| Location: | Michigan |
|---|---|
| Posted: | Oct 2, 2026 |
| Due: | Oct 22, 2026 |
| Agency: | Adrian city |
| Type of Government: | State & Local |
| Category: |
|
| Publication URL: | To access bid details, please log in. |
| Description | Opening Date/Time | Closing Date/Time |
|
Wells 2 and 4 Cleaning Bid Documents |
October 02, 2026 : |
October 22, 2026 2:00 PM |
Sealed Bid Notice Purchasing Office
Well #2 & #4 Cleaning & Redevelopment City of Adrian
Bid Year 2026-2027 October 1, 2026
Sealed bids will be received until 2:00 p.m. E.D.T. on Thursday, October 22, 2026 at the Purchasing Office, City Hall,
135 E. Maumee Street, Adrian, Michigan 49221, for Wells #2 & #4 Cleaning and Redevelopment. Scope of work and
specifications are attached.
Well #2 Cleaning and Redevelopment Base Bid Bid $____________________
Option: Well #2 Full Pump End Replacement Bid $____________________
Option: Well #2 Motor Bid $____________________
Well #4 Cleaning and Redevelopment Base Bid Bid $____________________
Option: Well #4 Full Pump End Replacement Bid $____________________
Option: Well #4 Motor Bid $____________________
Total Bid w/Options Bid $____________________
All bids must be firm for 45 days after bid opening.
Please contact Mr. Nathan Kane at (517)-264-4828 or NKane@adrianmi.gov with any questions.
The City of Adrian reserves the right to accept or reject any or all bids and to waive any irregularities.
Any deviation from specifications must be so noted.
All bids must contain descriptive literature and warranty information.
The City of Adrian has a local preference policy.
No contract shall be made with any person, firm or corporation in default of the city.
For all documents, please visit www.adriancity.com/community/reference_desk/bids.php
All contractor must sign the City of Adrian's Professional Service Contract and provide Liability Insurance and
Performance Bond.
All bids must be submitted in a sealed envelope clearly marked on the outside, " Wells #2 & #4 Cleaning &
Redevelopment"
NAME OF
COMPANY_______________________________________________________________________________________
ADDRESS_________________________________________________________________________________________
CITY___________________________________________STATE________________________ZIP_________________
BY__________________________________________________TITLE_______________________________________
TELEPHONE_________________________________________FAX_________________________________________
DATE_________________ EMAIL____________________________________________________________________
00 41 00.1
SECTION 00 41 00 BID FORM
CITY OF ADRIAN
WELL AND PUMP MAINTENANCE - WELL NOS. 2 AND 4
ARTICLE 1-SCHEDULE OF PRICES
For the entire Work outlined in these Contract Documents complete as specified, using equipment and materials only
of the type and manufacturers where specifically named, the following lump sum prices:
Well Cleaning and Pump Inspection - Well No. 2
Est Unit
Item Description Unit Quant. Price Amount
1 Mobilization/demobilization LSum 1 $ _____________ $ _______________
2 Pre/Post-Cleaning Test Pumping (2 hrs ea) LSum 2 $ _____________ $ _______________
3 Remove and Inspect Pump Assembly LSum 1 $ _____________ $ _______________
4 Video Camera Logging LSum 2 $ _____________ $ _______________
5 Mechanical and Chemical Cleaning LSum 1 $ _____________ $ _______________
Reinstall Original or Replacement Pump
6 LSum 1 $ _____________ $ _______________
Assembly and All Related Equipment
(Bacteriological testing to be performed $ _______________
Total Base Bid
by WTP staff)
Option: Full Replacement Pump End - Grundfos 800S300-1 (or if equal specify below) $
Option: Replacement Submersible Pump Motor - Franklin 30HP $
Well Cleaning and Pump Inspection - Well No. 4
Est Unit
Item Description Unit Quant. Price Amount
1 Mobilization/demobilization LSum 1 $ _____________ $ _______________
2 Pre/Post-Cleaning Test Pumping (2 hrs ea) LSum 2 $ _____________ $ _______________
3 Remove and Inspect Pump Assembly LSum 1 $ _____________
$ _______________
4 Video Camera Logging LSum 2 $ _____________
$ _______________
5 Mechanical and Chemical Cleaning LSum 1 $ _____________
$ _______________
Reinstall Original or Replacement Pump
6 LSum 1 $ _____________
Assembly and All Related Equipment $ _______________
(Bacteriological testing to be performed
Total Base Bid $ _______________
by WTP staff)
Option: Full Replacement Pump End - HydroFlo 7HL-2 (or if equal specify below) $________________
$________________
Option: Replacement Submersible Pump Motor - Franklin 25HP
10/1/2026 City of Adrian Well and Pump Maintenance, Well Nos. 2 and 4
00 41 00.2
SECTION 00 41 00 BID FORM
ARTICLE 2-MATERIAL AND EQUIPMENT ALTERNATES
The Contract Documents stipulate that the Base Bid price shall include materials and equipment selected from the
designated items and manufacturers listed therein. This is done to establish uniformity in bidding and to establish
standards of quality for the items named.
If the BIDDER wishes to quote alternate items for consideration by the OWNER, he may do so under this Article. A
complete description of the item and the proposed price differential are to be provided. Unless approved at the time of
award, substitutions, where items are specifically named, will be considered only in accordance with the terms set forth
in the General Conditions.
Add/Deduct
Item No. Description Amount (Dollars)
ARTICLE 4-SUBCONTRACTOR LISTING
Bid is submitted on the basis of the use of the following Subcontractors:
WORK ITEM FIRM CITY
Please note if work is to be performed by BIDDER. Failure to list Subcontractors with the Bid waives BIDDER'S rights
to a change in Contract Time or Price or withdrawal of Bid and Bid Security; in the event OWNER has reasonable
objection to any Subcontractor.
OWNER shall have the right to reject any Subcontractor for reasonable cause. If Subcontractors are not identified in
the Bid, the BIDDER/CONTRACTOR shall engage a Subcontractor acceptable to OWNER and waives the right to
withdraw Bid and Bid Security, and further, waives right to a change in Contract Time or Price due to failure to list.
10/1/2026 City of Adrian Well and Pump Maintenance, Well Nos. 2 and 4
City of Adrian Well Nos. 2 and 4 Well Screen Cleaning and Pump Inspection
Scope of Work
The following scope of work provides a summary of work and the equipment necessary for the cleaning
and redevelopment of the City of Adrian Well Nos. 2 and 4, and the inspection of the entire well pump
assemblies in both Well Nos. 2 and 4.
General Work Plan for Well Nos. 2 and 4 Cleaning and Pump Inspection
1. Test pump through various pumping rates (total period of 2 hours) to document pre-cleaning
well performance in accordance with the specification.
2. Remove the existing pump and motor, riser piping, power cabling, transducer cable, airline, etc.
from the well. Mark the position of the transducer in the well so that it can be replaced at the
same position when the work is completed.
3. Inspect all pump and motor components for wear. Inspect all riser piping and couplings for
wear. Report the results of this information to the owner and engineer.
4. Perform a pre-cleaning camera (video) survey of the entire casing and screen section. Report
this information to the owner and engineer before starting cleaning work.
5. Chemically clean and mechanically surge the well in accordance with the specification section.
6. Perform a post-cleaning camera (video) survey of the entire screen section at the completion of
cleaning procedures.
7. Provide a brief report outlining any repair or replacement parts, including pricing, regarding the
pump and related equipment.
8. Install pump assembly including, riser piping, check valve, cabling, etc.
9. Test pump through various pumping rates (total period of 2 hours) to document post-cleaning
well performance in accordance with the specification.
10. Provide pump and well performance testing results to Owner and Engineer (see specification
section).
33 20 01
SECTION 33 20 01 WATER WELL CLEANING AND REDEVELOPMENT
PART 1 - GENERAL
1.01 SECTION INCLUDES:
A. This section includes; Furnish all equipment and materials necessary for the cleaning and
redevelopment of Well Nos. 2 and 4. This work includes pump inspection, video camera logging and
pump/well performance testing - video logging and well performance testing will be performed two
times per well, prior to and after cleaning.
1.02 REFERENCES:
A. Michigan Water Well Disinfection Manual, Water Division, Michigan Department of Environmental
Quality, July 2003.
B. AWWA (American Water Works Association) Manual M20, 1973, Water Chlorination Principles and
Practices, John Wiley and Sons, 1984.
1.03 SUBMITTALS:
A. MSDS for well cleaning chemicals and confirmation of quantities.
1.04 DELIVERY, STORAGE AND HANDLING:
A. Protect all equipment and containers during delivery and storage on site.
PART 2 - PRODUCTS
2.01 Well Cleaning Chemicals. Certain products listed below may be available from other manufacturers by another
name but must be chemically equal. Confirm with ENGINEER if using an alternate brand.
A. Johnson Screens Nu-Well NW-120 Phosphoric Acid (75% Strength)
B. Johnson Screens Nu-Well NW-310 Biodispersant
C. Johnson Screens Nu-Well NW-410 Chlorine Enhancer
D. Sodium Hypochlorite (12% active)
E. Sodium Thiosulfate (99% strength, technical grade)
2.02 Well Cleaning Equipment - Required.
A. Well cleaning brushes sized to fit 12-inch casing. Typically manufactured by Cotey as Well Cleaning
Brush 12-inch (J400)
B. Mixing tank with enough capacity to hold the indicated quantities of chemicals - at least 2500 gallon
capacity.
PART 3 - EXECUTION
3.01 Pre-Cleaning Tasks
A. Pre-Cleaning Well Performance Test Pumping - Both Wells. This test pumping is intended to
establish the present well performance prior to the cleaning procedure. The existing pump shall be
run to waste for an overall period of two hours. The pump shall be run through the pump to waste
piping in the wellhouse. CONTRACTOR shall provide equipment and assistance necessary to
measure wire to water efficiencies at the flow rate schedule as determined by ENGINEER.
CONTRACTOR shall provide the necessary equipment to record the following data at four (4) flow
rate steps (four total measurement steps) each for a 30 minute pumped duration at the following
pumping rates; 200 gpm, 400 gpm, 600 gpm, 800 gpm (if attainable).
1. Rate of flow using OWNER'S flowmeter and CONTRACTOR'S orifice at each flow rate.
2. Depth to static water level.
3. Depth to pumping water level.
4. Pressure head reading (discharge pressure).
5. Amperage at each leg of motor (Line A, B and C).
6. Voltages for all three phases (AB, BC and AC).
7. Time of measurement
B. Video Camera Logging - Both Wells. Provide a camera (video) survey of the entire casing and
screen section prior to commencing cleaning procedures.
10/1/2026 City of Adrian Well and Pump Maintenance, Well Nos. 2 and 4
33 20 01
SECTION 33 20 01 WATER WELL CLEANING AND REDEVELOPMENT
3.02 Cleaning Procedures - This section outlines the work required for both well sites and indicates the appropriate
chemical quantities specific to each well.
A. For Both Wells: Pre-Cleaning Mechanical Brushing. Mechanical brushing from the top of the well
to the bottom using a stiff nylon bristle brush to loosen debris and scale. Well cleaning brush shall
be manufactured specifically for the use on water wells and for this purpose.
B. For Both Wells: Air lifting/pumping. Air lift or pump the well to remove loosened debris and
sediment from the bottom of the well. Water shall run generally free of debris and color prior to adding
chemicals.
C. Acid and Biodispersant Treatment. Chemical quantities are noted for each well.
1. For Well No. 2: The standing water volume in Well No. 2 is about 710 gallons. The total
treatment volume for acid treatment will be about 1.5 times the standing volume of water - this
is roughly equal to 1070 gallons. Chemical quantities to use to achieve the target concentrations
are as follows;
a. 72 gallons NW-120 Phosphoric Acid (75%) to achieve 8% phosphoric acid in the treatment
solution.
b. 18 gallons NW-310 Biodispersant to achieve 2% biodispersant in the treatment solution.
c. 1070 gallons of Potable Water
2. For Well No. 4: The standing water volume in Well No. 4 is about 520 gallons. The total
treatment volume for acid treatment will be about 1.5 times the standing volume of water - this
is roughly equal to 780 gallons. Chemical quantities to use to achieve the target concentrations
are as follows;
a. 53 gallons NW-120 Phosphoric Acid (75%) to achieve 8% phosphoric acid in the treatment
solution.
b. 13 gallons NW-310 Biodispersant to achieve 2% biodispersant in the treatment solution.
c. 780 gallons of Potable Water
3. For Both Wells: Blend chemicals in an adequately-sized poly tank in the following order; potable
water first, then phosphoric acid, then biodispersant. Mix lightly. Introduce chemicals throughout
the standing water column via tremie pipe or similar mechanism starting from the bottom.
4. For Both Wells: Surge the well using a swab block or brush specifically manufactured for the
use in water wells. Surging shall be focused on the screened interval. Assume a surging time of
6 hours. Allow the well to rest for a period of at least 12 hours after surging is complete. Maintain
a pH of 3.0 or lower throughout the surging procedure - add additional phosphoric acid
to adjust the pH down if necessary.
5. For Both Wells: Pump the well to a storage tank to purge loosened and dissolved debris from
the well. Pump until the pH has returned to normal (about 7-7.5), and the conductivity has
returned to normal (about 900 S/cm) and the water is free of turbidity and color.
6. For Both Wells: Neutralize the purged water with an alkaline product as sodium hydroxide,
sodium bicarbonate, or potassium hydroxide. Once neutralized to a pH of about 7 and solids
have settled, dispose of the solution according to local and state guidelines.
D. Phase I Disinfection. Chemical quantities are noted for each well.
1. For Well No. 2: Prepare a disinfection solution of 200-ppm chlorine for two (2) times the standing
well volume of the well - this is equal to about 1420 gallons of solution. Chemical quantities to
use to achieve the target concentration are as follows;
a. 2.4 gallons 12% sodium hypochlorite
b. 1420 gallons of potable water
2. For Well No. 4: Prepare a disinfection solution of 200-ppm chlorine for two (2) times the standing
well volume of the well - this is equal to about 1040 gallons of solution. Chemical quantities to
use to achieve the target concentration are as follows;
a. 1.7 gallons 12% sodium hypochlorite
b. 1040 gallons of potable water
10/1/2026 City of Adrian Well and Pump Maintenance, Well Nos. 2 and 4
33 20 01
SECTION 33 20 01 WATER WELL CLEANING AND REDEVELOPMENT
3. For Both Wells: Blend chemicals in an adequately-sized poly tank adding additional sodium
hypochlorite if necessary to achieve a 200 ppm chlorine solution. Introduce chemicals
throughout the standing water column via tremie pipe or similar mechanism starting from the
bottom.
4. For Both Wells: Surge the well lightly using a swab block or brush for at least six (6) hours to
allow sufficient contact time within and outside the well screen. Maintain a chlorine concentration
of 200 ppm throughout this surging procedure - add sodium hypochlorite if necessary.
5. For Both Wells: Pump the well to a storage tank to purge loosened and dissolved debris from
the well until a minor residual is present - about 50 ppm chlorine and conductivity has returned
to normal (about 900 S/cm) and the water is free of turbidity and color.
6. For Both Wells: Neutralize the purged water with sodium thiosulfate - utilize one (1) pound
sodium thiosulfate for every 1000 gallons of 150 ppm purge water. Once the chlorine has been
neutralized and solids have settled, dispose the solution according to local and state guidelines.
E. Phase II Disinfection.
1. For Well No. 2: Prepare a pH-adjusted disinfection solution of 300-ppm chlorine in the pH range
of 6.5-7 for three (3) times the standing well volume of the well - this is equal to about 2130
gallons of solution. Chemical quantities to use to achieve the target concentration are as follows;
a. 5.3 gallons 12% sodium hypochlorite
b. 11 gallons of NW-410 Chlorine Enhancer
c. 2130 gallons of potable water for blending
2. For Well No. 4: Prepare a pH-adjusted disinfection solution of 300-ppm chlorine in the pH range
of 6.5-7 for three (3) times the standing well volume of the well - this is equal to about 1560
gallons of solution. Chemical quantities to use to achieve the target concentration are as follows;
a. 4 gallons 12% sodium hypochlorite
b. 8 gallons of NW-410 Chlorine Enhancer
c. 1560 gallons of potable water for blending
3. For Both Wells: Blend chemicals in an adequately-sized poly tank starting with the chlorine
enhancer. Add additional sodium hypochlorite if necessary to achieve a 300 ppm chlorine
solution. Introduce chemicals throughout the standing water column via tremie pipe or similar
mechanism starting from the bottom.
4. For Both Wells: Surge the well lightly using a swab block or brush for at least six (6) hours to
allow sufficient contact time within and outside the well screen. Maintain a chlorine concentration
of 300 ppm throughout this surging procedure - add sodium hypochlorite if necessary.
5. For Both Wells: Pump the well to a storage tank to purge loosened and dissolved debris from
the well until a minor residual is present - about 50 ppm chlorine and conductivity has returned
to normal (about 900 S/cm) and the water is free of turbidity and color.
6. For Both Wells: Neutralize the purged water with sodium thiosulfate - utilize one (1) pound
sodium thiosulfate for every 1000 gallons of 150 ppm purge water. Once the chlorine has been
neutralized and solids have settled, dispose the solution according to local and state guidelines.
F. Pump Disinfection - Both Wells: Before placing associated equipment back into the well, disinfect
all outside surfaces using a handheld spray rig with a 100-ppm sodium hypochlorite solution - use
3.2 mL (0.11 fluid oz.) 12% sodium hypochlorite for each 1-gallon of potable water.
G. Post-Cleaning Well Performance Test Pumping - Both Wells:. This test pumping is intended to
establish the well performance after the cleaning procedure. The test pumping shall be run to waste
for an overall period of two hours using either the original pump or the CONTRACTOR's test pump.
The pump shall be run through the pump to waste piping in the wellhouse if the original pump is used,
or pumped to the ground if a test pump is used. CONTRACTOR shall provide the necessary
equipment to record the following data at four (4) flow rate steps (four total measurement steps) each
for a 30 minute pumped duration at the following pumping rates; 200 gpm, 400 gpm, 600 gpm, 800
gpm.
If using a test pump, record the following information;
1. Rate of flow using OWNER'S flowmeter and/or CONTRACTOR'S orifice at each flow rate.
10/1/2026 City of Adrian Well and Pump Maintenance, Well Nos. 2 and 4
33 20 01
SECTION 33 20 01 WATER WELL CLEANING AND REDEVELOPMENT
2. Depth to static water level.
3. Depth to pumping water level.
4. Time of measurement
If using a new replacement pump or refurbished original well pump, record the following
additional information;
5. Pressure head reading (discharge pressure).
6. Amperage at each leg of motor (Line A, B and C).
7. Voltages for all three phases (AB, BC and AC).
H. Chlorinate the well following completion of all work at the site.
I. Procedure: prepare and apply chlorine solution to produce chlorine concentration of 100 ppm residual
free chlorine in all parts of the well.
J. Pump to waste through watermain to wellhouse to pump-to-waste discharge until chlorine residual is non-
detect. City Water Treatment Plant staff to perform required bacteriological testing.
END OF SECTION
10/1/2026 City of Adrian Well and Pump Maintenance, Well Nos. 2 and 4

With GovernmentContracts, you can:
...Bid Number: ITB - 4692 Bid Title: ITB 4692 - Midland WTP Chemical ...
City of Midland
Bid Due: 10/27/2026
...Bracket, Hand Port 46514 Cardiovascular Instrumentation: Defibrillators, Heart Pumps, Additional...
State of Michigan
Bid Due: 10/28/2026
...the control cabinet and generator and other miscellaneous equipment at Pump Station No. ...
Macomb township
Bid Due: 11/05/2026