REQUEST FOR QUOTATION
Press Box Metal Stairs – Lookout Field
To: VENDOR COMPANY
Pre-Bid Walk Through: March 31, 2026
1:00 PM On Site
BID REPLY DUE BY: April 9, 2026, 9:00 AM
From:
Pocatello/Chubbuck School District #25
Business Operations
3115 Pole Line Rd.
Pocatello, ID 83201
(208) 235-3220 - phone
(208) 235-3280 – fax
Please promptly quote prices on item listed below. Unit price quotes to remain firm through August 2026. Bidders are
required to attend an on-site pre-bid walk-through, before bidding, on March 31, 2026 at 1:00 PM, to get an
understanding of the project. Please plan to meet in the Halliwell parking lot, adjacent to Lookout Field (Hawthorne
Middle School).
DELIVERY: All quote prices are to include FOB Pocatello, Idaho. All quotations must include the cost of the
transportation to the location as listed.
Must give notice of installation dates. Installation to be completed between June 8, 2026 and August 5, 2026.
DISTRICT REPRESENTATIVE: Inquiries or questions, contact Brian Glenn, School Plant Facilities Coordinator at
(208) 233-2604 or email: glennbr@sd25.us
WARRANTY: All items quoted to include full warranty disclosure.
PAYMENT: Prices must remain firm as quoted by supplier until quantity awarded is received. Application for payment
dated on or before the 25th of the month, shall be paid by the 15th of the following month. Application for payment
dated after the 25th of the month, shall be paid within 30 days.
EVALUATION CRITERIA: Selection of items will be evaluated based on the following:
1) Price
2) Design
3) Warranty
4) Contractor reputation
5) Delivery/Freight/Setup inclusive of uncrating, setting in place and removal of trash
REPLY DUE DATE: To be considered for purchase, all quotes are due no later than April 9, 2026 at 9:00 AM.
Request for Quotation
Metal Stairway – Press Box, Lookout Field
Page 1
REQUEST FOR QUOTATION
Date
March 20, 2026
Item Qty
1 Each
Address Reply To:
Jolene Smith
Business Operations
RE: Steel Stairway
3115 Pole Line Rd
Pocatello, ID 83201
Reply Due By:
April 9, 2026
9:00 AM
Description
Press Box Metal Stairway from ground level to landing area on
press box at Lookout Stadium.
Unit Price
1 Each Delivery & Installation
FOB: Hawthorne Middle School
1025 W. Eldredge
Pocatello, ID 83201
ESTIMATED DELIVERY & INSTALLATION DATE: _________________________________
Purchase will be put into effect by means of a purchase order executed by the Director of Business Operations.
Company Name
Address
City, State, Zip
Authorized Signature / Date
Title
Phone / Fax Number
Press Box Metal Stairway Bid Specification
Request for Quotation
Metal Stairway – Press Box, Lookout Field
Page 2
Lookout Stadium
SCOPE OF WORK: – This project is design build and quotes must include costs for all approvals, permits, materials,
installation, labor, equipment, and other necessary items for the design and fabrication, and applicable inspections.
Stairway and railings must be made of corrosion resistant material. Stairway will be located behind the west bleachers
and run from ground level to the north press box landing area.
GENERAL NOTES THAT APPLY TO ALL OF THE ABOVE BID ITEMS:
1. Contractor will submit equipment, materials and/or design submittals to the District for approval prior to ordering
equipment.
2. New installation shall meet all Federal, state and local code requirements. The contractor will be responsible for
obtaining any required permits and/or jurisdictional approvals. The contractor is responsible for providing any and
all drawings and specifications that are required by governmental agencies. The contractor will be required to
provide proof of final approval from all governmental agencies having jurisdiction over this work once the
installation is complete.
3. Manufacturer shall warrant products under normal use and service to be free from defects in materials and
workmanship for a period of one year from date of delivery. Warranty shall cover repair or replacement of such
parts determined defective upon inspection. Warranty does not cover any product or part of a product subject to
accident, negligence, alteration, abuse or misuse. Warranty does not cover any accessories or parts not supplied by
the manufacturer. Warranty shall not cover any labor expended or materials used to repair any equipment without
manufacturer’s prior written authorization.
4. The contractor shall at all times keep the premises free from accumulations of waste material or rubbish caused by
his employees or work, and at the completion of the work he shall remove all his rubbish from and about the
building and all tools and surplus materials and shall leave his work clean. In case of dispute, the owner shall
remove the rubbish and surplus materials and charge the cost to the contractor. At no time shall the School District
Dumpsters be used to remove the Contractor’s waste, garbage or scraps.
INSURANCE:
All contractors who provide goods or services to the District are required to provide the District with certificates of
insurance for General Liability, Auto Liability, Workers Compensation, and Professional Liability if applicable.
The General Liability and/or Professional Liability certificate must name the District as an additional insured under the
contractor’s policy. Certificates are to be provided to the District prior to any work commencing on District property.
This would include the placement of any equipment or materials at the work site
Minimum Insurance Limits
General Liability
$1,000,000 per occurrence
$1,000,000 products and completed operations
$1,000,000 annual aggregate
Auto Liability
$1,000,000 per occurrence
Request for Quotation
Metal Stairway – Press Box, Lookout Field
Page 3
Worker’ Compensation Statutory
Professional Liability
$1,000,000 per occurrence
$1,000,000 annual aggregate
INSPECTION OF WORK:
The representative of the owner shall at all times have access to the work wherever it is in preparation or progress and
the contractor shall provide facilities for such access and for inspection.
IDAHO EMPLOYER ALCOHOL AND DRUG-FREE WORKPLACE ACT: Include with your bid sheet a contractor’s affidavit
pursuant to Idaho Code Section 72-1717.
CONTRACTOR’S AFFIDAVIT
CONCERNING ALCOHOL AND DRUG-FREE WORKPLACE
Request for Quotation
Metal Stairway – Press Box, Lookout Field
Page 4
STATE OF
COUNTY OF
Pursuant to the Idaho Code, Section 72-1717, I, the undersigned, being duly sworn, depose and certify that named contractor
is in compliance with the provisions of Idaho Code section 72-1717; that named contractor provides a drug-free workplace
program that complies with the provisions of Idaho Code, title 72, chapter 17 and will maintain such program throughout the
life of a state construction contract and that named contractor shall subcontract work only to subcontractors meeting the
requirements of Idaho Code, section 72-1717(1)(a).
Name
Company Name
Authorized Signature / Date
Subscribed and sworn to before me this ______________ day of __________________, 2026.
Commission expires:
NOTARY PUBLIC, residing at
Request for Quotation
Metal Stairway – Press Box, Lookout Field
Page 5
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.