| Location: | South Carolina |
|---|---|
| Posted: | Jan 14, 2026 |
| Due: | Feb 17, 2026 |
| Agency: | State of South Carolina - State Fiscal Accountability Authority(SFAA) |
| Type of Government: | State & Local |
| Category: |
|
| Solicitation No: | W-25-83 |
| Publication URL: | To access bid details, please log in. |
Installation of approximately 120 LF 8 water main, 260 LF 6" water main, complete in place pipe bridge and related appurtenances to replace an old dilapidated main that is attached to the existing SCDOT bridge structure crossing Middle Fork Twelve Mill Creek.
Project funded by a grant from ARPA and the SC RIA, all Bidders must comply with all applicable state and federal requirements. SAM.GOV registratin will be used to verify debarment status as required.

With GovernmentContracts, you can:
...with the installation of the 12" Smooth Wall Pipe) * Temporary and Thermoplastic ...
County of Spartanburg
Bid Due: 9/08/2026
...@aikencountysc.gov Telephone: 8036421540 Description: Installation of approximately 368 linear feet of HDPE... sanitary ...
State of South Carolina - State Fiscal Accountability Authority(SFAA)
Bid Due: 9/22/2026
...Bid Number: 27-01-B Bid Title: New Hope Lateral Sewer Pipe Improvements Category: Request... ...
Aiken County
Bid Due: 9/22/2026
...; construction of a new transformer pad and installation of increased capacity transformer; ...
DEPT OF DEFENSE
Bid Due: 9/08/2026