Project Description: The following is a general sequence of Work to be completed under this project:
A. Remove existing storm drain pipe and concrete waterway and install storm drain pipe and structures;
B. Loop utility conflicts as necessary;
C. Rotomill existing asphalt and regrade west leg of intersection with approximately 18-inches of fill at the concrete waterway and tapering in the west and east directions and prepare final grade prior to overlay;
D. Striping work;
E. All work done according to APWA Standards and Specifications.
Complete bid documents for this project can be viewed/downloaded from the FILES section of this advertisement.

With GovernmentContracts, you can:
...and striping, storm drainage, 2" water supply, 1" water supply, water line and ...
State Government of Utah
Bid Due: 6/09/2026
...grading, drainage, utilities, concrete flatwork, asphalt trails, raised planters, restroom...
City of St. George
Bid Due: 6/11/2026
...drainage system. All ponds will be lined with a bituminous liner. The project ...
State Government of Utah
Bid Due: 6/23/2026
...roadway complete with curb and gutter, asphalt and drainage improvements on Minuteman Drive ...
State Government of Utah
Bid Due: 6/12/2026