| Location: | Minnesota |
|---|---|
| Posted: | Oct 9, 2026 |
| Due: | Nov 6, 2026 |
| Agency: | Washington County |
| Type of Government: | State & Local |
| Category: |
|
| Publication URL: | To access bid details, please log in. |
| Bid Title: |
RFP for CSAH 18 at CSAH 19 RAB Modifications
|
| Category: | Washington County Public Works |
| Status: | Open |
|
Request for Proposals (RFP) for
PROJECT COORDINATION, PRELIMINARY ENGINEERING, FINAL
DESIGN, STAKEHOLDER AND PUBLIC ENGAGEMENT AND UTILITY
COORDINATION
CSAH 18 @ CSAH 19
Roundabout Modifications Project
City of Woodbury
RFP release date: 10/9/2026
Submission due date: 11/6/2026
Government Center | 14949 62nd Street North | P. O. Box 6 | Stillwater, MN 55082-0006
P: 651-430-6001 | F: 651-430-6017 | TTY: 651-430-6246
www.washingtoncountymn.gov
Washington County is an equal opportunity organization and employer
Table of Contents
1. Introduction ......................................................................................................................................................... 3
1.1. Background Information .............................................................................................................................. 3
1.2. Project Goals and Objectives ....................................................................................................................... 3
1.3. Project Schedule .......................................................................................................................................... 4
2. Scope of Work and Deliverables .......................................................................................................................... 4
2.1. Project Management ................................................................................................................................... 4
2.2. Data Collection and Site Visit ....................................................................................................................... 5
2.3. Public and Agency Engagement ................................................................................................................... 5
2.4. Design Services ............................................................................................................................................ 5
2.5. Deliverables ................................................................................................................................................. 7
2.6. Bidding and Construction Assistance Services ............................................................................................. 7
2.7. Additional Tasks ........................................................................................................................................... 8
3. Proposal Content ................................................................................................................................................. 8
4. Proposal Submittal ............................................................................................................................................... 9
5. Proposal Evaluation ............................................................................................................................................. 9
5.1. Reserved Rights ............................................................................................................................................ 9
6. Proposal Questions ............................................................................................................................................ 10
P a g e | 2
CSAH 18 @ CSAH 19 Roundabout Modifications Project
1. Introduction
1.1. Background Information
The Washington County Public Works Department is issuing this request for proposals (RFP) to provide
project coordination, preliminary engineering, final design, stakeholder and public engagement and
utility coordination for the County State Aid Highway (CSAH) 18 (Bailey Road) at CSAH 19 (Woodbury
Dr.) Roundabout Modification Project.
In 2018, Washington County completed a study of the County State Aid Highway (CSAH) 18 (Bailey
Road) Corridor. Results of that study have been implemented via several projects, including
improvements to CSAH 18 between Pioneer Drive and CSAH 19 (Woodbury Drive), completed in 2019.
Traffic impacts related to construction on parallel routes, adjacent private development projects, and
expected growth in the area, including the Math and Science Academy, have led to increased traffic
volumes and delays at the roundabout at CSAH 18 and CSAH 19. This project will review the
roundabout capacity to identify responsible improvements to increase traffic flow.
Washington County, through its Capital Improvement Plan (CIP), has identified this project as Project
No. RB-2834. The anticipated project schedule includes preliminary design starting in 2026 and final
design and construction in 2027. Funding for the project will come from State AID.
The project will be delivered as a cooperative effort between Washington County, the City of
Woodbury and South Washington Watershed District, with Washington County serving as the lead
agency. All work performed under the anticipated contract shall comply with applicable procedures,
standards, and regulatory requirements of the Minnesota Department of Transportation (MnDOT),
MnDOT State Aid, Washington County and the City of Woodbury.
1.2. Project Goals and Objectives
The objective of this project is to improve the safety, mobility and traffic flow at the CSAH 18 and CSAH
19 intersection. In summary, the project goals are as follows:
* Produce municipally approved construction documents that meet all State AID, Washington
County, and local requirements for final design and environmental documentation, if necessary.
* Meet a schedule that ensures project advertisement by June 2027.
* Achieve a construction schedule that minimizes public inconvenience, while being sensitive to
reducing overall project costs and environmental impacts.
* Identify and implement stormwater drainage improvements that appropriately
balance the requirements of all agencies with the needs and goals of the
community.
P a g e | 3
| Overall Project Schedule | Anticipated Date |
|---|---|
| RFP Solicitation | October 2026 |
| Proposals Due | November 2026 |
| Consultant Selected | November 2026 |
| County Board Awards Consultant Contract | December 2026 |
| Project Kick-off | January 2027 |
| Data Collection | October - December 2026 |
| 60% Plan Submission | March 2027 |
| 2 Week County Review | March 2027 |
| 90% Plan Submission | May 2027 |
| 2 Week County/State AID Review | May 2027 |
| Final Plan Submission | June 2027 |
| Project Bidding | June 2027 |
| Pre Construction Open House | June 2027 |
| Construction | July 2027 |
CSAH 18 @ CSAH 19 Roundabout Modifications Project
1.3. Project Schedule
Washington County anticipates the following schedule for this project:
Overall Project Schedule Anticipated Date
RFP Solicitation October 2026
Proposals Due November 2026
Consultant Selected November 2026
County Board Awards Consultant Contract December 2026
Project Kick-off January 2027
Data Collection October - December 2026
60% Plan Submission March 2027
2 Week County Review March 2027
90% Plan Submission May 2027
2 Week County/State AID Review May 2027
Final Plan Submission June 2027
Project Bidding June 2027
Pre Construction Open House June 2027
Construction July 2027
2. Scope of Work and Deliverables
The following lists outline work tasks and associated items that shall be included as part of the contracted
services.
All reports/documentation must be developed and presented in Microsoft Office and all design files must be
developed and presented in MicroStation/Open Roads Designer (ORD) adhering to Washington County
approved formats unless otherwise noted or requested by the Consultant (the selected firm to perform this
work) with approval of the County.
The role of the selected Consultant team will be to complete all tasks necessary to take the project to a final
set of construction plans. Washington County will act as the lead agency through all aspects of the project.
The County's role as lead agency does not preclude direct and regular interaction between the Consultant,
the City of Woodbury, the Watershed District, and other agencies.
External Agency input and review is important; however, the County is to be kept informed of agency dialogue
and will assist the Consultant in determining the need and scope of interaction with a particular agency.
2.1. Project Management
The Consultant will perform all work necessary to effectively coordinate the project completion, maintain
the project schedule and budget, as well as manage the Project Management Team (PMT). The Consultant
will start with an in-person kick-off meeting at the County office. After the kick-off meeting, the Consultant
should host monthly PMT meetings, which will be a mix of virtual and in-person meetings. The proposal
should include a summary of the project management measures required to ensure that the project is
completed on time, within budget, and in accordance with applicable laws, policies, standards, and good
engineering practice. Monthly progress reports shall be submitted with each invoice.
The selected Consultant shall develop and implement a project specific Quality Management Plan, which
shall be available for review upon request during the project.
P a g e | 4
CSAH 18 @ CSAH 19 Roundabout Modifications Project
2.2. Data Collection and Site Visit
The Consultant shall collect existing data and reports relevant to the project area and obtain new
information as needed for all aspects of the project. At least one on-site coordination meeting shall be
arranged by the Consultant.
Washington County will provide the following information to the successful Consultant:
* Aerial imagery
* LIDAR
* Topographic Survey
* Existing Right of Way information
* Construction Plans/Record Drawings
* Traffic Counts
* Prior Traffic analysis and reports at the intersection of CSAH 18 and CSAH 19.
* CSAH 18 Corridor Study
* 2011 Geotechnical Report from American Engineering Testing
2.3. Public and Agency Engagement
The goal of the Washington County Public Works Department is to achieve excellence in design with every
project we do through comprehensive public involvement.
2.3.1. Project Website
Washington County will create a project-specific website, which will be available throughout the
duration of work, as well as throughout construction. The selected Consultant will be responsible
for providing text and graphics to support the website throughout the project.
2.3.2. Public Events and Newsletters
Assist the County in conducting public engagement and outreach throughout the project. This will
include but is not limited to public open houses, public mailers, social media, and email outreach as
necessary to maximize attendance and audiences. The County anticipates one pre construction open
house as part of this project. The Consultant will be responsible for developing materials to present at
this open house.
The Washington County Style Guide, shall be used to create documents for the public (newsletters,
post cards, posters, etc.), but Consultants are encouraged to developed and present cost effective
solutions to get the public involved.
2.4. Design Services
2.4.1. Utility Coordination
For the purposes of this RFP, "utilities" shall mean and include, but not be limited to, all
privately, publicly, or cooperatively-owned pipes, lines, antennas, or facilities for the distribution
or transmission of electrical energy, gasoline, oil, natural gas, water, sewage, steam, cable TV,
telephone or other material and communication lines and devices.
The Consultant shall contact Gopher State One Call to obtain a design locate requesting maps of
all utilities within the project limits to compare to the utilities shown in the topographic survey
file. The topographic survey that will be provided to the consultant includes utilities that were
marked as part of the Gopher State One Call ticket that was submitted by the County's survey
team. The Consultant will determine conflict points between planned improvements and existing
or planned utility facilities and develop and make recommendations on relocation alternatives,
P a g e | 5
CSAH 18 @ CSAH 19 Roundabout Modifications Project
with emphasis on cost effectiveness and on minimizing conflicts.
The Consultant shall obtain the locations of all utilities that exist within the limits of construction
and which may be affected by the project. Utility location information shall be obtained directly
from the utility owner unless such means is not feasible. All utilities shall be identified as to
owner, type and size. All utilities shall be shown on the plans in accordance with the
requirements of the "Utility Notification Law", Minnesota Statute Section 216D.04.
The Consultant shall contact the utility owners and use all customary procedures to review the
existing locations and discuss all utility relocations necessitated by the project construction as
well as any other revisions to the utilities, or installation of new utilities, within the project limits
which may be deemed desirable to accomplish in conjunction with the project construction or
for which the Consultant has learned will be required in the future. The procedures outlined in
the MnDOT Utility Accommodation and Coordination Manual for utility identifications and
notifications are applicable for design activities.
At least two utility coordination meetings will be arranged by the Consultant. Meeting agendas
and minutes of all such contacts, conferences and meetings with the utility companies shall be
kept and distributed by the Consultant and shall become part of the permanent project record
and shall be transferred to Washington County.
Specific areas may be identified for a utility Quality Level D and/or C. Quality levels shall be
determined according to the guidelines of ASCE/UESI/CI 38-22, entitled "Standard Guidelines for
Investigating and Documenting Existing Utilities."
2.4.2. Construction Plans and Specifications
Plans and specifications will include all elements and details required by the Minnesota
Department of Transportation (MnDOT) State Aid (CSAH), local and permitting agency standards.
At 60%, 90%, and 100% plan completion, design and supporting technical work (calculations,
assumptions, documentation, etc.) shall be submitted to Washington County for review and
comment.
At the same time as the 90% and 100% plan submittal, the consultant shall provide project
specific special provisions (600's), external agency specifications, and attachments for the bid
package (permits, etc.).
90% plans and specifications will be submitted by the Consultant to MnDOT State AID for
approval.
2.4.3. Geotechnical Evaluation
Washington County has a geotechnical report that was completed as part of the 2013
Roundabout project. This will be provided to the selected consultant. If additional borings are
deemed necessary, the County will utilize its on call geotechnical services contract to get
additional borings within the project area.
2.4.4. Wetland Delineation
If wetlands are present within the project area, the consultant shall prepare a wetland
delineation report and obtain a Notice of Decision by the watershed district/conservation
P a g e | 6
CSAH 18 @ CSAH 19 Roundabout Modifications Project
district/LGU if there are any wetlands that will be impacted by the project.
2.4.5. Drainage Design
The Consultant shall evaluate and design a drainage system that will convey storm water in a
manner that works with the proposed modifications to the existing roundabout.
2.4.6. Right-of-Way
The Consultant will determine construction limits and verify the County's permanent right-of-
way and temporary easement needs. Washington County will prepare plats, parcel sketches and
acquire right-of-way.
2.4.7. Project Costs
The Consultant will provide project cost estimates with the 60%, 90%, and final plans, and
include:
* Construction (include a 10% contingency with the 60% and 90% plans)
* Construction Engineering/Contract Admin. (8% of construction costs)
* Right-of-Way (cost to be provided by county)
* Design Engineering
* County Furnished Items, if applicable
2.4.8. Permits and Approvals
The Consultant will be responsible for identifying all permits and approvals warranted by the
proposed work with all regulatory agencies. Permits and approvals required may include but not
limited to the following: Watershed District, Minnesota Pollution Control Agency's NPDES
General Stormwater Permit and SWPPP documents.
2.5. Deliverables
The Consultant shall provide the following deliverables:
* Draft 60% and 90% Plans in 11"x17" PDF electronic format
* Signed final plans in 11"x17" PDF electronic format
* Signed final special provisions in 8.5" x 11" PDF and Word electronic format
* Final engineer's estimate in Microsoft Excel format
* Electronic design files in MicroStation/ORD format
* Quality Management Plan (QMP)
* All supporting documentation required for State Aid submittals
2.6. Bidding and Construction Assistance Services
2.6.1. Bidding Services
The Consultant shall modify plan sheets and specifications to reflect changes addressed in
addendums. The County will be responsible for packaging and posting addendums.
2.6.2. Shop Drawings
The Consultant shall be responsible to review, comment, and approve shop drawings submitted
by the Contractor during construction. The County should be included in this process.
2.6.3. Construction Support
The Consultant shall assist in answering any questions during construction by the county.
2.6.4. As-Built Drawings
Washington County will complete the post-construction survey necessary for as-built plan sets.
P a g e | 7
CSAH 18 @ CSAH 19 Roundabout Modifications Project
The Consultant shall modify the plan to incorporate any addendums, change orders, field
adjustments, or other deviations from the original bid plans. Record drawings for city utilities
shall meet the city's as- built requirements. As-Built Record Drawings shall be delivered in PDF
and MicroStation/ORD format.
2.7. Additional Tasks
The Consultant is encouraged to include and describe any additional tasks not mentioned within the RFP
that will enhance the project.
3. Proposal Content
Consultants who cannot provide the full range of requested services may submit a proposal but must clearly
note any services listed in this request which would not be provided. Consultants are also encouraged to
highlight any services for which they possess particularly notable qualifications.
All work performed under the anticipated contract must be carried out in accordance with the procedures,
requirements, and regulations of MnDOT State Aid, Washington County, and other applicable agencies including
municipalities within Washington County.
Proposals will be limited to no more than seven (7) pages in length, excluding a cover sheet, a cover letter,
and appendices. The font shall be no smaller than 11 point, 11x17 pages can be used for maps, exhibits,
and/or schedule and will count as a single page.
Appendices are anticipated to contain pre-prepared marketing materials and/or full resumes or other
supporting documents. Reviewers may or may not review material contained in appendices.
At a minimum, submitted proposals shall include:
1. Title Page/Cover Letter to introduce the Consultant submitting the proposal, including the name,
address, telephone number, and email address of the contact person(s) representing the team and the
names of other firms or individuals participating in the proposal.
2. Table of contents to identify the proposal material by section and page number.
3. A statement of the objectives, goals, and tasks to show or demonstrate the responder's understanding
of the nature of the project and the work required.
4. A description of the proposed approach and methodology to be utilized; the deliverables to be provided
by the responder; and a description of the proposed project management techniques.
5. A project manager from the firm must be identified with detailed educational experience and any other
additional information to demonstrate competence and ability to fulfill the obligations of the Contract.
The project manager must have been a project manager on a similar project prior to working on this
project. The Consultant project manager must be available in a local office (Minneapolis/St. Paul
metropolitan area) during the entire project period.
6. A detailed description of the responder's background and experience. This should include examples of
similar work indicating the responder's level of involvement in the project and shall include information
on the client contact person, address, email address, and phone number as well as original budget and
final budget and original completion date and final completion date.
Emphasis should be placed on ability and history to successfully deliver projects similar to the County's
proposed project.
7. A list of key personnel who will be assigned to the project; their area of responsibility, work experience,
P a g e | 8
| 1. Expressed understanding of the project objectives | 20% |
|---|---|
| 2. Completeness, quality, and overall technical competence of the proposal, project approach, and methodology | 20% |
| 3. The experience and qualifications of the project manager and team members and their work on similar projects | 40% |
| 4. Work plan, schedule, and availability of personnel and other resources to perform the work within the specified project schedule | 20% |
CSAH 18 @ CSAH 19 Roundabout Modifications Project
qualifications, and availability to perform the proposed work. No change in personnel assigned to the
project will be permitted without the written approval of the County's Project Manager.
8. A work plan and/or schedule identifying the major tasks to be accomplished. The work plan must
present the responder's approach, task breakdown of the major project requirements, a critical path
timeline, approach to quality control, deliverable due dates, and project completion date. This work plan
will form the basis for cost negotiations after responder selection.
9. The Proposer shall summarize the key elements of the proposal and provide a discussion as to why the
firm should be selected for this project.
10. Firms are encouraged to propose additional tasks or activities if they believe such tasks or activities will
substantially improve the results of the project. These proposed additional tasks should be separated
from the required material.
11. Provide a signed Appendix A - County's Standard Terms and Conditions as the contractor to whom the
contract is awarded shall be required to comply with the terms and conditions contained therein.
4. Proposal Submittal
To be considered, an electronic version of the proposal shall be submitted no later than 3:00 PM on Friday,
November 6, 2026 to:
Mike Kline, PE - Project Manager
michael.kline@washingtoncountymn.gov
In the event that the submitted proposals are unacceptable, the County reserves the right to reject any and
all proposals. Late submittals will not be considered.
All proposals, once submitted, become the property of the county. Submission of a proposal indicates
acceptance by the consultant of the conditions contained in this RFP unless clearly and specifically noted in
the proposal submitted and confirmed in the contract between the county and the selected consultant.
5. Proposal Evaluation
A "Qualification Based Selection" method will be used to review proposals submitted in response to this RFP.
The responder must not include price information either in the body of the proposal or as a separate submittal.
The factors and weighting on which proposals will be judged are:
1. Expressed understanding of the project objectives 20%
2. Completeness, quality, and overall technical competence of the proposal,
20%
project approach, and methodology
3. The experience and qualifications of the project manager and team members
40%
and their work on similar projects
4. Work plan, schedule, and availability of personnel and other resources to
20%
perform the work within the specified project schedule
5.1. Reserved Rights
* This RFP process does not obligate the county to award a contract or complete the services.
* The county reserves the right to waive any minor irregularities.
* The county reserves the right to reject any or all proposals.
* The county reserves the right to request additional information or clarifications from contractors.
* The county reserves the right to interview any, all, or none of the contractors.
* The county reserves the right to enter into a contract with more than one contractor.
P a g e | 9
CSAH 18 @ CSAH 19 Roundabout Modifications Project
* If the RFP process concludes by withdrawal, cancellation or rejection of all proposals, the county
reserves the right to issue another RFP for this service.
* The county shall not be liable for any expenses incurred by the contractor including but not limited
to expenses associated with the preparation and submission of the proposal.
6. Proposal Questions
Any questions regarding this RFP should be directed via email to michael.kline@washingtoncountymn.gov
by 3:00 PM on Wednesday, October 28, 2026. If a question pertains to a clarification of this RFP, the
question and answer will be posted on the County's website.
Only written questions and notifications will receive responses. Washington County reserves the right to
disregard questions received after the above deadline.
P a g e | 10

With GovernmentContracts, you can:
Project: IMACS Master Systems Integrator RFR Ref. #: Solicitation221 Department: Purchasing Type: RFP
Metropolitan Airports Commission (MAC)
Bid Due: 11/16/2026
DATE NOTICE Oct. 22, 2026 Request for proposals (PDF, 356KB) 2027 Social services
St. Louis Park city
Bid Due: 11/16/2026
Follow FMC Rochester- Install Above Ground Tanks Active Contract Opportunity Notice ID 15B41227Q00000001
JUSTICE, DEPARTMENT OF
Bid Due: 11/19/2026
division number title/general description issue date due date type Transit 26P031 NEW Green
Metropolitan Council
Bid Due: 11/24/2026