Bldg. 175 Replace Fuel Underground Storage Tank, NAS Lemoore, CA

Location: California
Posted: Feb 3, 2026
Agency: DEPT OF DEFENSE
Type of Contract: Awards
Type of Government: Federal
Category:
  • Z - Maintenance, Repair or Alteration of Real Property
Solicitation No: N62473-25-R-J514
Publication URL: To access bid details, please log in.
Follow
Bldg. 175 Replace Fuel Underground Storage Tank, NAS Lemoore, CA
Active
Contract Opportunity
Notice ID
N62473-25-R-J514
Related Notice
Contract Line Item Number
Department/Ind. Agency
DEPT OF DEFENSE
Sub-tier
DEPT OF THE NAVY
Major Command
NAVFAC
Sub Command
NAVFAC PACIFIC CMD
Sub Command 2
NAVFAC SOUTHWEST SW
Office
NAVFACSYSCOM SOUTHWEST
Award Details
  • Contract Award Date: Dec 09, 2025
  • Contract Award Number: N62473-20-D-1103
  • Task/Delivery Order Number: N62473-26-F-0039
  • Contractor Awarded Unique Entity ID: MLSMLM5BFMW5
  • Contractor Awarded Name: WU & ASSOCIATES INC
  • Contractor Awarded Address: Mount Laurel , NJ 08054 USA
  • Base and All Options Value (Total Contract Value): $2,640,000.00
General Information
  • Contract Opportunity Type: Award Notice (Original)
  • Original Published Date: Feb 03, 2026 12:20 am EST
  • Inactive Policy: Manual
  • Original Inactive Date: Feb 16, 2026
  • Initiative:
    • None
Classification
  • Original Set Aside:
  • Product Service Code: Z2GC - REPAIR OR ALTERATION OF FUEL STORAGE BUILDINGS
  • NAICS Code:
    • 236220 - Commercial and Institutional Building Construction
  • Place of Performance:
    Lemoore , CA 93246
    USA
Description

The intent of this project is to replace the underground jet fuel storage

tank at the B-175 Jet Engine Test Cell with a new, double-wall,

aboveground storage tank. Specific methods shall be as described below.





Work Requirements:





a. Construction:

1. Install new concrete pad, tank footings, and containment curb in

accordance with the drawing requirements including piping and conduit

penetrations.

2. Install a new 20,000 gallon factory fabricated, double wall, protected,

above-ground jet fuel storage tank including platform and stairway as

indicated on the drawing.

3. Install new concrete fuel pipe trench with traffic rated grating as

indicated on the drawing.

4. Install new electrical pull boxes, concrete ductbank, and conduits as indicated on the drawing.

5. Install new two new fuel pumps in accordance with the pump schedule.

6. Relocate indicated devices and piping including new cathodic protection

for underground piping.

7. Relocate existing emergency stop panel as indicated and add a new

readout for the automatic tank gauge system.

8. Install new stainless steel piping and valves as indicated to

re-establish all connections with the new above-ground tank.

9. Install bollards all the way around the new tank and pad area as

indicated on the drawing.

10. Install new light post where indicated on the drawing, including switch

near the stairwell.

11. Install new fire hydrant where indicated on the drawing.

12. Install a new eyewash station as indicated.

13. Perform all requisite equipment testing and verifications in

accordance with specification requirements.





b. Demolition:

1. Demolish and remove all concrete as indicated above the underground

tank to provide access for excavation of the tank.

2. Remove existing devices and piping to be relocated as indicated on the

drawing.

3. Remove existing emergency stop panel and associated conduit to be

relocated as indicated on the drawing.

4. Remove existing cathodic protection test wells and associated cabling

and anodes where indicated.

5. Remove existing fiberglass transition sump and concrete collar as

indicated.

6. Remove the existing fuel pumps, associated devices, and electrical

boxes and conduits as indicated.

7. Excavate and completely remove the 20,000 gallon underground jet fuel

storage tank. This tank removal must be completed (out of the ground) by

December 31st 2025. Liquidated damages may be assessed as detailed in

Section 1.7 for this activity.

8. Remove the concrete base beneath the existing underground tank.

9. Perform all requisite clean-up and testing associated with the removal

in accordance with all of the federal, state, and local environmental

requirements.

10. Remove existing fire hydrant and associated piping as indicated.

10. Remove existing valve, valve box, pedestal type hose bib, and

associated piping as indicated.

11. Remove existing bollards where indicated.

12. Remove existing concrete ductbank and conduits back to the building as

indicated.

13. Remove existing double wall fuel supply and return pipes back to the

building as indicated.


Attachments/Links
Contact Information
Contracting Office Address
  • 750 PACIFIC HIGHWAY
  • SAN DIEGO , CA 92132-0001
  • USA
Primary Point of Contact
Secondary Point of Contact
History
  • Feb 03, 2026 12:20 am ESTAward Notice (Original)
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

...area. Work includes excavation, clearing and grubbing, embankment reconstruction, placement of soil...

Contra Costa County

Bid Due: 6/09/2026

...Date: 06/09/2026 3:00PM PDT Description: Contractor will develop an excavation safety outreach...

State Government of California

Bid Due: 6/09/2026

...of the existing batting cage at Sea Cloud Park including selective removal of ...

City of Foster City

Bid Due: 6/04/2026

..., excavation, traffic control, storm water pollution prevention measures, construction of a reinforced...

Sutter County

Bid Due: 6/25/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.