Agency: | DEPT OF DEFENSE |
---|---|
State: | Federal |
Type of Government: | Federal |
Category: |
|
Posted: | Apr 22, 2024 |
Due: | Apr 29, 2024 |
Solicitation No: | N6893624Q0089 |
Publication URL: | To access bid details, please log in. |
APEX Accelerators are an official government contracting resource for small businesses. Find your local APEX Accelerator (opens in new window) for free government expertise related to contract opportunities.
APEX Accelerators are funded in part through a cooperative agreement with the Department of Defense.
The APEX Accelerators program was formerly known as the Procurement Technical Assistance Program (opens in new window) (PTAP).
The purpose of this modification is to extend the closing date to 4/29/2024 02:00 PM PST and there will be not more extensions. To provide answers to questions that were missed from the previous cut off date. This concludes all questions and answers.
Questions Answers
1. Are Scaled Drawings available, if so please post. Don’t have access to scaled drawing.
2. Are Ceilings Suspended? Or Hard Lid? Open ceiling which will require conduit
3. Are there existing Cable Trays for wiring above ceilings? No cable trays
4 .Can Existing Wiring be utilized? No
5. Is a “UPS” required? If so, What Time/Power Duration is required? No UPS required. The Identiv and Altronix has dual backup batteries.
6. Are “Or Equal” Equipment substitutions allowed? As long as the part specified functions, performs, and has the same quality.
7. Is “Plenum Wire” acceptable? Not for underground. Refer to SOW.
8. Is “After Hours Access” for said work, available to contractor at no add’l cost to the Gov’t? NO
9. What is the height of Exterior Cameras? (If any) Top of existing fence post is acceptable
10. Please provide/post other “Q & A” requests. ???????
11.Please provide a list of equipment to be installed. Refer to SOW
12 Are there pipe chases between floors? Between what floors? Single level.
13. What is the range of the budget for this project, and is it already appropriated? NA This information is not available. When requirement comes to Simplified Acquisition it is submitted for procurement for purchased.
14. Because of the high cost of the parts can we bill when parts arrive on site, or in the alternative are progress payments allowed? Payment will be Net 30 after completion of Job. (We are Simplified Acquisitions and we don’t provide progress payments)
1. How many feet of new wire will have to be run? Refer to SOW, Recommend job walk
2. What is the total count of doors and readers? As stated in the SOW- 2 each Identiv 8336ABTR000 uTrust TS ScrambleProx insert reader
Apr 11, 2024 | [Combined Synopsis/Solicitation (Original)] Install New Access Control System |
Apr 18, 2024 | [Combined Synopsis/Solicitation (Updated)] Install New Access Control System |
With GovernmentContracts, you can:
...Follow Next Generation Command and Control (NGC2) Capability Characteristics Active Contract... and services. ...
DEPT OF DEFENSE
Bid Due: 5/15/2024
...THEATER AIRCRAFT CORROSION CONTROL PREP HANGAR, KADENA AIR BASE, OKINAWA Active Contract... affects ...
Federal Agency
Bid Due: 5/30/2024
...WEAPON CENTER Sub Command 2 NUCLEAR COMMAND, CONTROL & COMMUNICATION WEAPON Office FA8221 ...
DEPT OF DEFENSE
Bid Due: 11/24/2025
...WEAPON CENTER Sub Command 2 NUCLEAR COMMAND, CONTROL & COMMUNICATION WEAPON Office FA8221 ...
DEPT OF DEFENSE
Bid Due: 10/17/2026