Bldg. 4309a Target Flip Area and 593 at Kirtland AFB

Agency: DEPT OF DEFENSE
State: New Mexico
Type of Contract: Awards
Type of Government: Federal
Category:
  • Z - Maintenance, Repair or Alteration of Real Property
Posted: Aug 22, 2023
Solicitation No: W912PP23Q0051
Publication URL: To access bid details, please log in.
Follow
Bldg. 4309a Target Flip Area and 593 at Kirtland AFB
Active
Contract Opportunity
Notice ID
W912PP23Q0051
Related Notice
Contract Line Item Number
Department/Ind. Agency
DEPT OF DEFENSE
Sub-tier
DEPT OF THE ARMY
Major Command
USACE
Sub Command
SPD
Office
W075 ENDIST ALBUQUERQUE
Award Details
  • Contract Award Date: Aug 22, 2023
  • Contract Award Number: W912PP23P0032
  • Task/Delivery Order Number:
  • Contractor Awarded Unique Entity ID: E5MNYJ7TK8R6
  • Contractor Awarded Name: ALTIMA CONSTRUCTION INC
  • Contractor Awarded Address: Albuquerque , NM 87105 USA
  • Base and All Options Value (Total Contract Value): $111,536.52
General Information
  • Contract Opportunity Type: Award Notice (Original)
  • All Dates/Times are: (UTC-04:00) EASTERN STANDARD TIME, NEW YORK, USA
  • Original Published Date: Aug 22, 2023 06:23 pm EDT
  • Inactive Policy: 15 days after contract award date
  • Original Inactive Date: Sep 06, 2023
  • Initiative:
    • None
Classification
  • Original Set Aside: 8(a) Sole Source (FAR 19.8)
  • Product Service Code: Z1AA - MAINTENANCE OF OFFICE BUILDINGS
  • NAICS Code:
    • 236220 - Commercial and Institutional Building Construction
  • Place of Performance:
    Kirtland AFB , NM 87117
    USA
Description

This action was awarded as an 8(a) Sole Source Set-Aside under the authority of section 8(a) of the Small Business Act.





The contractor shall furnish all parts, material, labor, equipment and supervision necessary to complete the work for Building 430A Repair Target Prep Area and Building 593.




  1. Demolition

    1. Contractor must remove existing flooring and wall base in its entirety.

    2. Contractor must demolish indicated portion of wall and prep for installation of door frame.

    3. Contractor must remove existing door.

    4. Contractor must remove existing lighting in its entirety.

    5. Contractor must remove and salvage data drop.

    6. Contractor must remove existing emergency lights and wire mold in their entirety.

    7. Contractor must remove light switch and cover plate. Contractor must reuse circuit.

    8. Existing HVAC supply and return diffusers to remain. Contractor to clean and comfort balance.

    9. Contractor must remove existing light switch and circuit in their entirety. Replace with blank cover plate to match existing.

    10. Contractor must remove and salvage indicated wall mounted data jacks in Room 2 in B593. Patch and paint to match existing wall.

    11. Contractor must remove and salvage indicated wall mounted phone jacks in Room 2 in B593. Patch and paint to match existing wall.








  1. Construction

    1. Contractor must provide and install new rubber flooring (FL-1) and wall base (RB-1).

    2. Contractor must provide and install carpet tiles (FL-2) and wall base (RB-1).

    3. Contractor must construct new 3-5/8" 20-gauge metal stud wall with 3" sound insulation and one-layer pf 5/8" gyp. board on each side. Tape, float, texture and paint to match existing adjacent walls, install rubber wall base (RB-1). Refer to material schedule on sheet A-201. Construct wall to ceiling, as indicated on drawings.

    4. Contractor must install salvaged data drop and conduit.

    5. Contractor must patch and paint walls to match existing, as indicated on drawings.

    6. Contractor must provide and install new doors, frames, and associated hardware, refer to door schedule on sheet A-201, as indicated on drawings.

    7. Contractor must provide and install new light switch with cover plate to match existing. Tie into existing circuit.

    8. Contractor must provide and install nine (9) new surface- mounted lights (L-1). Refer to lighting schedule on sheet A-201.

    9. Contractor must provide and install new light switch with cover plate to match existing. Contractor must run and tie into new circuit, as indicated on drawings.

    10. Contractor must provide and install new emergency light (L-2). Refer to lighting schedule on sheet A-201, as indicated on drawings.

    11. Contractor must provide and install new emergency exit lights (L-3). Refer to lighting schedule on sheet A-201, as indicated on drawings.

    12. Contractor must patch and paint ceiling to match existing walls, as indicated on drawings.

    13. Contractor must provide and install new workbenches and shelves, as indicated on drawings.

    14. Contractor must install one (1) new surface mounted drop for NIPR, cable to be cat 6 green. Terminate per comm notes on sheet G-000, as indicated on drawings.

    15. Contractor must replace door and associated hardware with new door with tempered glass and closer, refer to elevation 3 on drawings for B593.

    16. Contractor must install new trilogy cipher lock and associated hardware on new door in B593.

    17. Contractor to install salvaged wall mounted data jacks and conduit on indicated wall in Room 2 in B593. Contractor to hook up data to new furniture (NIC).

    18. Contractor must install salvaged wall mounted phone jacks and conduit on indicated wall in Room 2 in B593. Contractor to hook up phone ports to new furniture (NIC).

    19. Contractor to connect new furniture to indicated power in Room 2 in B593.




Attachments/Links
No attachments or links have been added to this opportunity.
Contact Information
Contracting Office Address
  • KO CONTRACTING DIVISION 4101 JEFFERSON PLAZA NE
  • ALBUQUERQUE , NM 87109-3435
  • USA
Primary Point of Contact
Secondary Point of Contact


History
  • Aug 22, 2023 06:23 pm EDTAward Notice (Original)
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL
* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only as a convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.