PROJECT INFORMATION SHEET
CONSTRUCTION - GENERAL CONTRACTOR/TRADE CONTRACTOR
INVITATION TO BID
ELIGIBLE PREQUALIFIED BIDDERS: The following Contractors are prequalified and may submit a bid for
this Project:
• All State Construction Inc
• BRD Builders LLC
• Carlin Construction Company, LLC
• Connecticut Carpentry Corporation
• Daniel O'Connells Sons Inc
• DEF Services Group, Ltd
• Dimeo Construction Company
• Diversity Construction Group
• Downes Construction Company
• G. Donovan Associates, Inc.
• JLY Enterprises LLC
• KBE Building Corporation
• Kronenberger & Sons Restoration LLC
• Lee Kennedy Co., Inc.
• Loureiro Building Construction, LLC
• Mattern Construction, Inc.
• Noble Construction & Management Inc
• Nosal Builders, Inc.
• O&G Industries, Inc.
• Pat Munger Construction Company, Inc.
• Richards Corporation
• Sarazin General Contractors, Inc.
• Scope Construction Company Inc.
• The Associated Construction Company
• The Morganti Group, Inc.
• The Whiting-Turner Contracting Company
• Turner Construction Company
• Western Buiders, Inc.
• Wohlsen Construction Company, Inc.
• Zlotnick Construction
Construction GC-Trade ITB, July 2024
Page 1 of 2
PROJECT SCHEDULE/DURATION:
• Anticipated Contract Issuance/Notice to Proceed: April 2026
• Construction is planned to start: May 12, 2026
• Substantial Completion: August 22, 2026
PROJECT DESCRIPTION/SCOPE OF WORK: Install new plumbing risers on floors 2-9 in Ellsworth Residential
Hall and replace existing shower stalls and plumbing on floors 6-9 in Ellsworth Residential Hall. Project
to comply with International Energy Conservation Code and the International Building Code along with Fire
Classification codes.
The work that will be required includes but is not limited to the following:
• Removal of existing showers on floors 6-9 in Ellsworth Res Hall
• Removal of an existing urinal or toilet on floors 6-9 of Ellsworth Res Hall
• Removal of existing domestic water risers, existing waste and vent risers on floors 2-9 in
Ellsworth Res Hall
• Installation of new domestic water risers, waste and vent risers on floors 2-9 in Ellsworth Res
Hall
• Installation of new shower units including fixtures and drain assemblies in Ellsworth Res
Hall on floors 6-9
• Installation of one new toilet per floor in Ellsworth Res Hall floors 6-9
• Ceilings to be removed beneath all locations where showers are to be removed and replaced.
• Additional framing included where new shower install deems necessary.
• New Shower accessories to be installed to achieve all code requirements
• Removal and reinstallation of existing partitions where shown on drawings.
• New lighting to be installed where ceilings are removed during demo phase and new light is
shown on new ceiling drawings
Construction GC-Trade ITB, July 2024
Page 2 of 2