Docusign Envelope ID: B6FA5536-AD2F-8B65-80CA-A407E6187709
ADDENDUM #1
AH Written Responses to questions posted to Q&A board
ISSUE DATE: Tuesday, July 7, 2026
This Addendum shall become and form a part of:
Request for Qualifications # RFQL 2026-0121
Architects and Engineering
TO ALL VENDORS This Addendum, including all articles and corrections listed
below, shall become a part of the original Request for Qualifications (“RFQL”)
package and shall be taken into account in preparing your proposal response.
The above-numbered solicitation is amended as set forth below. Vendors must
acknowledge receipt of this addendum by signing and completing Addenda
Acknowledgement Form. The Addenda Acknowledgement Form must be
submitted with the Firm’s response to this RFQL. Failure to include the Form in
the proposal response may subject your firm to disqualification.
In order to ensure that all firms are given an equal opportunity to submit a
competitive response, the following are responses to questions and/or requests for
clarification concerning RFQL 2026-0121.
*Proposal Due Date Extended to read as follows:
EVENTS
DATE AND/OR TIME
“NEW” Proposal Due Date and Time Thursday July 9, 2026 at 2:00 P.M.
EST.
Thursday, July 16, 2026 at 2:00 P.M.
EST.
Docusign Envelope ID: B6FA5536-AD2F-8B65-80CA-A407E6187709
ADDENDUM #1
Request for Qualifications # RFQL 2026-0121
Architects and Engineering
*Written Responses from Atlanta Housing to the questions received from
interested respondents via the Q&A board associated with the solicitation
event. All other terms, conditions, and specifications in the original solicitation
remain unchanged:
• Item #10 requests a "List of SBE firms that Respondents may solicit for
subcontracting opportunities." If we already have a group of subcontractors
on our team, should this list be a plan of action to add subs to our team for a
particular task order/scope of work?
AH Response:
Item #10 specifically refers to firms that fit the SBE categorization. If you have
assembled a group of subcontractors for your response, please identify those
subcontractors that qualify as SBE firms. If you do not include SBEs on your
team, you may also list SBE firms that you could add to supplement your team
should the need arise on a future task order.
• In this list of information to provide for previous project experience under
submittals section #2, item k. requests a "List of MBE/WBE/SBE firms that
Respondents may solicit for subcontracting opportunities" Since this is for
previous project experience, would you simply like a list of the team members
on the project and their MBE/WBE/SBE status?
AH Response:
Yes, that is acceptable. Also see 3.1.2(l) regarding MBE/WBE/SBE joint
venturing.
Docusign Envelope ID: B6FA5536-AD2F-8B65-80CA-A407E6187709
• Should we include resumes of Key Personnel in Uploads 3 and 4 as stated in
the portal? We're assuming we should include Resumes in "Key Personnel"
and our 5 project examples in "Project Experience" as stated in the RFQ. Is
that correct?
AH Response:
Yes. Respondents should upload information in the section corresponding to
the applicable Evaluation Factor. Resumes for proposed key personnel should
be submitted under Evaluation Factor C – Qualifications of Key Personnel,
and project examples should be submitted under Evaluation Factor D –
Project Experience.
Respondents should provide all information necessary to address the
applicable evaluation criteria and the submittal requirements identified in
Section 3.1 of the RFQL.
• As outlined in this RFQL, selected respondents from this RFQL, will then
have the opportunity to respond to a specific Task Order Request for a
particular project/scope of work. It also appears that Task Order would
contain a price and technical proposal (which would include hourly rates,
expenses, breakdown of all costs, etc.). However, it was mentioned by AH
during the pre-proposal conference for this RFQL, that we should include our
rates in this RFQL response. If this is correct, please specify where our rates
should be included in this RFQL response, and what exactly they should
contain (hourly rate, expenses, breakdown of all costs, etc.).
AH Response:
Hourly rates should be included in the RFQL so that they can be
implemented at the Task Order stage.
• What types of supplemental staff would the AH need of the A/E team?
AH Response:
The A/E bench is established and exists using the framework of a conventional
client-contractor relationship. However, there may be a need, though rare, for
Docusign Envelope ID: B6FA5536-AD2F-8B65-80CA-A407E6187709
Atlanta Housing to request temporary in-house support for internal staff
engaged in a specific task. While on-retainer services will be determined on a
case-by-case basis, it could include any service listed in Section 1.2.
• Is a hazardous material consultant required on the A/E team?
AH Response:
The ideal composition of an A/E team is contingent on the requested scope of
work in a future task order. This may include hazardous materials consulting
services. While it is up to each proposer to put forth the most complete team to
address the range of potential services listed in Section 1.2, it is not mandatory.
Proposers may choose to supplement their team in the future to respond to the
unique circumstances of a task order. In that scenario, proposers must submit
qualifications for any additional team members not represented in response to
this solicitation. See Section 3.2.
• Will AH be contracting with a CM or Owner’s Representative on any of the
anticipated projects/task orders?
AH Response:
Atlanta Housing may utilize Construction Managers, Owner's Representatives,
development partners, contractors, or other project-specific consultants as
determined by the needs of a particular project. The composition of the project
team and the contractual relationships among participants will be identified at
the Task Order stage. Respondents should assume they may be required to
coordinate with AH staff, contractors, developers, Owner's Representatives,
Construction Managers, and other consultants as applicable.
• Can AH confirm whether there are page limits, file size limits, required
tabs/sections, naming conventions, or preferred organization for the RFQL
response within the Business Management Portal?
Docusign Envelope ID: B6FA5536-AD2F-8B65-80CA-A407E6187709
AH Response:
Atlanta Housing does not identify any page limits, file size restrictions, required
naming conventions, or prescribed organizational format within the RFQL.
Respondents are responsible for providing all information required under
Sections 3 and 4 and addressing the Evaluation Factors identified in the
solicitation. Respondents are encouraged to organize their submissions in a
clear and logical manner to facilitate review and evaluation.
• Section 3.1 requests both a list of MBE/WBE/SBE firms and a narrative
regarding MBE/WBE/SBE participation, and later separately requests a list
and narrative for SBE firms. Can AH confirm whether a single coordinated
subcontracting/utilization narrative and proposed consultant list may satisfy
these requirements?
AH Response:
Yes. Respondents may submit a consolidated narrative and
consultant/subcontractor list provided the submission clearly addresses all
information requested regarding MBE, WBE, and SBE participation, as well
as SBE-specific participation. The response should identify proposed firms
and describe historical or future efforts related to joint venturing, mentoring,
subcontracting, and supplier inclusion.
• For forms such as the Section 3 Hires Tracking Form and related Section 3
documentation, should respondents complete these based on current company
information and anticipated approach, or may respondents provide a general
Section 3 compliance plan with project-specific details to be completed at the
Task Order stage?
AH Response:
Respondents should complete and submit the required Section 3 forms
identified in Section 3.3. In addition, respondents may provide a general
Section 3 Action Plan describing their anticipated approach to compliance,
training, employment opportunities, business utilization, and outreach efforts.
Because project-specific requirements may vary by assignment, additional