| Location: | Florida |
|---|---|
| Posted: | May 14, 2025 |
| Due: | May 29, 2025 |
| Agency: | City of Sanford |
| Type of Government: | State & Local |
| Category: |
|
| Solicitation No: | IFB 24/25-23 |
| Publication URL: | To access bid details, please log in. |
| Date | Time | Mandatory | Location |
| Question | Date Asked | Answer | Date Answered |
| Please clarify the correct completion time? Pg 24 of the IFB shows 270 days. Pgs 66-67 show 365 + 60 days. | 4/22/2025 8:46:35 AM | ||
| 4/22/2025 12:40:18 PM | |||
|
1.Plans sheet 6 shows the wet well riser piping material as Ductile Iron. Will the city accept HDPE from the base elbows to the check valves in the VB. Please advise.
2.Is the old WW being converted to a MH need to be lined with Raven 405 coating. Please advise. 3.Plan sheet 4 shows the use of a line stop. Please advise what materials this needs to be made of (SS or Epoxy). 4.Plan sheet 4 in general note #2 calls for "install vapor barrier prior to concrete placement". This is normal for a house slab but have never seen it required for a driveway or slab area around a station. Please advise. 5.Plan sheet 5 shows a 6" plug valve on the suction line of the by-pass pump. Is this needed since there is no pressure from this pipe if it needs to be disconnected. Please advise. 6.Plan sheet 5 shows a pressure gauge on the vacuum suction line. I believe the tradewinds unit comes standard with this gauge on the side of it. Please advise if the second redundant gauge is still going to be required. |
4/25/2025 11:19:27 AM | ||
| What is the engineer`s estimate? | 4/28/2025 4:11:54 PM | ||
| Is there is a pre-bid meeting for this solicitation? | 4/29/2025 8:31:26 AM | ||
| Please clarify status of Emergency Bypass Pump Scope. Has it already been purchased? If not, are there conditions of service details specified? | 4/30/2025 9:10:05 AM | ||
| is a site visit available? | 5/5/2025 7:15:40 AM | ||
| Is there an engineers estimate? | 5/5/2025 7:15:47 AM | ||
| Is there a schedule of bid items (and units) or is it a single lump sum bid? p.24 of the project manual has a blank schedule of values. p.196 Summary of Work (SECTION 01110) says it’s a single lump sum contract amount. The Summary as well as the Measurement and Payment (SECTION 01270) are generalized and vary vague, yet indicates contractor is responsible for items “whether specifically indicated in the Contract Documents or not.” Is CPH going to add items after the contract award and/or during construction and make the contractor responsible for them even though it wasn’t in the bid price? Who confirms and/or validates what “is reasonably and properly inferable and necessary for the proper completion of the Work,”? | 5/5/2025 7:15:56 AM | ||
| What is the permanent bypass pump discharge size supposed to be? Sheet 5 and 7 are calling out 2 different sizes. | 5/5/2025 7:16:04 AM | ||
| Please confirm that the City will receive bids through VendorLink. | 5/5/2025 11:52:38 AM | ||
| Will there be a virtual or call-in option for the Public Opening? | 5/5/2025 11:52:55 AM | ||
| Vendorlink does not have currently have the option to upload bid, will this be updated? Or will physical delivery be required? | 5/6/2025 9:57:13 AM | ||
|
Per Page 14 of the Project Manual see below. Can you advise what the engineer/project estimate is or what percentage the bid bond shall be?
1. Construction Projects where the Maximum Bid Price is $60,000 or greater: Bid Security shall be in an amount equal to at least 5% of the Maximum Bid Price (Base Bid Plus Alternates). 2. Construction Projects where the Maximum Bid Price is less than $60,000: Bid Security shall be in an amount equal to at least 10% of the Maximum Bid Price (Base Bid Plus Alternates). |
5/6/2025 10:00:31 AM | ||
| Can the wet well be installed via the tremie method? | 5/13/2025 1:15:55 PM | ||
| Please clarify who the required RTU supplier is and whether it should be a cellular system, which would negate the antenna and antenna tower. | 5/14/2025 8:31:41 AM |
| Code | Description |
| [890-66] | Sewer Lift Stations and Parts |
| [720-56] | Pumps, Miscellaneous (Not Otherwise Classified) |
| [936-62] | Pumps and Pump Accessories Maintenance and Repair |
| [936-63] | Pumps, Vertical, Maintenance and Repair |
| [150-15] | Concrete, Polymer, All Types |
| [750-30] | Concrete, Precast |
| [060-37] | Electrical Parts (Not Ignition) (Not Otherwise Classified) |
| [914-38] | Electrical |
| [150-10] | Construction Materials (Not Otherwise Classified) |
| [912-23] | Construction, General (Backfill Services, Digging, Ditching, Road Grading, Rock Stabilization, etc.) |
| [913-19] | Construction, Curb and Gutter (Includes Maintenance, Repair, and Removal) |
| [913-59] | Construction and Upgrades, Wastewater Treatment Plant |
| [913-60] | Construction, Water System/Plants, Main and Service Line |
| [913-61] | Construction, Vertical, Concrete, Pour-In-Place, Form/Place/Finish |
| [913-62] | Construction, Concrete, Pour-In-Place, Form, Place, Finish |
| [929-31] | Construction Equipment Maintenance and Repair (Not Otherwise Listed) |
| Publication | Date |
| Orland Sentinel | 4/21/2025 |

With GovernmentContracts, you can:
...Document Title Document Number Deadline Rigdon Center - Epoxy Floors ITB FM 16-26 ...
Okaloosa County
Bid Due: 12/10/2026
..., coatings (paint & epoxy), masonry/concrete coatings, fiberglass, electrostatic painting...
Town of Palm Beach
Bid Due: 6/23/2026