| Location: | Virginia |
|---|---|
| Posted: | Jan 9, 2026 |
| Due: | Jan 19, 2026 |
| Agency: | DEPT OF DEFENSE |
| Type of Government: | Federal |
| Category: |
|
| Solicitation No: | W91QF526RA002 |
| Publication URL: | To access bid details, please log in. |
APEX Accelerators are an official government contracting resource for small businesses. Find your local APEX Accelerator (opens in new window) for free government expertise related to contract opportunities.
APEX Accelerators are funded in part through a cooperative agreement with the Department of Defense.
The APEX Accelerators program was formerly known as the Procurement Technical Assistance Program (opens in new window) (PTAP).
ADDENDUM #3 1/9/26
RFI #2
1. Is the 2 hour on site requirement for Emergence call a must have?
a. Yes. These are back-up generators that need to be operational within 2hrs or less as IT equipment switches to battery back-up which only lasts for a very short time with the heavy data center load.
2. Can you clarify the Testing requirements for the Load Banking of each generator ? Load Percentages and time for each level
a. This is outlined within PWS para 4.1.5.1
i. 30 minutes at 20% of rated load of genset.
ii. 30 minutes at 50% of rated load of genset.
3. Are there different requirements for each generator?
a. No, generators are all Caterpillar and follow the same type of load bank testing.
4. How often does the Load Testing happen, and what time of year?
a. This is outlined with PWS para 4.1.5.1
i. Annual load bank test
5. Doing the Advantage ESC, witch CAT Dealership does the report get sent to?
a. Once the vendor performs services, they return to their office to finalize the service and send a copy to our facilities management team and the COR. This action usually takes them less than 2-3 days (depending on workload)
END
ADDENDUM #2 1/8/26
An updated Combined Synopsis has been posted.
END
ADDENDUM #1 1/6/26
RFI #1
1. Could you please confirm whether this is a new requirement? If not, we kindly request the incumbent contractor’s name and the previous contract number.
a. This action is a follow-on requirement
Contract number: W91QF0-21-P-0040
Contract Awardee: Virginia Energy & Lighting, LLC.
Description of requirement: Caterpillar Diesel Standby Generator Preventive Maintenance (PM) and Emergency Repair Services (ERS)
Method of procurement: Set-Aside Small Business
Contract type: Firm-Fixed Price
Number of option periods: 4
2. Additionally, are there any notable changes to the scope of work compared to the prior award?
a. The scope of the contract has changed significantly since the previous award. Key additions include annual Advantage Extended Service Coverage (ESC) certification inspection, load bank testing, battery replacement, consumable parts replacement, and fluid sampling and testing services. These enhancements were introduced to address the requirements brought about by upgraded equipment, improved maintenance procedures, the need for additional coverage for new assets, and expanded preventive maintenance services. Incorporating fluid sampling also helps prevent equiopment damage, making the new contract more comprehensive and cost-effective by consolidating service that were previously sourced separately at higher expense.
END
This is to confirm that the site visit for the requirement is scheduled for January 7, 2026, at 0900 AM. Please confirm by email to Myrisha Mullen @ myrisha.l.mullen2.civ@army.mil, if you will be in attendance.
Please find attached the following documents for your reference:
Additionally, please note that the deadline for submitting questions is January 9, 2026, at 1500 PM.
| Dec 17, 2025 | [Solicitation (Original)] Generator Semi-Annual Preventive Maintenance (PM), Emergency Repair Services (ERS) |
| Jan 6, 2026 | [Solicitation (Updated)] Generator Semi-Annual Preventive Maintenance (PM), Emergency Repair Services (ERS) |
| Jan 8, 2026 | [Solicitation (Updated)] Generator Semi-Annual Preventive Maintenance (PM), Emergency Repair Services (ERS) |

With GovernmentContracts, you can: