STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
JOSH STEIN
GOVERNOR
April 2, 2026
DANIEL H. JOHNSON
SECRETARY
ADDENDUM # 1
Contract No. DN01127
TIP No.:
BL-0008
Federal Aid No.: STBGDA-1413019
WBS Element: 49463.3.1
County:
Henderson
Description:
Grading, Paving, Structures, And Drainage on Clear Creek Greenway
From Oklawaha Greenway At SR-1508 (Balfour Rd) To SR-1518
(Lakewood Rd) In Henderson County
Letting Date: April 14, 2026
Plan Holders
Content Summary: Question & Answer, Provision Changes, Plans Sheet Changes
Pay Item Changes, Quantity Changes
The above contract has experienced the following revisions:
1. Bidder Questions/Concerns and Department Responses:
a. Bidder Concern: “The proposal indicates that there is no tree clearing from
April 1st to October 15th. When visiting the site, there will be trees to clear,
especially under ICT #3 which states that the work from station 81+23 to
station to station 147+47 to be completed in that window.”
b. Department’s Response: On page G-8, the Construction Moratorium
provision has been removed from the proposal. The City of
Hendersonville cleared some but not all the trees before the moratorium
began. For those trees that still need to be cleared during the
moratorium, the Department will utilize the Biological Programmatic
Opinion to allow for the removal of those trees. The Contractor shall
coordinate with the Resident Construction Engineer and the Division
PDEA Engineer, prior to cutting any remaining trees.
Mailing Address:
NC DEPARTMENT OF TRANSPORTATION
DIVISION OF HIGHWAYS - DIVISION 14
253 WEBSTER ROAD
SYLVA, NC 28779
Telephone: (828) 331-5200
Fax: (828) 331-5201
Customer Service: 1-877-368-4968
Website: www.ncdot.gov
Location:
253 WEBSTER ROAD
SYLVA, NC 28779
c. Bidder Question: The 2024 Standard Specification book calls for Pratt
bridges, but the specs in the drawings call for Pratt trusses- can you verify
what type of truss is needed?
d. Department’s Response: “The required truss type is a Pratt truss. Any
reference in the specifications to “Pratt bridges” is intended as a
general bridge classification only. The drawings explicitly define the
structural system and shall govern. Provide a Pratt truss in accordance
with the contract drawings.”
e. Bidder Question: “The drawings call for a rub rail, is that PT pine, steel, or
IPE?”
f. Department’s Response: The Contractor shall provide an IPE rub rail as
shown and detailed on the contract drawings
2. Remove Provision SP1 G18C Construction Moratorium on page G-8
3. Remove Provision SP11 R06 Temporary Crash Cushions on page R-9
4. Replace Sheet 1A of the DN01127 STANDARD PLANS SHEETS – ROADWAY as it
includes notation for sheet 3B-1 in the Index of Sheets list (see attached)
5. Add Sheet 3B-1 of the DN01127 STANDARD PLANS SHEETS – ROADWAY (see
attached)
6. The following pay items have changed
a. The quantity for line item 0014: 1099500000-E SHALLOW UNDERCUT has
decreased from 500 to 100 CY
b. The quantity for line item 0005: 1099500000-E GEOTEXTILE FOR SOIL
STABILIZATION has increased from 1,000 to 1,300 CY
c. 0036000000-E 225 UNDERCUT EXCAVATION has been added, 350 CY
d. 0195000000-E 265 SELECT GRANULAR MATERIAL has been added, 200
CY
e. 2022000000-E 815 SUBDRAIN EXCAVATION has been added, 84 CY
f. 2026000000-E 815 GEOTEXTILE FOR SUBSURFACE DRAINS has been
added, 250 SY
g. 2036000000-E 815 SUBDRAIN COARSE AGGREGATE has been added, 42
CY
h. 2044000000-E 815 6" PERFORATED SUBDRAIN PIPE has been added, 250
LF
i. 2070000000-N 815 SUBDRAIN PIPE OUTLET has been added, 1 EA
j. 2077000000-E 815 6" OUTLET PIPE has been added, 6 LF
Please access ebsx addenda files, DN01127.001x. on Bid Express®.
Thank you for your attention to this matter.
If you have any questions, please contact the Division Proposal Engineer at (828) 331-
5200.
Sincerely,
Wes Jamison, P.E.
Division 14 Project Development Engineer
INDEX OF SHEETS
SHEET NUMBER
SHEET
1
TITLE SHEET
1A
INDEX OF SHEETS, GENERAL NOTES, AND LIST OF
STANDARD DRAWINGS
1B
CONVENTIONAL SYMBOLS
2A-1
TYPICAL SECTIONS
2B-1 THRU 2B-4
ROADWAY DETAILS
3B-1
ROADWAY SUMMARY
3D-1
DRAINAGE SUMMARY SHEET
3P-1
PARCEL INDEX SHEET
4 THRU 24
PLAN AND PROFILE SHEETS
TMP-1
TRAFFIC MANAGEMENT PLAN
PMP-1 THRU PMP-7
PAVEMENT MARKING PLANS
EC-1 THRU EC-43
EROSION CONTROL PLANS
SIGN-1 THRU SIGN-6
SIGNING PLANS
X-1
CROSS-SECTION INDEX
X-2 THRU X-49
CROSS-SECTION SHEETS
S-1 THRU S-16
STRUCTURE PLANS
UTILITY AND GOVERNING AGENCIES CONTACT LIST
CITY OF HENDERSONVILLE ENGINEERING
CITY OPERATIONS CENTER
305 WILLIAMS STREET
HENDERSONVILLE, NC 28792
(828) 697-3000 TEL
CONTACT: BRENDAN SHANAHAN, P.E., CFM
CITY ENGINEER
POLICE DEPARTMENT
HENDERSONVILLE POLICE DEPARTMENT
630 ASHE STREET
HENDERSONVILLE, NC 28792
(828) 697-3000
POLICE CHIEF: BLAIR MYHAND
WATER COMPANY
HENDERSONVILLE WATER AND SEWER
305 WILLIAMS STREET
HENDERSONVILLE, NC 28792
(828) 697-3073 TEL
POWER COMPANY
DUKE ENERGY
957 SPARTANBURG HWY
HENDERSONVILLE, NC 28792
(800)777-9898 TEL
FIRE DEPARTMENT
HENDERSONVILLE FIRE DEPARTMENT
632 SUGARLOAF ROAD
HENDERSONVILLE, NC 28792
(828) 697-3024 TEL
FIRE CHIEF: GARY STYERS
GENERAL NOTES:
2024 SPECIFICATIONS
EFFECTIVE:
01-16-2024
REVISED:
GRADE LINE:
GRADING AND SURFACING:
THE GRADE LINES SHOWN DENOTE THE FINISHED ELEVATION OF THE PROPOSED
SURFACING AT GRADE POINTS SHOWN ON THE TYPICAL SECTIONS. GRADE LINES MAY BE
ADJUSTED AT THEIR BEGINNING AND ENDING AND AT STRUCTURES AS DIRECTED BY THE
ENGINEER IN ORDER TO SECURE A PROPER TIE-IN.
CLEARING:
CLEARING ON THIS PROJECT SHALL BE PERFORMED TO THE LIMITS ESTABLISHED BY
METHOD II.
SUPERELEVATION:
ALL CURVES ON THIS PROJECT SHALL BE SUPERELEVATED IN ACCORDANCE WITH
STD. NO. 225.04 USING THE RATE OF SUPERELEVATION AND RUNOFF SHOWN ON THE PLANS.
SUPERELEVATION IS TO BE REVOLVED ABOUT THE GRADE POINTS SHOWN ON THE TYPICAL
SECTIONS.
SIDE ROADS:
THE CONTRACTOR WILL BE REQUIRED TO DO ALL NECESSARY WORK TO PROVIDE
SUITABLE CONNECTIONS WITH ALL ROADS, STREETS, AND DRIVES ENTERING THIS PROJECT.
THIS WORK WILL BE PAID FOR AT THE CONTRACT UNIT PRICE FOR THE PARTICULAR ITEMS
INVOLVED.
DRIVEWAYS:
DRIVEWAYS SHALL BE CONSTRUCTED IN ACCORDANCE WITH STD. 848.02
USING 3 FOOT RADII OR RADII AS SHOWN ON THE PLANS. LOCATIONS OF DRIVES
WILL BE AS SHOWN ON THE PLANS OR AS DIRECTED BY THE ENGINEER.
END BENTS:
THE ENGINEER SHALL CHECK THE STRUCTURE END BENT PLANS, DETAILS, AND CROSS-
SECTION PRIOR TO SETTING OF THE SLOPE STAKES FOR THE EMBANKMENT OR EXCAVATION
APPROACHING A BRIDGE.
UTILITIES:
UTILITY OWNERS ON THIS PROJECT ARE HENDERSONVILLE WATER AND
SEWER AND DUKE ENERGY CORPORATION.
SUBSURFACE DRAINS
SUBSURFACE DRAINS SHALL BE CONSTRUCTED IN ACCORDANCE WITH STD. NO.
815.02 AT LOCATIONS DIRECTED BY THE ENGINEER
SUBSURFACE PLANS
NO SUBSURFACE PLANS ARE AVAILABLE ON THIS PROJECT. THE CONTRACTOR SHOULD
MAKE HIS OWN INVESTIGATIONS AS TO THE SUBSURFACE CONDITIONS.
2024 ROADWAY ENGLISH STANDARD DRAWINGS
EFF. 01-16-2024
REV.
The following Roadway Standards as appear in "Roadway Standard Drawings" Contracts Standards and Development Unit -
N. C. Department of Transportation - Raleigh, N. C., Dated January 16, 2024 are applicable to this project
and by reference hereby are considered a part of these plans:
STD.NO.
TITLE
DIVISION 2 - EARTHWORK
200.02 Method of Clearing - Method II
225.02 Guide for Grading Subgrade - Secondary and Local
225.04 Method of Obtaining Superelevation - Two Lane Pavement
DIVISION 3 - PIPE CULVERTS
300.01 Method of Pipe Installation
DIVISION 8 - INCIDENTALS
806.01 Concrete Right-of-Way Marker
806.03 Concrete Contol of Access Marker
838.11 Brick Endwall for Single and Double Pipe Culverts - 15" thru 48" Pipe 90 Skew
838.27 Reinforced Concrete Endwall - for Single 48" Pipe 90 Skew
846.01 Concrete Curb, Gutter and Curb & Gutter
848.01 Concrete Sidewalk
848.06 Concrete Curb Ramp
848.07 Concrete Sidepath / Shared Use Path / Greenway Construction
866.07 Wildlife Frence - with Chain Link
867.02 Steel Bollards
876.02 Guide for Rip Rap at Pipe Outlets
PREPARED IN THE OFFICE OF:
REV. No.:
REVISION:
DATE:
DRAWN BY:
CHECKED BY:
This document, together with the concepts and designs presented herein, as an instrument of service, is
intended only for the specific purpose and client for which it was prepared. Reuse of and improper
reliance on this document without written authorization and adoption by Kimley-Horn and Associates, Inc.
shall be without liability to Kimley-Horn and Associates, Inc.
Copyright Kimley-Horn and Associates, Inc., 2025
NC LICENSE #F-0102
200 S TRYON ST, SUITE 200
CHARLOTTE, NORTH CAROLINA 28202
PHONE: (704) 333-5131
C 2025
INDEX OF SHEETS,
GENERAL NOTES,
AND STANDARD DRAWINGS
ORTOHFECSASRIOONLIN
SEAL
052843
IAENGG.INGEOEL 4RA/S2/2026
PROJECT:
CLEAR CREEK GREENWAY
JOB NUMBER:
015574013
SHEET NUMBER:
1A
COMPUTED BY:
CHECKED BY:
SRR
TGR
DATE:
DATE:
04-01-2026
04-01-2026
STATE OF NORTH CAROLINA
DIVISION OF HIGHWAYS
STATION
SUMMARY OF EARTHWORK
IN CUBIC YARDS
STATION
UNCLASSIFIED
EXCAVATION
UNDERCUT
EMBT
+%
-L1- 81+23.35
-L1- 109+27.00
-L1- 145+75.00
-Y1- 200+00.00
-Y3- 400+06.22
108+37.00
146+00.00
178+30.71
201+68.26
433+36.97
SUBTOTAL
SUMMARY TOTAL
MATERIAL FOR SHOULDER CONSTRUCTION
LOSS DUE TO CLEARING AND GRUBBING
ADDITONAL UNDERCUT
SELECT GRANULAR MATERIAL IN LIEU OF BORROW
PROJECT TOTAL
EST. 5% TO REPLACE TOP SOIL ON BORROW PIT
GRAND TOTAL
SAY
EST. SHALLOW UNDERCUT = 100 CUBIC YARDS
CLASS IV SUBGRADE STABILIZATION = 2000 TON
1523
266
223
5
405
2422
2422
-300
2122
2122
2200
2929
3915
1459
412
1344
10059
10059
350
350
403
-230
10232
350
350
10232
PREPARED IN THE OFFICE OF:
REV. No.:
REVISION:
DATE:
DRAWN BY:
CHECKED BY:
This document, together with the concepts and designs presented herein, as an instrument of service, is
intended only for the specific purpose and client for which it was prepared. Reuse of and improper
reliance on this document without written authorization and adoption by Kimley-Horn and Associates, Inc.
shall be without liability to Kimley-Horn and Associates, Inc.
Copyright Kimley-Horn and Associates, Inc., 2025
NC LICENSE #F-0102
200 S TRYON ST, SUITE 200
CHARLOTTE, NORTH CAROLINA 28202
PHONE: (704) 333-5131
C 2026
EARTHWORK SUMMARY
BORROW
WASTE
1406
3649
1236
407
939
7637
7637
403
-230
8110
406
8516
8600
NOTE: EARTHWORK QUANTITES ARE CALCULATED BY THE ROADWAY
DESIGNER. THESE EARTHWORK QUANTITIES ARE BASED IN PART ON
SUBSURFACE DATA PROVIDED BY THE GEOTECHNICAL
ENGINEERING UNIT.
PROJECT:
CLEAR CREEK GREENWAY
JOB NUMBER:
015574013
SHEET NUMBER:
3B-1