North Downtown Parking Lot Resurfacing Bid Tabulation
|
| Category: | Bid Results |
| Status: | Open |
|
| Engineers Estimate | Advantage Paving | K Five | Gallagher | Dale, Inc. | ||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| ITEM NO. | DESCRIPTION | ENGINEER'S ESTIMATED QUANTITY | UNIT PRICE | EXTENDED AMOUNT | UNIT PRICE | EXTENDED AMOUNT | UNIT PRICE | EXTENDED AMOUNT | UNIT PRICE | EXTENDED AMOUNT | UNIT PRICE | EXTENDED AMOUNT |
| 1 HMA Surface Removal-Milling (2.0") | 12,850 S.Y. | $3.50 $44,975.00 $0.10 $600.00 $90.00 $135,000.00 $0.50 $5,000.00 $10.00 $1,200.00 $500.00 $2,500.00 $500.00 $5,000.00 $100.00 $1,000.00 $2,000.00 $2,000.00 | $1.95 $25,057.50 $0.01 $60.00 $102.85 $154,275.00 $0.90 $9,000.00 $24.25 $2,910.00 $56.00 $280.00 $40.00 $400.00 $0.01 $0.10 $17.40 $17.40 | $4.05 $52,042.50 $0.01 $60.00 $87.00 $130,500.00 $0.70 $7,000.00 $8.10 $972.00 $685.00 $3,425.00 $1,350.00 $13,500.00 $250.00 $2,500.00 $6,000.00 $6,000.00 | $2.85 $36,622.50 $0.01 $60.00 $84.50 $126,750.00 $0.75 $7,500.00 $2.15 $258.00 $195.00 $975.00 $300.00 $3,000.00 $45.00 $450.00 $9,250.00 $9,250.00 | $11.50 $147,775.00 $1.50 $9,000.00 $110.00 $165,000.00 $0.50 $5,000.00 $9.00 $1,080.00 $750.00 $3,750.00 $750.00 $7,500.00 $495.00 $4,950.00 $2,500.00 $2,500.00 | ||||||
| 2 Bituminous Materials (Tack Coat) | 6,000 LBS | $0.10 | ||||||||||
| 3 HMA Surface Course, Mix D, N50. (2.0") 4 Striping (Paint), 4" Yellow 5 Striping (Paint), Letters and Symbols Yellow 6 Water Valve Box Adjustment 7 MH Frame Adjustments 8 Inlet Protection 9 Traffic Control and Protection | 1,500 TON 10,000 FT. 120 S.F. 5 Each 10 Each 10 Each 1 L.S. |
| M/ J Asphalt | Everlast Blacktop | "D" Construction | McGill Construction | Iroquois Paving | ||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| ITEM NO. | DESCRIPTION | ENGINEER'S ESTIMATED QUANTITY | UNIT PRICE | EXTENDED AMOUNT | UNIT PRICE | EXTENDED AMOUNT | UNIT PRICE | EXTENDED AMOUNT | UNIT PRICE | EXTENDED AMOUNT | ||
| UNIT | EXTENDED | |||||||||||
| PRICE | AMOUNT | |||||||||||
| 1 HMA Surface Removal-Milling (2.0") | 12,850 S.Y. | $2.35 $30,197.50 $0.01 $60.00 $96.00 $144,000.00 $0.35 $3,500.00 $13.00 $1,560.00 $380.00 $1,900.00 $750.00 $7,500.00 $150.00 $1,500.00 $4,350.00 $4,350.00 | $2.69 $34,566.50 $0.55 $3,300.00 $106.37 $159,555.00 $0.80 $8,000.00 $9.20 $1,104.00 $519.54 $2,597.70 $491.50 $4,915.00 $125.00 $1,250.00 $5,000.23 $5,000.23 | $2.10 $26,985.00 $0.01 $60.00 $88.00 $132,000.00 $1.28 $12,800.00 $50.60 $6,072.00 $300.00 $1,500.00 $900.00 $9,000.00 $200.00 $2,000.00 $4,700.00 $4,700.00 | $2.45 $31,482.50 $0.01 $60.00 $94.50 $141,750.00 $0.50 $5,000.00 $8.50 $1,020.00 $250.00 $1,250.00 $550.00 $5,500.00 $60.00 $600.00 $1,850.00 $1,850.00 | $2.90 $37,265.00 $0.01 $60.00 $85.50 $128,250.00 $0.80 $8,000.00 $5.15 $618.00 $285.00 $1,425.00 $395.00 $3,950.00 $0.01 $0.10 $2,250.00 $2,250.00 | ||||||
| 2 Bituminous Materials (Prime Coat) | 6,000 LBS | $0.01 | ||||||||||
| 3 HMA Surface Course, Mix D, N50. (2.0") 4 Striping (Paint), 4" Yellow 5 Striping (Paint), Letters and Symbols Yellow 6 Water Valve Box Adjustment 7 MH Frame Adjustments 8 Inlet Protection 9 Traffic Control and Protection | 1,500 TON 10,000 FT. 120 S.F. 5 Each 10 Each 10 Each 1 L.S. |
VILLAGE OF PARK FOREST TABULATION OF BIDS N.D.T. PARKING LOT RESURFACING
Engineers Estimate Advantage Paving K Five Gallagher Dale, Inc.
ENGINEER'S
ITEM DESCRIPTION ESTIMATED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED
NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
1 HMA Surface Removal-Milling (2.0") 12,850 S.Y. $3.50 $44,975.00 $1.95 $25,057.50 $4.05 $52,042.50 $2.85 $36,622.50 $11.50 $147,775.00
2 Bituminous Materials (Tack Coat) 6,000 LBS $0.10 $600.00 $0.01 $60.00 $0.01 $60.00 $0.01 $60.00 $1.50 $9,000.00
3 HMA Surface Course,
Mix D, N50. (2.0") 1,500 TON $90.00 $135,000.00 $102.85 $154,275.00 $87.00 $130,500.00 $84.50 $126,750.00 $110.00 $165,000.00
4 Striping (Paint), 4" Yellow 10,000 FT. $0.50 $5,000.00 $0.90 $9,000.00 $0.70 $7,000.00 $0.75 $7,500.00 $0.50 $5,000.00
5 Striping (Paint), Letters and Symbols Yellow 120 S.F. $10.00 $1,200.00 $24.25 $2,910.00 $8.10 $972.00 $2.15 $258.00 $9.00 $1,080.00
6 Water Valve Box Adjustment 5 Each $500.00 $2,500.00 $56.00 $280.00 $685.00 $3,425.00 $195.00 $975.00 $750.00 $3,750.00
7 MH Frame Adjustments 10 Each $500.00 $5,000.00 $40.00 $400.00 $1,350.00 $13,500.00 $300.00 $3,000.00 $750.00 $7,500.00
8 Inlet Protection 10 Each $100.00 $1,000.00 $0.01 $0.10 $250.00 $2,500.00 $45.00 $450.00 $495.00 $4,950.00
9 Traffic Control and Protection 1 L.S. $2,000.00 $2,000.00 $17.40 $17.40 $6,000.00 $6,000.00 $9,250.00 $9,250.00 $2,500.00 $2,500.00
TOTAL $ $197,275.00 TOTAL $ $192,000.00 TOTAL $ $215,999.50 TOTAL $ $184,865.50 TOTAL $ $346,555.00
M/ J Asphalt Everlast Blacktop "D" Construction McGill Construction Iroquois Paving
ENGINEER'S
ITEM DESCRIPTION ESTIMATED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED
NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
1 HMA Surface Removal-Milling (2.0") 12,850 S.Y. $2.35 $30,197.50 $2.69 $34,566.50 $2.10 $26,985.00 $2.45 $31,482.50 $2.90 $37,265.00
2 Bituminous Materials (Prime Coat) 6,000 LBS $0.01 $60.00 $0.55 $3,300.00 $0.01 $60.00 $0.01 $60.00 $0.01 $60.00
3 HMA Surface Course,
Mix D, N50. (2.0") 1,500 TON $96.00 $144,000.00 $106.37 $159,555.00 $88.00 $132,000.00 $94.50 $141,750.00 $85.50 $128,250.00
4 Striping (Paint), 4" Yellow 10,000 FT. $0.35 $3,500.00 $0.80 $8,000.00 $1.28 $12,800.00 $0.50 $5,000.00 $0.80 $8,000.00
5 Striping (Paint), Letters and Symbols Yellow 120 S.F. $13.00 $1,560.00 $9.20 $1,104.00 $50.60 $6,072.00 $8.50 $1,020.00 $5.15 $618.00
6 Water Valve Box Adjustment 5 Each $380.00 $1,900.00 $519.54 $2,597.70 $300.00 $1,500.00 $250.00 $1,250.00 $285.00 $1,425.00
7 MH Frame Adjustments 10 Each $750.00 $7,500.00 $491.50 $4,915.00 $900.00 $9,000.00 $550.00 $5,500.00 $395.00 $3,950.00
8 Inlet Protection 10 Each $150.00 $1,500.00 $125.00 $1,250.00 $200.00 $2,000.00 $60.00 $600.00 $0.01 $0.10
9 Traffic Control and Protection 1 L.S. $4,350.00 $4,350.00 $5,000.23 $5,000.23 $4,700.00 $4,700.00 $1,850.00 $1,850.00 $2,250.00 $2,250.00
TOTAL $ $194,567.50 TOTAL $ $220,288.43 TOTAL $ $195,117.00 TOTAL $ $188,512.50 TOTAL $ $181,818.10
2
| Murphy Construction | Maneval Construction | |||||
|---|---|---|---|---|---|---|
| ITEM NO. | DESCRIPTION | ENGINEER'S ESTIMATED QUANTITY | UNIT PRICE | EXTENDED AMOUNT | UNIT PRICE | EXTENDED AMOUNT |
| 1 HMA Surface Removal-Milling (2.0") | 12,850 S.Y. | $2.70 $34,695.00 $0.01 $60.00 $96.50 $144,750.00 $0.32 $3,200.00 $5.00 $600.00 $900.00 $4,500.00 $1,200.00 $12,000.00 $200.00 $2,000.00 $1,600.00 $1,600.00 | $1.00 $12,850.00 $0.01 $60.00 $110.00 $165,000.00 $0.57 $5,700.00 $5.25 $630.00 $1.00 $5.00 $1.00 $10.00 $1.00 $10.00 $1.00 $1.00 | |||
| 2 Bituminous Materials (Prime Coat) | 6,000 LBS | $0.01 | ||||
| 3 HMA Surface Course, Mix D, N50. (2.0") 4 Striping (Paint), 4" Yellow 5 Striping (Paint), Letters and Symbols Yellow 6 Water Valve Box Adjustment 7 MH Frame Adjustments 8 Inlet Protection 9 Traffic Control and Protection | 1,500 TON 10,000 FT. 120 S.F. 5 Each 10 Each 10 Each 1 L.S. |
VILLAGE OF PARK FOREST TABULATION OF BIDS N.D.T. PARKING LOT RESURFACING
Murphy Construction Maneval Construction
ENGINEER'S
ITEM DESCRIPTION ESTIMATED UNIT EXTENDED UNIT EXTENDED
NO. QUANTITY PRICE AMOUNT PRICE AMOUNT
1 HMA Surface Removal-Milling (2.0") 12,850 S.Y. $2.70 $34,695.00 $1.00 $12,850.00
2 Bituminous Materials (Prime Coat) 6,000 LBS $0.01 $60.00 $0.01 $60.00
3 HMA Surface Course,
Mix D, N50. (2.0") 1,500 TON $96.50 $144,750.00 $110.00 $165,000.00
4 Striping (Paint), 4" Yellow 10,000 FT. $0.32 $3,200.00 $0.57 $5,700.00
5 Striping (Paint), Letters and Symbols Yellow 120 S.F. $5.00 $600.00 $5.25 $630.00
6 Water Valve Box Adjustment 5 Each $900.00 $4,500.00 $1.00 $5.00
7 MH Frame Adjustments 10 Each $1,200.00 $12,000.00 $1.00 $10.00
8 Inlet Protection 10 Each $200.00 $2,000.00 $1.00 $10.00
9 Traffic Control and Protection 1 L.S. $1,600.00 $1,600.00 $1.00 $1.00
TOTAL $ $203,405.00 TOTAL $ $184,266.00
2

With GovernmentContracts, you can:
Follow 88TH RD US ARMY RESERVE CENTER ARLINGTON HEIGHTS, IL WATER INFRASTRUCTURE IMPROVEMENTS-
DEPT OF DEFENSE
Bid Due: 9/16/2026
DEPARTMENT OF WATER MANAGEMENT Construction 76305 1334862 1334862: Block Level Lead Service Line
City of Chicago
Bid Due: 10/01/2026
Project: C26FI103384111 - Request for Proposals (RFP) for Construction Services for the Red
Chicago Transit Authority
Bid Due: 10/07/2026
Project: Mechanical Engineering Design Services Ref. #: 214619 Department: Purchasing Type: Other Status:
Metra Rail
Bid Due: 9/25/2026