistance when necessary.
The City does not anticipate requiring the new MSP to duplicate existing cybersecurity
services.
SECTION 6 - APPLICATIONS AND SYSTEM SUPPORT
Question 18: Which Tyler Technologies applications are currently in use, and what level of
support is expected from the selected MSP?
Response: The City currently utilizes Tyler Technologies cloud-based solutions, including ERP
10, Municipal Justice 10, and EnerGov.
The City generally relies on Tyler Technologies for software hosting, updates, and application
support. The MSP will primarily assist with reporting issues, connectivity concerns, and
coordinating with Tyler Technologies when necessary.
The Police Department also utilizes a legacy Public Safety system. Support responsibilities
are limited and coordinated with Police Department personnel and Tyler Technologies.
SECTION 7 - COMPLIANCE AND SECURITY
Question 19: Will the City require Texas registrations, licenses, and certifications at the
time of proposal submission?
Response: Any registrations, licenses, certifications, or other legal authorizations required
to perform the services must be obtained and maintained before contract execution and
throughout the contract term. Respondents should ensure they can meet all applicable
legal requirements if selected for award.
SECTION 8 - CONTRACT TERMS AND PRICING
Question 20: Is the sample Professional Services Agreement included in the RFP intended to
serve as the final contract or Statement of Work (SOW)? Will the City consider proposed
exceptions or suggested modifications to the agreement?
Response: The Sample Contract included in the RFP is intended to serve as the basis for the final
agreement. The Scope of Work is established in Part II of the RFP, including the Service
Responsibility Matrix, and will be incorporated into the final contract along with any applicable
addenda and the selected contractor's accepted proposal.
Proposers may identify requested exceptions or suggested modifications for the City's
consideration during contract negotiations. Any proposed changes are subject to review and
acceptance by the City. The City reserves the right to accept or reject proposed modifications,
and no changes shall be binding unless incorporated into the final executed agreement.
Respondents must comply with the proposal submission requirements of the RFP, and the City is
not obligated to negotiate or accept any proposed exceptions.
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.