General Engineering Consultant (GEC) for Preconstruction Services Master Contract

Brief Description: MnDOT requests responses for General Engineering Consultant (GEC) services that would support the Department’s need for preconstruction project activities and services. The goal of the GEC Program is to have the successful responders deliver preconstruction activities and services.  This GEC Program will focus on areas where MnDOT must act quickly to meet time, resource, or planning constraints. It is anticipated that the majority of work orders will be comprised of Core Project Development Activities as defined in Exhibit A.

Date posted: 10/09/2026
Due date: 11/17/2026

Attachment Preview

Pre-Letting Services Master Contract
Exhibit A
Scope of Work
*For purposes of this Exhibit MnDOT means State and General Engineering Contractor (GEC)
means Contractor.
1.0 General Requirements
This section outlines a general list of the responsibilities and requirements for the
General Engineer Contractor (GEC). It is anticipated that the GEC will be used to support
and supplement MnDOT staff in a variety of roles. The skill sets and number of GEC
personnel will vary with each Work Order.
Functional experts used as a resource or in an advisory role do not need to be
registered/ licensed in the State of Minnesota, but qualifications must be approved by
MnDOT.
1.1 General Staffing Requirements
1.1.1 The GEC may only use competent personnel who are qualified by experience,
education and licensing as indicated. Minimum qualifications for some example
positions are defined in this section. For any specific project Work Order, MnDOT may
require that these minimum qualifications be altered in specific instances when the
unique nature of the work requires specific or more specialized skills that are not shown
below.
1.1.2 The GEC will adequately staff each Work Order sufficiently in advance of the
beginning of work on that project to be properly prepared to satisfy its responsibilities.
The GEC must not assign any additional personnel (beyond those included in the GEC
proposal) to any project until reviewing the proposed staffing plan with the MnDOT
work order Project Manager.
1.1.3 An individual, who is previously approved by the Project Manager, but whose
performance is later determined by the Project Manager to be unsatisfactory, will not
be allowed to continue on the project and may be replaced by the GEC if the alternate is
acceptable to the Project Manager.
1.1.4 MnDOT considers that any personnel identified in the GEC's proposal will be
assigned to Work Orders and committed to performing program support services. Any
changes in personnel from the people identified in the GEC's proposal will need to be
reviewed with the work order Project Manager.
1.1.5 Specific personnel, experience, licensure, and registration requirements may
vary from project to project, but will be specifically defined in each project Work Order.
The personnel, experience, licensure, and registration requirements shown below are a
representative sample of what MnDOT would require on specific project or program
support activities.
1.1.6 All key personnel must be effective communicators in spoken and written
English and must exercise initiative and independent judgement in the solution of the
work problems.
1

Pre-Letting Services Master Contract
Exhibit A
Scope of Work
1.2 Program and Project Manager(s)
1.2.1 Program Manager
a) Primary role is to act as MnDOT's single point of contact for this Program
(Master Contract) and organize staff to meet deliverables and deadlines within
the Work Orders. Minimum qualifications include:
i. Extensive knowledge of professional/technical contracting in the
transportation industry and with MnDOT.
ii. Effective communicator.
iii. Able to plan and organize the work of subordinate staff members.
1.2.2 Project Managers for Work Order Contracts
a) B.S. in Civil Engineering or equivalent in accordance with type of work
b) Registration as a professional engineer in the state of Minnesota or equivalent
by the time the Master Contract is executed.
c) Extensive knowledge and experience delivering transportation projects to
letting.
d) Able to plan and organize the work of subordinate staff members.
e) Develop and review methods, practices, and procedures for conformity with
MnDOT standards.
f) Exercise initiative and independent judgment in the solution of work problems.
1.3 Design Engineers
1.3.1 Roadway Design Engineer(s)
a) B.S. in Civil Engineering or equivalent.
b) Registration as a professional engineer in the state of Minnesota by the time the
Master Contract is executed.
c) Engineering experience in road design on state transportation projects.
d) Direct a highly complex and specialized design review program.
e) Able to plan and organize the work of subordinate staff members.
f) Develop and review policies, methods, practices, and procedures and review
programs for conformity with MnDOT standards.
g) Exercise initiative and independent judgment in the solution of work problems.
1.3.2 Hydraulics Engineer(s)
a) B.S. in Civil Engineering or equivalent.
b) Registration as a professional engineer in the state of Minnesota by the time the
Master Contract is executed.
c) Experience with configuring inlets to meet MnDOT spread criteria and design
storm sewers on MnDOT's highway system.
d) Experience using HydroCAD and XP-SWMM to design systems of wet storm
water ponds and infiltration/filtration basins to meet rate control, water quality,
and volume control requirements for highway drainage systems.
e) Experience completing waterway analysis with HECRAS, HY8, SRH2D, or other
relevant software packages.
f) Permitting experience related to hydraulic design and wetland impacts.
g) Familiarity with MnDOT's HydInfra rating system and database and
rehabilitation techniques for drainage infrastructure.
2

Pre-Letting Services Master Contract
Exhibit A
Scope of Work
h) Experience developing erosion control plans, turf establishment plans, and
Storm water Pollution Prevention Plans (SWPPP) for highway projects.
1.3.3 Traffic Engineer(s)
a) B.S. in Civil Engineering or equivalent.
b) Registration as a professional engineer in the state of Minnesota by the time the
Master Contract is executed.
c) Traffic engineering experience on MnDOT's highway system.
d) Traffic safety analysis.
e) Traffic modeling, forecasting, and Interstate Access Requests experience.
f) Transportation Management Plan development experience.
g) Non-motorized aspects of traffic engineering.
h) Signing, signal, lighting, pavement marking, temporary traffic control, and
Intelligent Transportation Systems (ITS) design experience.
i) Able to receive general instructions regarding assignment to exercise initiative
and independent judgment in the solution of work problems.
1.4 Bridge/Structural Engineers
1.4.1 Senior Structures Design Engineer
a) B.S. in Civil Engineering or equivalent.
b) Registration as a professional engineer in the state of Minnesota by the time the
Master Contract is executed.
c) Bridge and structures design experience for new/replacement and repair
projects on MnDOT's highway system.
d) Direct a highly complex and specialized design review program.
e) Able to plan and organize the work of subordinate staff members.
f) Able to receive general instructions regarding assignment to exercise initiative
and independent judgment in the solution of work problems.
1.4.2 Structures Design Engineer(s)
a) B.S. in Civil Engineering or equivalent.
b) Registration as a professional engineer in the state of Minnesota by the time the
Master Contract is executed.
c) Bridge and structures design experience for new/replacement and repair
projects on MnDOT's highway system.
d) Able to receive general instructions regarding assignment to exercise initiative
and independent judgment in the solution of work problems.
1.5 Engagement Task Lead
a) Experience with implementing transportation public engagement processes as
outlined in Section 2.12.
1.6 Environmental Task Lead
a) Degree requirement intentionally omitted from these criteria, recognizing that a
variety of educational backgrounds are applicable to this position.
b) Experience with the preparation of environmental documents such as
Environmental Assessments, Environmental Assessments Worksheets,
Categorical Exclusions and 4(f) Documentation.
3

Pre-Letting Services Master Contract
Exhibit A
Scope of Work
c) Experience with coordinating and obtaining permits from local, state and
federal agencies.
d) Experience with state environmental laws and federal National Environmental
Policy Act (NEPA) requirements.
e) Experience with the development of Environmental Management Plans.
1.7 Quality Coordinator
a) Experience with implementing and assisting staff in performing quality
management processes and procedures.
2.0 Core Project Development Activities
It is anticipated that the majority of work orders will be comprised of the following Core
Project Development activities.
2.1 Bridge Specifications and Design Criteria
Those tasks required to prepare the written special provisions and design criteria
required for the bridge construction that supersede or supplement MnDOT standard
specifications and the information shown on the plan.
2.2 Preliminary Bridge Plans
All tasks necessary to prepare type, size, and location drawings for a bridge project.
Drawings must show span arrangements, roadway cross sections, and any other
information necessary to guide final design activities for the bridge(s). Work may
include any of the following:
a) Bridge hydraulics
b) Bridge foundations
c) Bridge surveys
d) Structure depth iterations
e) Structure grade reviews
f) Plan preparation
g) Quality Control (QC) activities
2.3 Bridge Visual Quality
All tasks necessary to determine or make recommendations for the type and extent of
bridge aesthetics treatments. Work may include participating in and/or conducting
meetings, developing Visual Quality Manuals, preparing aesthetic guidelines, producing
renderings, etc.
2.4 Bridge Repair Recommendation Development
All tasks necessary to develop recommendations for bridge repair projects. Work may
include development of safety recommendations, paint recommendations, or full repair
recommendations for bridge work.
2.5 Final Bridge Plans
All tasks necessary to produce certified bridge construction plans and special provisions
for new/replacement and repair projects. Work may include any of the following:
a) Bridge hydraulics
b) Bridge surveys
4

Pre-Letting Services Master Contract
Exhibit A
Scope of Work
c) Foundations information
d) Bridge Aesthetics
e) Constructability Reviews
f) Cost Estimates
g) Plan Preparation
h) QC activities
i) Load Ratings
2.6 Noise Analysis
All tasks associated with preparing preliminary noise analysis, including data collection,
background measurements, modeling, noise barrier analysis and design, public
involvement, and documents for inclusion in environmental documents.
2.7 Air Quality Analysis
All tasks associated with preparing the necessary air quality analysis, including data
collection, background air quality sampling, modeling (both Mobile Source Air Toxics
and Carbon Monoxide (CO)), public involvement, and documents for inclusion in
environmental documents.
2.8 Environmental Documentation
All tasks necessary to produce or assist MnDOT, or its consultant hired under a separate
contract, in the preparation of documents and items related to Class II - Categorical
Exclusions, Environmental Assessments (EA's), and Environmental Assessment
Worksheets (EAW's). It may also be used as a vehicle for coordination with outside
agencies (and the public) that may have an interest in the project. Work could include
any of the following:
a) Prepare document.
b) Conduct review process.
c) Incorporate comments.
d) Assist with obtaining approvals.
e) Produce and distribute documents.
f) Prepare and/or conduct public hearings or public meetings.
2.9 Geometric Layout
All tasks necessary to prepare and update Staff Approved Geometric Layouts, as defined
in Minnesota Statute 161.162, Subd. 2. Work could include any of the following:
a) Alignment and profile.
b) Cross-sections.
c) Road approach profiles and touchdown points.
d) Preparing the geometric layout and design criteria.
e) Interstate access modification requests.
f) Establishment of construction limits to support items such as:
i. Purchase of Right of way (R/W)
ii. Drainage design and considerations
iii. Staging and maintenance of traffic
iv. National Pollution Discharge Elimination System (NPDES) permit
requirements
v. Wetland mitigation
5

Pre-Letting Services Master Contract
Exhibit A
Scope of Work
2.10 Traffic Engineering and Forecasting
This task may include a variety of traffic engineering tasks used to develop preliminary
design concepts, pavement design criteria, and traffic engineering related plans. Work
could include, but is not limited to, any of the following:
a) Traffic Forecasting.
b) ESAL Calculations.
c) Traffic Counts.
d) Crash Studies.
e) Intersection Control Evaluation analysis.
f) Traffic Management Plan development.
g) Staging and Maintenance of Traffic.
h) Signing, signal, lighting, pavement marking, temporary traffic control, and/or ITS
plan sheet/special provision development.
2.11 Surveying
a) This task may include a variety of surveying activities to assist MnDOT. Work
could include, but is not limited to, any of the following:
b) Preliminary Design Mapping - obtain survey information necessary to prepare
the geometric layout, including land surveying, exhibits and map annotation.
c) Control Surveys - furnish horizontal and vertical control for the project such as
traverse/GPS control, tie sheets, photo control, placing targets for Mobile LIDAR
mapping.
d) Land Surveys - Public Land Survey sections corners, research information,
update survey base map, etc.
e) Design Survey - survey tasks necessary to complete design activities, such as
topography, cross sections, utilities, drainage, etc.
f) Bridge Survey - all tasks necessary to document bridge geometrics.
g) R/W boundary and monumentation.
2.12 Public Outreach and Engagement
All public engagement tasks necessary to aid MnDOT in informing and encouraging
participation from stakeholders and elected officials that could be impacted by the
proposed project. Work could include any of the following:
a) Support the MnDOT Project Manager in public engagement efforts.
b) Develop public engagement strategies and plans.
c) Prepare for, conduct, and document public information meetings.
* Provide supporting materials such as graphics, surveys, animations, and videos.
* Incorporate comments into Public Meeting Document.
2.13 Preliminary/Final Hydraulics Design
The tasks needed to develop preliminary hydraulic recommendations from the District
Hydraulics/Metro Water Resources Engineer. Work could include any of the following:
a) Research files.
b) Identify and prepare permits.
c) Identify and review in place drainage patterns and structures.
d) Identify new drainage patterns and design criteria.
e) Recommend preliminary construction limits.
6

Pre-Letting Services Master Contract
Exhibit A
Scope of Work
f) Prepare hydrology and hydraulic reports, designs and plans.
g) Prepare cost estimates, cost splits (by agency if applicable), and
recommendations.
2.14 Preliminary and Final Road Design
All tasks necessary to prepare the desired level of road plans, specifications and
roadway design criteria. This includes, but is not limited to, elements such as signing,
lighting, turf establishment and erosion control, ITS, intersection improvements, ADA
improvements, signal design criteria, roadway drainage considerations, ponding
locations, wetland mitigation, bike and pedestrian considerations, and estimates of
construction cost.
2.15 Permits
All tasks associated with preparing, processing, and securing permits on a project
(including but not limited to DNR, Watershed, NPDES, 404). Work could include any of
the following:
a) Prepare permit documentation.
b) Coordination and submission of documentation to permitting agencies.
c) Obtaining final permits.
2.16 Right-of-Way (R/W)
All tasks associated with assisting MnDOT with the preparation of Right-of-Way
documents and deliverables for the project. Specific tasks could include:
a) Title Opinions.
b) Right-of-Way Acquisition Package (authorization map, R/W work map, building
books).
c) Plats (plat preparation, stake boundary monumentation).
d) Pre-acquisition activities (legal descriptions, field title reports, market data
reports, relocation plans, identify replacement housing, preparation of purchase
instruments).
e) Valuation Reports.
f) Direct Purchase Orders to landowners and subsequent negotiations.
2.17 Planning Activities
All tasks necessary to assist MnDOT with planning, including;
a) Multimodal studies.
b) Safety audits.
c) Corridor studies and modelling.
d) Non-motorized transportation studies and conceptual design.
e) Grant applications and supporting documentation.
f) Greenhouse gas emissions and offsets analysis.
2.18 Digital Delivery
All tasks necessary to assist MnDOT with the application of digital delivery processes
and technologies. This work consists of technical, engineering, and coordination services
to support, accelerate, and standardize digital, model-based delivery through pilot
projects.
7

Pre-Letting Services Master Contract
Exhibit A
Scope of Work
At the project level, examples of this work may include development and technical
review of digital design deliverables; preparation of supplemental documents; reduction
of plan sheets; use of item types, clash detection, and file certification processes;
participation in project milestone meetings and facilitation of digital delivery meetings
or workshops with project stakeholders; making recommendations on project-specific
workflows; providing user support for modeling software and navigating cloud-based
model review environments; advancing interoperability and facilitating file
exchange; providing feedback on digital delivery processes, producing regular project
progress reports, and capturing lessons-learned.
2.19 Utility Coordination
All tasks associated with utility identification and coordination. Work could include any
of the following:
a) Identify utilities and assess project impacts on utilities.
b) Provide Subsurface Utility Engineering (SUE)
c) Coordinate with affected utilities.
d) Verify utility.
e) Develop utility plan information.
f) Coordinate with Central Office Utilities.
2.20 Project Cost Estimating
a) All tasks associated with the preparation of a detailed opinion of probable
construction costs. Assistance with the development of municipal, utility, and
other cost sharing agreements.
3.0 Additional Project Development Activities
3.1 Work orders may include additional Project Development Activities outside of
the Core Project Development Activities listed in Section 2.0. In this case, the work
order Project Manager will work with the GEC project manager to establish the
appropriate staffing and scope of work.
4.0 Work Order Management
4.1 All administrative work performed and invoiced under the Work Order to
maintain supervision and management of all activities. This includes any reporting
requirements to MnDOT, quality management, invoicing, and general contract
management of the Work Orders. No management or supervisor activities will be
shown under other tasks.
The remainder of this page is intentionally left blank.
8

This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

Historic Roadside Properties and Waysides: Historic Architect Design and Contract Administration - Fiscal

State Government of Minnesota

Bid Due: 11/24/2026

HVAC Upgrades Commissioning Services Dakota County is seeking proposals from qualified commissioning firms

Dakota County

Bid Due: 11/25/2026

Bid Title: RFP for CSAH 20 Final Design Category: Washington County Public Works

Washington County

Bid Due: 12/04/2026

ARCHITECTURAL & ENGINEERING SERVICES. The City of Dassel is requesting proposals from experienced

League of Minnesota Cities

Bid Due: 11/20/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.