J056--BSL3 HVAC Controls Replacement - Sol
Active
Contract Opportunity
Department/Ind. Agency
VETERANS AFFAIRS, DEPARTMENT OF
Sub-tier
VETERANS AFFAIRS, DEPARTMENT OF
Office
257-NETWORK CONTRACT OFFICE 17 (36C257)
Looking for contract opportunity help?
General Information View Changes
-
Contract Opportunity Type: Solicitation (Updated)
-
All Dates/Times are: (UTC-05:00) CENTRAL STANDARD TIME, CHICAGO, USA
-
Updated Published Date: Apr 10, 2024 03:45 pm CDT
-
Original Published Date: Mar 21, 2024 11:23 am CDT
-
Updated Date Offers Due: Apr 16, 2024 01:00 pm CDT
-
Original Date Offers Due: Apr 16, 2024 01:00 pm CDT
-
Inactive Policy: Manual
-
Updated Inactive Date: May 16, 2024
-
Original Inactive Date:
Apr 26, 2024
-
Initiative:
Classification
-
Original Set Aside:
-
-
Product Service Code: J056 - MAINT/REPAIR/REBUILD OF EQUIPMENT- CONSTRUCTION AND BUILDING MATERIALS
-
NAICS Code:
-
238220 - Plumbing, Heating, and Air-Conditioning Contractors
-
Place of Performance:
Description View Changes
RFI RESPOSPONSES
Are we to dispose/abate of any asbestos, lead, mold or other hazardous material as part of this project? If so, provide appropriate hazardous material site survey report.
No
What will the ICRA level be for this project? What is the extent of the required ICRA barriers
Level 4 Critical 3 months
Are there any required/proprietary subcontractors the general contractor is to hire associated with this project?
No
Will all work associated with this project able to be performed during regular working hours?
Yes
It is our understanding that the Solicitation is a negotiated Bid (RFP) design-bid-build project with the Government's AE being responsible for the design portion (providing a full and complete set of Specifications and Plans) and the successful offeror being responsible for bidding and building the project based on the Specifications and Plans provided by the Government's AE. Put another way, the successful offeror will not be required to perform any design-build services as part of the contract - correct?Â
Yes
Could you please provide plumbing and electrical as well as supply room floor plans.
Yes
Will VA protect material to remain behind?
No
Will plans be provided for this project?
Yes
May a controller different than the model specified (but equal) be provided?
Check with Entech
Does testing need to be performed by a third party?
Yes, ENV Services for certification
We understand the work to include air handler controls and not the installation of a new HVAC unit.
Yes
Please confirm the project does not require containment and that the outer doors will act as the containment.
The project will require floor mats and a 6mill plastic barrier over the main door.
Confirm the project does not require temporary ducted negative air to the outside of the building.
Current condition is a negative air. The project doesn t need additional negative air.
Statement of work paragraph 2.b indicates pressure monitors shall be installed and cabled to pick up the analog signal for pressure reading of the monitored space.
This statement is part of the requirement.
Are new pressure monitors required or are we to use the existing pressure monitors?
Supply new pressure monitors and plan on replacing them. For this bid assume they will need to be replaced.
How many pressure monitors are there?
3
Will sheetrock need to be removed and patched for the cabling to the pressure monitors?
No. the contractor can use the same opening and J-box the existing pressure monitors uses.
Should statement of work paragraph 2.e read Contractor shall move AH 1-1 and AH 1-2 points over to the existing controller previously used by AH1.3 and AH1-4.
Yes. AH1.3 and controls is dedicated/emergency power
Statement of work paragraph 2.f states rework supply fan sequence to modulate supply fan speed control to insure all four spaces remain negative and neutral as they should. Â Â Â Please provide by amendment a designed sequence of operations that contractors can implement and test.
Please see the update sequence of operation
Reference SOW paragraph 2.g. Confirm a new VFD is not required.
A new VFD is not required
Paragraph 2.i indicates the contractor shall certify BSL-3 lab in accordance with BMBL 6th edition. This document seems to refer to certification of the bio-safety cabinets which we understand is not in the scope of this project. Please clarify what is required for the certification of the BSL-3 lab.
We need to certify the room as a whole. The BMBL 6th edition has requirements for a BSL-3 lab.
Can the VA provide names and poc information for the 3rd party companies who have certified BSL labs in the past?
ENV Services
SOW paragraph 2.j.i.I indicates replacement of ceiling due to mold . The requirement does not indicate to abate mold. At the site visit, we saw that the ceiling was damaged, but we did not notice any mold. If any mold abatement is required, please clarify by amendment including quantities to be abated so that these costs can be included in contractor proposals.
The VA would like to have the entire ceiling replace because there could be mold. Mold was not confirmed to be present, but because the ceiling gotten wet, we require the contractor to replace the ceiling.
If any hazardous materials abatement is required, please clarify by amendment and provide an abatement specification.
No abatement is required.
SOW paragraph 2.j.III calls to replace insulation around windows to alleviate condensation. How wide should the gypsum board and insulation be removed/replaced from each side of the windows?
Please use 5/8 type X gypsum wall board.
SOW paragraph 2.j.IV requires Enclosing of window to prevent condensation.  The exterior walls have outer windows and inner windows with a substantial gap between them. At the site visit, the VA indicated this scope requires the removal of the inner windows which would then be replaced with insulation and gypsum board walls. Please clarify by amendment if this is the requirement.
Use Rock wool insulation and 5/8 type X wall board for window in enclosure. The contractor will need to frame out window open will metal stubs. The wall should be installed next to the existing exterior window.
Confirm the project does not require temporary ducted negative air to the outside of the building.
The project will need to have negative air however the site already has exhaust ducted to fans outside.
Statement of work paragraph 2.b indicates pressure monitors shall be installed and cabled to pick up the analog signal for pressure reading of the monitored space.
Please see the response to questions 14 and question 15
Are new pressure monitors required or are we to use the existing pressure monitors?
Please see the response to questions 14 and question 15
How many pressure monitors are there?
3
Will sheetrock need to be removed and patched for the cabling to the pressure monitors?
No. the contractor can use the same opening and J-box the existing pressure monitors uses.
Should statement of work paragraph 2.e read Contractor shall move AH 1-1 and AH 1-2 points over to the existing controller previously used by AH1.3 and AH1-4.
Yes. AH1.3 and controls are dedicated/emergency power
Statement of work paragraph 2.f states rework supply fan sequence to modulate supply fan speed control to insure all four spaces remain negative and neutral as they should. Please provide by amendment a designed sequence of operations that contractors can implement and test.
This is part of the requirements
Reference SOW paragraph 2.g. Confirm a new VFD is not required.
Not required. Existing
Paragraph 2.i indicates the contractor shall certify BSL-3 lab in accordance with BMBL 6th edition. This document seems to refer to certification of the bio-safety cabinets which we understand is not in the scope of this project. Please clarify what is required for the certification of the BSL-3 lab.
We need to certify the room as a whole. The BMBL 6th edition has requirements for a BSL-3 lab.
Can the VA provide names and poc information for the 3rd party companies who have certified BSL labs in the past?
ENV Services
SOW paragraph 2.j.i.I indicates replacement of ceiling due to mold . The requirement does not indicate to abate mold. At the site visit, we saw that the ceiling was damaged, but we did not notice any mold. If any mold abatement is required, please clarify by amendment including quantities to be abated so that these costs can be included in contractor proposals.
The VA would like to have the entire ceiling replace because there could be mold. Mold was not confirmed to be present, but because the ceiling gotten wet, we require the contractor to replace the ceiling.
If any hazardous materials abatement is required, please clarify by amendment and provide an abatement specification.
No abetment is required.
SOW paragraph 2.j.III calls to replace insulation around windows to alleviate condensation. How wide should the gypsum board and insulation be removed/replaced from each side of the windows?
Use Rock wool insulation and 5/8 type X wall board for window in enclosure. The contractor will need to frame out window open will metal stubs. The wall should be installed next to the existing exterior window.
SOW paragraph 2.j.IV requires Enclosing of window to prevent condensation. The exterior walls have outer windows and inner windows with a substantial gap between them. At the site visit, the VA indicated this scope requires the removal of the inner windows which would then be replaced with insulation and gypsum board walls. Please clarify by amendment if this is the requirement.
Use Rock wool insulation and 5/8 type X wall board for window in enclosure. The contractor will need to frame out window open will metal stubs. The wall should be installed next to the existing exterior window.
Provide updated SOW as per the site visit findings
These questions will be use are the update information for the SOW
Provide Drawings
See Attached Drawings/Specs
Provide Specifications
See Attached Drawings/Specs
Provide pictures of interior rooms
See Attached Illustrations
Provide ceiling detail showing existing
See Attached Illustrations
Provide specifications on how to cover the interior windows
See response to question 26
Provide specification on who is to remove and relocate the electrical and data comm in the interior rooms between windows
The VA will remove the TempTrak device on the wall and the contractor will need to replace the electrical.
Provide updated bid due date required for lead time of materials
Bid due date is extended to April 29, 2024 at 1:00 PM CST
Provide mold test results for interior rooms that have water damage
Please see the response to question 23.
Provide paint specification and color / finish texture
ICI Paints white whisper gloss
Provide nearest location for electrical for roof equipment
Quick-disconnect is in the area.
Attachments/Links
Contact Information
Contracting Office Address
-
5441 Babcock Road Suite 302
-
San Antonio , TX 78240
-
USA
Secondary Point of Contact
History
Daily notification on new contract opportunities
With GovernmentContracts, you can:
- Find more opportunities and win more business
- Receive daily alerts for all new bid opportunities
- Get contract opportunities matched to your business
ONE WEEK FREE TRIAL
See also
...to be approved prior to beginning construction. As part of this solicitation, the ...
VETERANS AFFAIRS, DEPARTMENT OF
Bid Due: 5/15/2024
* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only as a convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.