Gourmet and Railroad Alleys Improvement Project

Agency: City of Gilroy
State: California
Type of Government: State & Local
Category:
  • Y - Construction of Structures and Facilities
Posted: Oct 27, 2023
Due: Nov 1, 2023
Solicitation No: 24-PW-287
Publication URL: To access bid details, please log in.
Bid Number: 24-PW-287
Bid Title: Gourmet and Railroad Alleys Improvement Project
Category: Bids
Status: Open

Description:

**UPDATED October 26, 2023 per Addendum #2**

See Addendum #2 for additional modifications.

**UPDATED October 20, 2023 per Addendum #1**

Notice is hereby given that SEALED BIDS will be received by the Purchasing Coordinator in person at the City of Gilroy Council Chambers, 7351 Rosanna Street, Gilroy, CA 95020, from 1:30 PM to 2:00 PM, Wednesday, November 1, 2023, for the Gourmet and Railroad Alleys Improvement Project No. 24-PW-287. Bids will be publicly opened and read at 2:00 PM.

All references to the October 25, 2023 bid opening date in the original bid documents shall be changed to November 1, 2023. See Addendum #1 for additional modifications.

The work includes the furnishing of all labor, materials, and equipment necessary to install

asphalt concrete pavement, pavement slurry seal, lighting, trash enclosures, trash

receptacles, drought-resistant trees, benches, signage, pavement striping, stormwater

management, and other incidentals thereto, in Gourmet Alley between Fourth and

Seventh Streets and in Railroad Alley between Lewis and Seventh Streets in the City of

Gilroy, as indicated in these Plans and Specifications.

This project is funded by the California Department of Transportation Clean California

Grant Program. Per the terms of the grant agreement, all contract work shall be completed

by June 30, 2024. The Contractor’s final invoice must be submitted to the City by July 31,

2024.

A virtual pre-bid conference will be held on Monday, October 16, 2023, at 2:00 pm. To request

a link, email Jose.Cedano@CityofGilroy.org For security reasons, you must enable JavaScript to view this E-mail address. and Jorge.Duran@CityofGilroy.org For security reasons, you must enable JavaScript to view this E-mail address. by 5:00 PM,

October 13, 2023. Attendance at the pre-bid conference is encouraged but not mandatory.

Bids received after the stated time and date will not be accepted. The City of Gilroy will

not be responsible for delayed deliveries or deliveries made to another location other than

the location specified above. Bids should be in a sealed envelope plainly marked with the

project title, project number, bidder’s name, and time and date of the bid opening. All

prospective parties shall check the City’s website for any addendums prior to the bid

opening. Bid documents can be downloaded from the City of Gilroy Website at:

https://www.cityofgilroy.org/Bids.aspx .

Bids delivered before October 25 at 2:00 PM must be delivered to the City Hall

Information Desk at the northeast entrance of City Hall. City Hall is currently open Monday

through Thursday from 8:30 AM to 4:30 PM, and Fridays by appointment only.

Publication Date/Time:
10/6/2023 12:00 AM
Closing Date/Time:
11/1/2023 2:00 PM
Related Documents:

Attachment Preview

CITY OF GILROY
PUBLIC WORKS DEPARTMENT
Gourmet and Railroad Alleys
Improvement Project
No. 24-PW-287
SECTION 00020 ............................................................................................................. 1
NOTICE TO PROSPECTIVE BIDDERS ...................................................................... 1
SECTION 00100 ............................................................................................................. 3
INSTRUCTIONS TO BIDDERS ................................................................................... 3
1.0 WORK TO BE DONE .................................................................................... 3
2.0 EXAMINATION OF CONTRACT DOCUMENTS ........................................... 3
3.0 INSPECTION OF SITE.................................................................................. 3
4.0 INTERPRETATION OF CONTRACT DOCUMENTS .................................... 4
5.0 POSTPONEMENT OF OPENING ................................................................. 4
6.0 OPENING OF BIDS ...................................................................................... 4
7.0 PREPARATION OF BID FORMS .................................................................. 5
8.0 BIDDER’S SIGNATURE AND AUTHORITY.................................................. 5
9.0 ERASURES AND CORRECTIONS............................................................... 5
10.0 BID IRREGULARITIES.................................................................................. 5
11.0 MODIFICATION OF BID ............................................................................... 6
12.0 WITHDRAWAL OF BIDS............................................................................... 6
13.0 ADDENDA ..................................................................................................... 6
14.0 BID PRICES .................................................................................................. 6
15.0 BID GUARANTY ........................................................................................... 7
16.0 QUALIFICATION OF BIDDER ...................................................................... 7
17.0 SUBCONTRACTORS ................................................................................... 7
18.0 MAJOR EQUIPMENT ITEMS........................................................................ 8
19.0 SUBSTITUTIONS DURING BIDDING........................................................... 8
20.0 BIDDERS INTERESTED IN MORE THAN ONE BID .................................... 8
21.0 SHEETING, SHORING AND BRACING........................................................ 9
22.0 WAGE RATES .............................................................................................. 9
23.0 WAGE THEFT PREVENTION....................................................................... 9
24.0 OFFER OF ASSIGNMENT OF ANTITRUST ACTIONS.............................. 10
25.0 ASSIGNMENT OF CONTRACT .................................................................. 11
26.0 REJECTION OF BIDS................................................................................. 11
27.0 CONTRACT, BONDS AND INSURANCE CERTIFICATES ........................ 11
28.0 AWARD OF CONTRACT ............................................................................ 12
29.0 EXECUTION OF CONTRACT..................................................................... 12
30.0 CONSTRUCTION DOCUMENTS ............................................................... 13
31.0 CONTRACTOR AND SUBCONTRACTOR REGISTRATION
ii
REQUIREMENTS .................................................................................................. 13
SECTION 00220 ........................................................................................................... 17
GEOTECHNICAL DATA ........................................................................................... 17
SECTION 00300 ........................................................................................................... 18
BID ............................................................................................................................ 18
SECTION 00310 ........................................................................................................... 20
BID SCHEDULE ........................................................................................................ 20
SECTION 00410 ........................................................................................................... 24
BID GUARANTY BOND ............................................................................................ 24
SECTION 00420 ........................................................................................................... 25
CERTIFICATION OF BIDDER’S EXPERIENCE AND QUALIFICATIONS ................ 25
SECTION 00425 ........................................................................................................... 27
PROPOSED BOND PROVIDER................................................................................ 27
SECTION 00430 ........................................................................................................... 28
PROPOSED SUBCONTRACTORS .......................................................................... 28
SECTION 00435 ........................................................................................................... 31
NON-COLLUSION AFFIDAVIT TO BE EXECUTED BY BIDDER AND SUBMITTED
WITH BID .................................................................................................................. 31
SECTION 00500 ........................................................................................................... 32
AGREEMENT............................................................................................................ 32
SECTION 00610 ........................................................................................................... 36
FAITHFUL PERFORMANCE BOND ......................................................................... 36
SECTION 00620 ........................................................................................................... 38
PAYMENT BOND...................................................................................................... 38
SECTION 00630 ........................................................................................................... 40
CERTIFICATE OF INSURANCE ............................................................................... 40
SECTION 00650 ........................................................................................................... 45
WORKERS’ COMPENSATION INSURANCE CERTIFICATE................................... 45
SECTION 00670 ........................................................................................................... 46
NOTICE OF NONDISCRIMINATION IN EMPLOYMENT .......................................... 46
SECTION 00700 ........................................................................................................... 47
GENERAL CONDITIONS .......................................................................................... 47
1.0 GENERAL ................................................................................................... 47
iii
1.1 Intent Of Contract Documents.......................................................................... 47
1.2 Discrepancies and Omissions .......................................................................... 47
1.3 Headings.............................................................................................................. 48
1.4 Penalty for Collusion .......................................................................................... 48
1.5 Successors and Assigns ................................................................................... 48
1.6 Assignment to City ............................................................................................. 49
1.7 Rights and Remedies ........................................................................................ 49
2.0 ADMINISTRATION...................................................................................... 49
2.1 Administration of the Contract .......................................................................... 49
2.2 City’s Representative......................................................................................... 50
2.3 Construction Manager ....................................................................................... 50
2.4 Design Consultant .............................................................................................. 52
3.0 CITY ............................................................................................................ 53
3.1 General ................................................................................................................ 53
3.2 Attention to Work ................................................................................................ 53
3.3 Inspection ............................................................................................................ 53
3.4 City’s Right to Carry Out the Work .................................................................. 54
3.5 City’s Right to Use or Occupy .......................................................................... 54
3.6 City’s Right to Perform Work and to Award Separate Contracts................ 55
4.0 CONTRACTOR ........................................................................................... 55
4.1 Office .................................................................................................................... 55
Contractor’s Representative ......................................................................................... 55
4.3 Construction Procedures................................................................................... 56
4.4 Contractor’s Employees .................................................................................... 56
4.5 Subcontractors.................................................................................................... 57
4.6 Contractor’s Equipment and Facilities ............................................................ 57
4.7 Public Safety and Convenience ....................................................................... 57
4.8 City-Contractor Coordination ............................................................................ 58
4.9 Contractor’s Responsibility for the Work and Materials ............................... 59
4.10 Laws to be Observed......................................................................................... 59
4.11 Safety ................................................................................................................... 62
4.12 Municipal License............................................................................................... 67
5.0 CONTROL OF WORK AND MATERIALS ................................................... 67
5.1 Means and Methods .......................................................................................... 67
5.2 City-Furnished Materials ................................................................................... 68
5.3 Defective and Unauthorized Work................................................................... 68
5.4 Unnoticed Defects .............................................................................................. 71
5.5 Right to Retain Imperfect Work........................................................................ 71
6.0 PROGRESS OF THE WORK ...................................................................... 71
6.1 Beginning of Work .............................................................................................. 71
6.2 Time of Completion ............................................................................................ 71
6.3 Delays .................................................................................................................. 72
6.4 Time Extensions ................................................................................................. 73
6.5 Liquidated Damages .......................................................................................... 76
6.6 Temporary Suspension of Work ...................................................................... 77
iv
6.7 Termination of Contract..................................................................................... 77
7.0 SCOPE OF WORK - CHANGES IN THE WORK ........................................ 79
7.1 Change Orders ................................................................................................... 79
7.2 Differing Site Conditions.................................................................................... 80
7.3 Resolution of Disputes ...................................................................................... 81
8.0 PAYMENT ................................................................................................... 83
8.1 Scope of Payment .............................................................................................. 83
8.2 Partial Payments ................................................................................................ 84
8.3 Partial Payments - Inclusion of Materials on Hand ....................................... 86
8.4 Right to Withhold Amounts ............................................................................... 87
8.5 Substantial Completion ..................................................................................... 92
8.6 Final Inspection, Notice of Completion and Payment .................................. 93
8.7 Warranty of Title ................................................................................................. 94
9.0 EXISTING UTILITIES .................................................................................. 94
9.1 General ................................................................................................................ 94
9.2 Notification and Location................................................................................... 94
9.3 Damage and Protection .................................................................................... 95
9.4 Utility Relocation and Rearrangement ............................................................ 95
SECTION 00800 ........................................................................................................... 97
SUPPLEMENTARY CONDITIONS ........................................................................... 97
SECTION 00810 ........................................................................................................... 98
MODIFICATIONS TO GENERAL CONDITIONS....................................................... 98
1.0 CONTRACT ADMINISTRATION ................................................................. 98
2.0 TIME ALLOWED FOR COMPLETION ........................................................ 98
3.0 DAMAGES FOR DELAYS ........................................................................... 98
4.0 WEATHER DAYS........................................................................................ 98
SECTION 00820 ........................................................................................................... 99
LIABILITY AND INSURANCE REQUIREMENTS ..................................................... 99
1.0 INDEMNIFICATION .................................................................................... 99
2.0 INSURANCE REQUIREMENTS ............................................................... 100
SECTION 01010 ......................................................................................................... 105
SUMMARY OF WORK ............................................................................................ 105
1.0 WORK COVERED BY CONTRACT .......................................................... 105
2.0 WORK SEQUENCE AND CONSTRAINTS ............................................... 105
3.0 OCCUPANCY REQUIREMENTS.............................................................. 105
4.0 CITY FURNISHED MATERIALS ............................................................... 105
5.0 TRENCH EXCAVATION ........................................................................... 105
6.0 WORK UNDER OTHER CONTRACTS..................................................... 106
7.0 CONTRACTOR'S WORK PERCENTAGE ................................................ 106
8.0 UNDERGROUND FACILITIES.................................................................. 106
SECTION 01025 ......................................................................................................... 107
v
This is the opportunity summary page. You are currently viewing an overview of this opportunity and a preview of the attached documentation. For more information, please visit the Publication URL Web page.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

Follow Simplifed Acquisition of Base Engineering Requirements (SABER) Unit Price Guide Software Active

Federal Agency

Bid Due: 12/20/2024

Follow USCGC BERTHOLF REPLACEMENT CIC DOOR Active Contract Opportunity Notice ID 70Z08524P0001371 Related

Federal Agency

Bid Due: 12/08/2024

Image SFO has an opportunity for you to join its successful concession program.

San Francisco International Airport

Bid Due: 5/08/2024

Bid Title: Qualified Contractors List Application Category: Capital Improvement Projects (CIP) Status: Open

City of Laguna Hills

Bid Due: 12/31/2024

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only as a convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.