| Location: | Wyoming |
|---|---|
| Posted: | Oct 21, 2025 |
| Due: | Nov 4, 2025 |
| Agency: | TRANSPORTATION, DEPARTMENT OF |
| Type of Government: | Federal |
| Category: |
|
| Solicitation No: | 6982AF25B000010 |
| Publication URL: | To access bid details, please log in. |
APEX Accelerators are an official government contracting resource for small businesses. Find your local APEX Accelerator (opens in new window) for free government expertise related to contract opportunities.
APEX Accelerators are funded in part through a cooperative agreement with the Department of Defense.
The APEX Accelerators program was formerly known as the Procurement Technical Assistance Program (opens in new window) (PTAP).
THIS IS NOT AN INVITATION FOR BID, PLAN AND SPECIFICATIONS ARE NOT AVAILABLE
Offerors or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
PROJECT NUMBER: WY FLAP SHE 26(1)
PROJECT NAME: Red Grade Road
PROJECT DESCRIPTION: The purpose of this project is to improve access to the Bighorn National Forest and BLM lands through roadway rehabilitation, widening, and minor roadway realignment of Red Grade Road (County Road 26/USFS Route FSR 26). Red Grade Road provides a travel corridor from Wyoming State Highway 335 to Highway US 14. The project will address the substandard roadway typical section, geometrics, and safety issues.
SCOPE OF THE WORK: This total project length is approximately 2.6 miles. The plans include two schedules and one option:
The proposed roadway will vary from 22-foot wide (two 10-foot lanes and 1-foot shoulders) to 18-foot total where geometry does not allow widening. The existing roadway width is 18 feet wide. The project will include minor horizontal and vertical realignments to improve sight distance and roadway geometry, as well as drainage improvements to obtain a design standard for the proposed roadway. The project is considered 3R+ and located in mountainous terrain.
PRINCIPAL WORK ITEMS:
Line Item Unit Estimated Quantity
Clearing and grubbing ACRE 33.80
Roadway excavation CUYD 29,000
Placed rip rap, method A, Class 1 CUYD 2,150
Special rock embankment CUYD 1,500
Rock buttress CUYD 1,210
Rockery SQFT 6,520
Roadway aggregate, method 2 TONS 7,700
Concrete headwalls EACH 18
12-Inch Pipe culvert LNFT 125
18-Inch Pipe culvert LNFT 45
24-Inch Pipe culvert LNFT 800
36-Inch Pipe culvert LNFT 100
Placing conserved topsoil ACRE 13.0
Temporary traffic control, flagger HOUR 10,300
ANTICIPATED SCHEDULE: It is anticipated construction will begin May 2026 and end November 2027 with a winter shutdown.
The work will be performed at high altitude (approximately 7,000 to 8,000 feet above sea level). Red Grade Road is closed to vehicles generally November through May because of snow. The road remains opened to tracked vehicles during this winter shutdown.
The contractor will be allowed to close the road to public traffic on weekdays from 8 am to 12 pm and from 1 pm to 6 pm during construction.
ESTIMATED COST RANGE: The estimated cost is $10,000,000 to $20,000,000.
| Oct 30, 2025 | [Presolicitation (Updated)] WY FLAP SHE 26(1), Red Grade Road, Phase 1 |
| Nov 6, 2025 | [Presolicitation (Updated)] WY FLAP SHE 26(1), Red Grade Road, Phase 1 |
| Nov 17, 2025 | [Presolicitation (Updated)] WY FLAP SHE 26(1), Red Grade Road, Phase 1 |
| Nov 18, 2025 | [Presolicitation (Updated)] WY FLAP SHE 26(1), Red Grade Road, Phase 1 |
| Nov 25, 2025 | [Presolicitation (Updated)] WY FLAP SHE 26(1), Red Grade Road, Phase 1 |
| Dec 17, 2025 | [Presolicitation (Updated)] WY FLAP SHE 26(1), Red Grade Road, Phase 1 |
| Jan 21, 2026 | [Solicitation (Original)] WY FLAP SHE 26(1), Red Grade Road, Phase 1 |
| Feb 1, 2026 | [Solicitation (Updated)] WY FLAP SHE 26(1), Red Grade Road, Phase 1 |
| Feb 12, 2026 | [Solicitation (Updated)] WY FLAP SHE 26(1), Red Grade Road, Phase 1 |
| Feb 18, 2026 | [Solicitation (Updated)] WY FLAP SHE 26(1), Red Grade Road, Phase 1 |
| Feb 21, 2026 | [Solicitation (Updated)] WY FLAP SHE 26(1), Red Grade Road, Phase 1 |
| Feb 24, 2026 | [Solicitation (Updated)] WY FLAP SHE 26(1), Red Grade Road, Phase 1 |

With GovernmentContracts, you can:
...Detention Erosion Mitigation project will include removal and resetting of rip-rap, excavation, and ...
City of Cheyenne
Bid Due: 6/10/2026
...The Christensen Road Detention Erosion Mitigation project will include removal and resetting of ...
City of Cheyenne
Bid Due: 6/04/2026
...The Christensen Road Detention Erosion Mitigation project will include removal and resetting of ...
City of Cheyenne
Bid Due: 6/04/2026
...Detention Erosion Mitigation project will include removal and resetting of rip-rap, excavation, and ...
City of Cheyenne
Bid Due: 6/10/2026