Seminole Road MSW Landfill 2026 Gas Collection and Control System (GCCS) Expansion

Location: Georgia
Posted: Jan 12, 2026
Due: Feb 20, 2026
Agency: DeKalb County
Type of Government: State & Local
Category:
  • 66 - Instruments and Laboratory Equipment
Publication URL: To access bid details, please log in.


Project ID:

Title: Seminole Road MSW Landfill 2026 Gas Collection and Control System (GCCS) Expansion

Addenda: 0

Release Date: 1/12/2026

Due Date: 2/20/2026

Follow
Seminole Road MSW Landfill 2026 Gas Collection and Control System (GCCS) Expansion
Invitation To Bid
Purchasing and Contracting
91221 , 91238 , 96261 , 96296 , 98846
Project ID: 2025-167-ITB
Release Date: Monday, January 12, 2026
ยท Due Date: Friday, February 20, 2026 3:00pm
Posted Monday, January 12, 2026 12:00am
All dates & times in Eastern Time
Draft Response Events RSVP No Bid38 days, 17 hours, 57 minutes


Post Information

Posted At:Mon, Jan 12, 2026 12:00 AM
Sealed Bid Process:Yes (Bids Sealed / Pricing Sealed)
Private Bid:No
Overview


Summary

The County of DeKalb, GA (the "County"), is soliciting sealed Bids for Seminole Road MSW Landfill 2026 Gas Collection and Control System (GCCS) Expansion . Bids are to be submitted via the County's eProcurement Portal via https://procurement.opengov.com/portal/dekalbcountyga PRIOR TO 3:00 pm on Friday, February 20, 2026 . Late Bids will not be accepted.

The project work to be performed by the Contractor consists of furnishing all labor, materials, equipment, tools, transportation, services, incidentals, and
performing all work necessary to complete the project, in place and ready for service in accordance with the plans and specifications prepared therefor and generally includes but is not limited to the following items:


1. Construction staking/system layout/surveying prior to construction.
2. Installing below grade Polyvinyl Chloride (PVC) and High-Density Polyethylene (HDPE) landfill gas (LFG) extraction wells.
3. Installing below grade HDPE horizontal collectors and rock targets on existing and proposed horizontal collectors
4. Installing below grade HDPE LFG laterals and header, air supply line, and liquid conveyance line.
5. Installing gas wellheads, including fittings, valves, tubing, hoses, clamps, regulators and filters, and related appurtenances.
6. Installing new pumps, including tubing, clamps, and related appurtenances.
7. Installing new litter fence and repairing existing litter fence.
8. Installing stationary and portable odor control system.
9. LFG well abandonments.
10. Connection of the Gas Collection and Control System (GCCS) Expansion to the existing GCCS.
11. System start-up and testing
12. Conformance surveying
13. Providing as-built documentation (record drawings)



Timeline

Advertisement Date:
January 12, 2026
Mandatory DeKalb LSBE Meeting (Bidders must attend 1 meeting on either of the dates listed in person or via video conference.): (Mandatory):
January 14, 2026, January 21, 2026 or January 28, 2026
For attendance instructions utilize the following link: www.dekalbcountyga.gov/purchasing-contracting/general-information
(Meetings are held at 10:00 a.m. and 2:00 p.m.)
Pre-Bid Meeting and Site Visit (Non-Mandatory):
January 27, 2026, 10:00am
Renewable Fuels Facility
Seminole Road Landfill
4203 Clevemont Rd,
Ellenwood, GA 30294
Question Submission Deadline:
January 30, 2026, 5:00pm
Response Submission Deadline:
February 20, 2026, 3:00pm
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL
* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.