Steven M. Clouse WRC Biosolids Upgrades

Location: Federal
Posted: May 7, 2026
Due: Aug 3, 2026
Agency: San Antonio Water System
Type of Government: State & Local
Category:
  • 70 - General Purpose Information Technology Equipment (including software).
Solicitation No: SM
Publication URL: To access bid details, please log in.
Steven M. Clouse WRC Biosolids Upgrades

IN-PERSON CONTRACTOR OUTREACH MEETING

July 28, 2025 at 10:00 am (CDT)

Steven M. Clouse Water Recycling Center

Cafeteria, Building 16

3495 Valley Rd.

San Antonio, Texas 78221

San Antonio Water System

Room: C145, Tower 2

2800 US-281, San Antonio, TX 78212

OUTREACH MEETING

Please join us for an informational meeting to discuss the Steven M. Clouse WRC Biosolids Upgrades.

This will be an in-person meeting and attendees are encouraged to arrive (10) minutes prior to the meeting.  The presentation will start promptly at 10:00 pm (CDT). The presentation will provide updated and important information about the project. To obtain additional information about the project, ask questions, or provide comment, contact Stephen Muñiz, Contract Administrator, at 210-233-2950 or via email at stephen.muniz@saws.org .

This outreach meeting is primarily for prime contractors or key subcontractors only. Refer to the project information below.

Please submit questions and/or comments by August 11, 2025 by 4:00 PM (CDT).  Answers to the questions will be posted to the web site by August 25, 2025 by 4:00 PM (CDT).

Project Description

The Steven M. Clouse Water Recycling Center (WRC), located in southeast San Antonio, is the largest of the three SAWS wastewater treatment plants and is the centralized location for handling the biosolids generated at the treatment plants.

This project will address the capacity gaps for the biosolids screening, thickening, and dewatering processes at the Steven M. Clouse WRC based on biosolids projections through 2050; replace existing equipment at the end of its useful life; prevent or mitigate higher biosolids cake management costs; and better position SAWS for possible future Class A biosolids production. The project will construct a new consolidated biosolids building that will house new biosolids screen presses, thickening, and dewatering equipment to address condition- and capacity-related needs as well as reduce the operational complexity of the existing biosolids handling system.

When Will Work Occur?

  • Construction solicitation is anticipated in the 3rd Quarter of 2026.
  • Construction is anticipated to start in the 4th Quarter of 2026.
  • Estimated construction duration is 3 years.
  • Estimated construction budget is >$100M.

What to Expect:

  • A new centralized biosolids building with new solids screen presses, thickening, and dewatering equipment sized to process current and projected 2050 biosolids loads
  • New cake storage silos
  • A new biosolids laboratory with office and storage spaces, a new parking lot, roads, and sidewalks
  • Demolition of the current belt filter press pavilion
  • Adequate levels of system automation, controls, and instrumentation to optimize plant operation and performance
  • Associated site/civil, mechanical, structural, architectural, electrical and instrumentation and controls work

SAWS Contract Administration Point of Contact:

Stephen Muñiz, Contract Administrator

Email: Stephen.Muniz@saws.org

Phone: 210-233-2950

Notify Me


Receive updates sent straight to your inbox.
Subscribe
Downloads

Not logged in

Contractor Outreach Fact Sheet


Mar. 26, 2025

Outreach Meeting Sign-in Sheet


Jul. 29, 2025

Outreach Meeting Contracting Presentation


Jul. 29, 2025

Outreach Meeting Engineering Presentation


Jul. 29, 2025

Q & A


Jul. 11, 2025



Questions? Please contact

Stephen Muniz

at 210-233-2950 |

Receive Email Updates |
Registration Agreement

Attachment Preview

Steven M. Clouse WRC Biosolids Upgrades
The Steven M. Clouse Water Recycling Center (WRC), located in southeast San Antonio, is the largest of the three
SAWS wastewater treatment plants and is the centralized location for handling the biosolids generated at the
treatment plants.
This project will address the capacity gaps for the biosolids screening, thickening, and dewatering processes at the
Steven M. Clouse WRC based on biosolids projections through 2050; replace existing equipment at the end of its
useful life; prevent or mitigate higher biosolids cake management costs; and better position SAWS for possible future
Class A biosolids production. The project will construct a new consolidated biosolids building that will house new
biosolids screen presses, thickening, and dewatering equipment to address condition- and capacity-related needs as
well as reduce the operational complexity of the existing biosolids handling system.
When Will Work Occur?
Construction solicitation is anticipated in the 3rd
Quarter of 2026.
Construction is anticipated to start in the 4th Quarter
of 2026.
Estimated construction duration is 3 years.
Estimated construction budget is >$100M.
What to Expect:
A new centralized biosolids building with new solids
screen presses, thickening, and dewatering
equipment sized to process current and projected
2050 biosolids loads
New cake storage silos
A new biosolids laboratory with office and storage
spaces, a new parking lot, roads, and sidewalks
Demolition of the current belt filter press pavilion
Adequate levels of system automation, controls, and
instrumentation to optimize plantoperation and
performance
Associated site/civil, mechanical, structural,
architectural, electrical and instrumentation and
controls work
For more information:
Hari Ponnekanti, P.E.
Hari.Ponnekanti@saws.org
210-233-2352
SAWS Contracting
Stephen Muniz
Stephen.Muniz@saws.org
210-233-2350
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

...Follow Replace filter media of Water Treatment Plant at Camp Humphreys Active Contract ...

DEPT OF DEFENSE

Bid Due: 9/01/2026

...Follow Replace filter media of Water Treatment Plant at Camp Humphreys Active Contract ...

DEPT OF DEFENSE

Bid Due: 9/01/2026

.../TEST/INSPECT- WATER PURIFICATION AND SEWAGE TREATMENT EQUIPMENT NAICS Code: 221310 - Water Supply... ...

VETERANS AFFAIRS, DEPARTMENT OF

Bid Due: 9/04/2026

...Follow 46--MODIFICATION KIT,WATER Active Contract Opportunity Notice ID SPE8E826Q0358 Related... Initiative: None Classification ...

DEPT OF DEFENSE

Bid Due: 9/21/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.