COUNTY OF MONROE
REQUEST FOR PROPOSALS
PROJECT TITLE:
MODERNIZATION OF ELEVATOR CABS AND MECHANICAL
SYSTEMS
ISSUED TO CONTRACTORS: FRIDAY, JANUARY 30, 2026
PROPOSALS DUE: FRIDAY, MARCH 6, 2026 @ 4:00 P. M.
Table of Contents
Table of Contents……………………………………………..…………………..1
Introduction…………….…….………………………………..………………….2
Project Description and Schedule …….………………..………………...………3
Future Elevator Maintenance Proposal………………………………………..….4
Elevator Serial #7351.…………………………………………………...………..5
Elevator Serial #10624 ……………………...…...…….……………...………….7
Elevator Serial #6545………………………….…………………………..……...9
Two (2) Elevators Serial #19633 and #19634…………..………………….……12
General Information/Requirements……………………………….……………..15
End of RFP………………………………………………………………………20
1|Page
MONROE COUNTY
FINANCEDEPARTMENT
125 East Second Street ⋅ Monroe, Michigan 48161-2197
Telephone: (734) 240-7250 ⋅ Fax (734) 240-7266
January 30, 2026
Dear Elevator Contractor:
The County of Monroe is requesting your response to this request for proposals for the upgrade
and modernization of five (5) elevators in County buildings.
The elevators with select information and their locations are as follows:
Elevator
Serial #
7351
10624
6545
19633
19634
Make
Haughton
Haughton-Dover
Otis
Dover-Schindler
Dover-Schindler
Location
Building Type
106 East First Street, Monroe, MI 48161
106 East First Street, Monroe, MI 48161
29 Washington Street, Monroe, MI 48161
100 East Second Street, Monroe, MI 4861
100 East Second Street, Monroe, MI 4861
Courthouse
Courthouse
Office Bldg.
Jail
Jail
The contractor’s proposal shall include all costs for equipment, labor, materials, transportation,
shipping, rigging, temporary barricading, safety devices and equipment and supervision to
effectively and efficiently manage the project(s). All equipment supplied shall be new and
factory or manufacturer authorized to be installed on the elevator system(s). Each elevator
upgrade shall include telemetry equipment to allow remote notification and diagnosis by a
qualified elevator maintenance company. The communication equipment shall be open
architecture to allow for other companies to utilize the base telemetry equipment while
connecting with their company specific software.
A list of project requirements and supplement project information are provided in the following
pages as part of this Request for Proposal. Please review the project requirements and schedule
a field visit to each site to review the elevators, the equipment rooms, site conditions and all
field conditions and all dimensions prior to submitting a proposal.
Proposal Response Format: Each proposal shall describe the work and equipment proposed
for each elevator. A proposal of not more than three (3) pages describing your work and the
equipment to be installed for each elevator shall be submitted. Each elevator proposals must
address the County’s Scope of Work outlined in the proposal beginning on page 4 and confirm
your proposal meets or exceeds what is outlined. Overall, your proposal shall be limited to not
more than 20 pages and shall include product cut sheets showing your proposed elevator cab
2|Page
front, the interiors and major equipment. Pages shall be not smaller than 12 font and 1-inch
margins.
BRIEF PROJECT DESCRIPTION:
Work being performed will consist of ensuring code compliance and meeting all safety
requirements of the Bureau of Construction Codes (BCC), which is part of the Michigan
Department of Licensing and Regulatory Affairs (LARA). The selected contractor shall be
responsible for securing all necessary permits prior to performing any work on the elevator
systems. Any follow-up inspections and operating permits or certificates needed after the
upgrades are complete will be the responsibility of the contractor.
All five (5) of the elevators are traction operated.
The contractor’s proposal shall describe the work that will be performed by others and the cost
for this work shall be broken out and shown but then included in the overall project cost
proposal. The selected contractor shall be responsible for managing and coordinating the work
of any other sub-contractors and the sub-contractor’s scope of work.
For each elevator or banks of elevators, we outline the Scope of Work to be performed
generally and contractors shall supply details of the work they propose. Each elevator or banks
of elevators have a separate Scope of Work. Proposals shall mirror this Scope of Work and
describe the details of the work for each elevator or banks of elevators. We include photos of
the machine room and existing equipment.
SCHEDULE:
Project Released for Bidding
Contractor Site Inspections
Bids Due
Bid Review/Analysis
Owner Awards Project
January 30, 2026
February 2-February 27, 2026
March 6, 2026 at 4:00 pm
March 9-March 13, 2026
March 16, 2026
To schedule a site inspection of the elevators, the equipment rooms and overall site conditions
where the work will be performed, contact:
Tony Gabriel, Maintenance Coordinator
Telephone: 734-240-7267-Desk
Telephone: 734-430-6437-Cellular
Email: tony_gabriel@monroemi.org
Or
Andrew Kish, Operations Coordinator
Email: andrew_kish@monroemi.org
The work is to be coordinated with the County as to schedule, staging/storing of equipment,
machinery, materials and access to the sites. Advance notice to the County of the work is
required.
3|Page
Any questions concerning the project, the project requirements, your proposal, etc., shall be
directed jointly to the following individuals via email as follows:
Michael Bosanac, Administrator/Chief Financial Officer
Email: michael_bosanac@monroemi.org
Andrew Kish, Operations Coordinator
Email: andrew_kish@monroemi.org
Either one of these individuals will promptly reply to any inquiry or direct your inquiry to
another individual who will reply.
The final date for submitting a proposal for this project is Friday, March 6, 2026 at 4:00 P.M.
Proposals may be submitted in one of two (2) methods:
1. Hard Paper Copy: Mail, courier delivery service or personal delivery to Monroe
County Finance Department, 2nd Floor, 125 East Second Street, Monroe, Michigan
48161-2197. Your envelope must be sealed and clearly marked “Elevator Proposal” so
that no error in opening may occur.
2. Electronic Email: Submit proposals by the same deadline via e-mail as a separate
Microsoft Word or PDF document attachment to rfp@monroemi.org. Indicate in the
email subject line, a Sealed Proposal is attached for “Elevator Proposal”.
The County is prepared to commence the work as soon as a contract is awarded and a mutually
agreeable schedule for the work is developed.
Future Elevator Maintenance Proposal:
In addition to the capital upgrade of the elevators and equipment outlined in this RFP, each
contractor shall offer a maintenance agreement to cover the full-service maintenance of the
elevators being upgraded. Include a proposed maintenance agreement that covers each elevator
and price your agreement for each of the next three (3) years following the conclusion of the
warranty period after the County accepts the work performed for the upgrades.
The County of Monroe reserves the right to accept or to reject any and all proposals, to waive
any irregularities and to make an award that is determined by the County of Monroe to be in the
best interest of the County.
Sincerely,
Michael G. Bosanac
Administrator/Chief Financial Officer
4|Page
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.